Attachment 1: Permit Special Conditions
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
WORK LIMITS / NOTIFICATION
1. Work Limits: All work authorized by this permit shall be performed in strict compliance
with the following attached permit plans, which are a part of this permit:
a) Figure 3 – Detail Map (Sheets 1 - 137)
b) Snow Creek Wetland Mitigation Site Conceptual Plan (Sheets G-001 – G-603)
The Permittee shall ensure that the construction design plans for this project do not
deviate from the permit plans attached to this authorization. Any modification to the
attached permit plans must be approved by the U.S. Army Corps of Engineers (Corps)
prior to any active construction in waters or wetlands.
2. Unauthorized Dredge and/or Fill: Except as authorized by this permit or any Corps-
approved modification to this permit, no excavation, fill or mechanized land-clearing
activities shall take place at any time in the construction or maintenance of this project,
within waters or wetlands. This permit does not authorize temporary placement or
double handling of excavated or fill material within waters or wetlands outside the
permitted area. This prohibition applies to all borrow and fill activities connected with
this project.
3. Permit Distribution: The Permittee shall require its contractors and/or agents to comply
with the terms and conditions of this permit in the construction and maintenance of
this project and shall provide each of its contractors and/or agents associated with the
construction or maintenance of this project with a copy of this permit. A copy of this
permit, including all conditions and drawings shall be available at the project site during
construction and maintenance of this project.
4. Preconstruction Meeting: The Permittee shall conduct a preconstruction meeting
between their representatives, contractor’s representatives, and the appropriate U.S.
Army Corps of Engineers Project Manager prior to undertaking any work
within potentially jurisdictional waters and wetlands (except hand-felling trees) to
ensure that there is a mutual understanding of all terms and conditions contained
within the Department of the Army permit. The Permittee shall schedule the
preconstruction meeting for a time frame when the Corps, NCDEQ and VADEQ Project
Managers can attend. The Permittee shall invite the Corps, NCDEQ and VADEQ Project
Managers a minimum of thirty (30) days in advance of the scheduled meeting in order to
provide those individuals with ample opportunity to schedule and participate in the
required meeting. The thirty (30) day requirement can be waived with the concurrence
of the Corps.
5. Notification of Construction Commencement and Completion: The Permittee shall
notify the Corps in writing prior to beginning the work authorized by this permit and
again upon completion of the work authorized by this permit.
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
6. Reporting Address: All reports, documentation, and correspondence required by the
conditions of this permit shall be submitted to the following: U.S. Army Corps of
Engineers, Norfolk District, Special Projects Regulatory Section, Attn: Steven
VanderPloeg, at 804-397-9836 or Steven.A.Vanderploeg@usace.army.mil, and U.S.
Army Corps of Engineers, Wilmington District, Raleigh Regulatory Field Office,
Attn: Richard G Harmon, at 919-801-8990 or richard.g.harmon@usace.army.mil. The
Permittee shall reference the permit numbers NAO-2018-1574 and SAW-2018-00887 on
all submittals.
7. Permit Revocation: The Permittee, upon receipt of a notice of revocation of this permit
or upon its expiration before completion of the work will, without expense to the United
States and in such time and manner as the Secretary of the Army or his authorized
representative may direct, restore the water or wetland to its pre-project condition.
8. Reporting Violations: Violation of these permit conditions or violation of Section 404 of
the Clean Water Act shall be reported to the Corps in writing and by telephone at: 804-
397-9836 or Steven.A.Vanderploeg@usace.army.mil, and 919-801-8990 or
richard.g.harmon@usace.army.mil, within 24 hours of the Permittee’s discovery of the
violation.
9. Endangered Species Act: The Permittee shall implement all necessary measures to
ensure the authorized activity does not kill, injure, capture, harass, or otherwise harm
any federally listed threatened or endangered species. While accomplishing the
authorized work, if the Permittee discovers or observes an injured or dead threatened or
endangered species, the U.S. Army Corps of Engineers, Norfolk District, Special
Projects Regulatory Section, Attn: Steven VanderPloeg, at 804-397-9836
or Steven.A.Vanderploeg@usace.army.mil, and U.S. Army Corps of Engineers,
Wilmington District, Raleigh Regulatory Field Office, Attn: Richard G Harmon, at 919-
801-8990 or richard.g.harmon@usace.army.mil will be immediately notified to initiate
the required Federal coordination.
10. The permittee must adhere to the following requirements in accordance with the
special conditions from U.S. Fish and Wildlife Service:
a) Avoid tree clearing during active season (April 1 to September 30) within inner tier of
the northern long-eared bat (NLEB) known-use area from approximately milepost
(MP) 5.7 to MP 7.8.
b) Avoid building/structure removal / modification from April 1 to May 14 and August 1
to November 14.
c) Avoid blasting and HDD construction within inner tier of NLEB known-use area from
May 15 to July 31 (summer maternity season). Develop site specific blasting plans if
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
blasting is necessary within inner tier of NLEB to avoid the potential for adverse
effects.
11. National Historic Preservation Act: If the Permittee discovers any previously unknown
historic, cultural, or archeological remains and/or artifacts while accomplishing the
activity authorized by this permit, the Permittee must immediately notify the U.S. Army
Corps of Engineers, Norfolk District, Special Projects Regulatory Section, Attn: Steven
VanderPloeg, at 804-397-9836 or Steven.A.Vanderploeg@usace.army.mil, and U.S.
Army Corps of Engineers, Wilmington District, Raleigh Regulatory Field Office,
Attn: Richard G Harmon, at 919-801-8990 or richard.g.harmon@usace.army.mil, to
initiate the required Federal coordination. The Permittee must notify the Corps of what
has been found, and to the maximum extent practicable, avoid construction activities
that may affect the remains and artifacts until the required coordination has been
completed. If the discovery occurs within the Snow Creek PRM Site, the Corps will
initiate the Federal, Tribal, and state coordination required to determine if the items or
remains warrant a recovery effort or if the site is eligible for listing in the National
Register of Historic Places. If the discovery occurs elsewhere, coordination will proceed
in accordance with the Programmatic Agreement.
12. The permittee must implement the Approved Site Protection Plans that were
coordinated with the North Carolina State Historic Preservation Office to ensure that
any potential adverse effects to historic properties eligible for listing or listed in the
National Register of Historic Places (NRHP) are avoided. The Approved Site Protection
Plans include agreed-upon measures to avoid impacts to archaeological sites 31RK44,
31RK217, 31RK299, 31RK239 (unassessed for NRHP eligibility) and 31RK222 (NRHP
eligible). Should unanticipated discoveries occur during project construction, the
permittee shall implement the agreed-upon Plan for Unanticipated Discoveries of
Historic Properties and Human Remains for the MVP Southgate Project (revised
September 2021) that was coordinated with the NC SHPO.
13. Prior to any work at the Snow Creek PRM site, the boundaries of archeological resource
44FR0630, shall be clearly marked with safety fencing. All site plans for the area also
need to clearly mark the resource as an exclusion area. The safety fencing needs to
remain up for the duration of the project.
14. Temporary Impacts Restoration Measures: Within thirty (30) days of the date of
completing the authorized work, the Permittee shall remove all temporary fills in
potential waters of the US and restore the affected areas to pre-construction contours
and elevations. The affected areas shall be re-vegetated with regionally appropriate
native, non-invasive riparian vegetation to minimize erosion and ensure site stability.
15. Authorized temporary impacts to streams for the utility project component of this
project must be restored and stabilized according to the attached permit plans.
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
16. In wetland areas where utility installation via trenching is authorized, where practicable
wetland topsoil shall be segregated from the underlying subsoil, and the top 6 to 12
inches of the trench shall be backfilled with topsoil from the trench.
17. The Permittee must implement and adhere to the Mountain Valley Pipeline - Southgate
– Comprehensive Stream and Wetland Monitoring, Restoration, and Mitigation
Framework dated March 2026 and subsequently approved revisions thereto.
18. The Permittee must implement and adhere to the Implementation Plan dated January
2026 that is associated with the Federal Energy Regulatory Commission Order (Docket
No. CP25-60-000)
19. The permittee shall use an environmental compliance officer(s) experienced in stream
and wetland crossing methods and knowledgeable in federal and Virginia and North
Carolina environmental regulations, who will remain on-site throughout the
construction period. This individual must ensure compliance with all general and
specific Department of the Army, Virginia Department of Environmental Quality and
North Carolina Department of Environmental Quality permit conditions and
certifications. Once construction begins within crossings subject to this authorization,
compliance reports must be submitted to the Corps of Engineers, Norfolk District,
Virginia Department of Environmental Quality and North Carolina Department of
Environmental Quality on a bi-weekly basis, until construction within these areas is
complete.
RELATED LAWS
20. Maintain Flows and Circulation Patterns of Waters: Except as specified in the plans
attached to this permit, no excavation, fill or mechanized land-clearing activities shall
take place at any time in the construction or maintenance of this project, in such a
manner as to impair normal flows and circulation patterns within waters or wetlands or
to reduce the reach of waters and/or wetlands.
21. Fills Within 100-Year Floodplains: The activity must comply with applicable FEMA-
approved state or local floodplain management requirements.
22. Sediment and Erosion Control:
a. During the clearing phase of the project, heavy equipment shall not be operated in
surface waters or stream channels. Temporary stream crossings will be used to
access the opposite sides of stream channels. All temporary diversion channels
and stream crossings will be constructed of non-erodible materials. Grubbing of
riparian vegetation will not occur until immediately before construction begins on a
given segment of stream channel unless where necessary to install equipment
bridge crossing.
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
b. No fill or excavation impacts for the purposes of sedimentation and erosion control
shall occur within potentially jurisdictional waters, including wetlands, unless the
impacts are included on the plan drawings and specifically authorized by this
permit. This includes, but is not limited to, sediment control fences and other
barriers intended to catch sediment losses.
c. The Permittee shall remove all sediment and erosion control measures placed in
waters and/or wetlands, and shall restore natural grades on those areas, prior to
project completion.
d. The Permittee shall use appropriate sediment and erosion control practices and
stormwater management practices which equal or exceed those outlined in the
most recent versions of the (1) “North Carolina Sediment and Erosion Control
Planning and Design Manual” and “ Stormwater Design Manual”, which follows the
Minimum Design Criteria outlined in the NC Stormwater Rules and Regulations, and
(2) the “Virginia Stormwater Management Handbook” to ensure compliance with the
applicable water quality standard. Erosion and sediment control practices shall be
in full compliance with all specifications governing the proper design, installation
and operation and maintenance of such Best Management Practices in order to
ensure compliance with the applicable water quality standards. This shall include,
but is not limited to, the immediate installation of silt fencing or similar appropriate
devices around all areas subject to soil disturbance or the movement of earthen fill,
and the proper stabilization of all disturbed areas in accordance with the applicable
Virginia or North Carolina requirements. Additionally, the project shall remain in full
compliance with all aspects of the Virginia Erosion and Stormwater Management
Regulation (9 VAC 25-875, et seq.) and the Virginia Water Protection Permit Program
Regulation (9 VAC 25-210-10, et seq.) and the Sedimentation Pollution Control Act
of 1973 (North Carolina General Statutes Chapter 113A Article 4). Adequate
sedimentation and erosion control measures shall be implemented prior to any land
disturbing activities to minimize impacts to downstream aquatic resources. These
measures shall be inspected and maintained regularly, in accordance with the
applicable Virginia or North Carolina requirements. All fill material shall be
adequately stabilized at the earliest practicable date to prevent sediment from
entering into adjacent waters or wetlands.
23. Clean Fill: The Permittee shall use only clean material for this project. The discharge
material shall be free of items such as trash, construction debris, metal and plastic
products, and concrete block with exposed metal reinforcement bars. Soils used for fill
shall not be contaminated with any toxic substance in concentrations governed by
Section 307 of the Clean Water Act. Unless otherwise authorized by this permit, all
discharged material placed in waters or wetlands shall be generated from an upland
source.
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
24. Water Contamination: All mechanized equipment shall be regularly inspected and
maintained to prevent contamination of waters and wetlands from fuels, lubricants,
hydraulic fluids, or other toxic materials. In the event of a spill of a reportable quantity of
petroleum products or any other hazardous waste, the Permittee shall immediately
report it to the appropriate state environmental agency. For portions of the project
located in Virginia the permittee shall contact the Virginia Department of Environmental
Quality at (540) 562-6700, or brroprep@deq.virginia.gov. Within Virginia any spill of oil
as defined in § 62.1-44.34:14 of the Code of Virginia that is less than 25 gallons and that
reaches, or that is expected to reach, land only is not reportable, if recorded per § 62.1-
44.34:19.2 of the Code of Virginia and if properly cleaned up. For portions of the project
located in North Carolina the permittee shall contact N.C. Division of Water Resources
at (919) 733-3300 or (800) 858-0368 and provisions of the North Carolina Oil Pollution
and Hazardous Substances Control Act shall be followed.
AQUATIC LIFE
25. Aquatic Life Movement: No activity may substantially disrupt the necessary life cycle
movements of those species of aquatic life indigenous to the waterbody, including
those species that normally migrate through the area. All discharges of dredged or fill
material within waters of the United States shall be designed and constructed, except
as authorized as indirect impacts, to maintain low flows to sustain the movement of
aquatic species.
26. Prohibitions on Concrete: The Permittee shall take measures necessary to prevent live
or fresh concrete, including bags of uncured concrete, from coming into contact with
any water in or entering into waters of the United States. Water inside coffer dams or
casings that has been in contact with concrete shall only be returned to waters of the
United States when it no longer poses a threat to aquatic organisms (concrete is set
and cured).
COMPENSATORY MITIGATION
27. In order to compensate for impacts associated with this permit within the Wilmington
District regulatory boundary, mitigation shall be provided in accordance with the
provisions outlined on the most recent version of the attached Compensatory
Mitigation Responsibility Transfer Form. The requirements of this form, including any
special conditions listed on the form, are hereby incorporated as special conditions of
this permit.
28. You are responsible for meeting all the requirements of the PRM compensatory
mitigation plan associated with this permit authorization and the long-term
management of the compensatory mitigation project as outlined in the “Snow Creek
Mitigation Plan” dated March 12, 2026, and the plans titled “Snow Creek Wetland
Mitigation Site, Final Design” dated February 17, 2026 and received by this office on
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
March 18, 2026 . The Permittee is responsible for and must comply with the
Performance Standards and monitoring requirements as defined in the above
referenced documents. This responsibility can only be transferred if and when the
permit is transferred to another party and then only to the new permit recipient.
29. As compensation for permanent conversion impacts of 9.3855 acres of PFO and PSS to
PEM, permanent impact to 0.0362 acre PEM and for the temporal loss of wetland
function associated with 11.4713 acres of temporary wetland and wetland conversion
impacts associated with the pipeline construction portion of the MVP Southgate
Amendment Project, you will create 2.88 acres of PFO wetland, enhance 3.38 acres of
PEM wetland, and restore 5.11 acres of upland buffer as depicted on the compensation
plan entitled “Snow Creek Wetland Mitigation Site, Final Design” dated February 17,
2026, and received March 18, 2026. The PRM project will generate 4.75 wetland credits.
For the remaining wetland mitigation credit needs you must submit affidavit of credit
sales to this office prior to impacting wetlands above your current wetland mitigation
amount. The acreage of compensation for wetlands is based on the application of the
Norfolk District standard ratios (1:1 for wetland conversion) and the proposed ratios for
temporal loss proposed by the applicant.
30. You are required to notify the Corps 15 days prior to commencement of construction
of the PRM compensation site and you are required to follow the construction
sequence and timetable outlined in the Plan.
31. All PRM compensation construction must be completed prior to or concurrent with
project impacts in water of the U.S. including wetlands. You are required to submit an
accounting by December 1st of each year of the acres of wetlands impacted under this
permit the previous calendar year and the compensation activities performed the
previous calendar year. The impacts taken must not exceed the compensation
performed in any one calendar year.
32. You must record a legally binding real estate instrument (e.g. conservation easement or
declaration of restrictive covenants) in the chain of title for the PRM compensation
areas that will require the preservation of these lands (wetlands, stream channels, and
upland areas) on this property in perpetuity. You must submit the draft instrument to
this office for review and written approval prior to submittal for recordation. You must
submit proof of recordation to the Corps within 60 days of issuance of this permit. You
will install and maintain signage at the waters (including wetlands)/upland boundary of
the compensation area to advise future land disturbers of the deed restriction.
The permittee will submit language for the signage to this office for review and written
approval within 30 days of start of construction of the PRM site.
33. You must finalize the Long-Term Management Plan (LTPM), to include signatures for all
parties who are signatories to the LTMP within 60 days of issuance of this permit.
NAO -2018-1574 and SAW-2018-00887 Permit Special Conditions:
33. You must submit drawings accurately depicting the location and extent of the mitigation
activities occurring within the PRM site to this office within 15 days of the
commencement of construction of the PRM site. Those mitigation actions include, but
are not limited to, approximately 2.88 acres of wetland creation, 3.38 acres of wetland
enhancement, and 5.11 acres of upland buffer reforestation. Each area of preservation
area shall be labeled as “preservation area”.
34. As stated in the Project Narrative the Barn Group is responsible for the long-term
management of the PRM compensatory mitigation project. Any deviation from this long
term management plan must be approved by the Corps of Engineers.
35. The PRM Long-Term Management Fund (LTMF) will be funded through a single lump sum
payment of $129,591.43 upon construction, to be held in trust for the long-term,
perpetual management, maintenance, and monitoring of the Snow Creek Permittee
Responsible Mitigation Site, in accordance with the Final Mitigation Work Plan (FMWP),
the Site Development Plan/Mitigation Work Plan, the Long-Term Management Plan, and
the associated Long-Term Management Funding Table of the costs of perpetual long-
term management of the PRM Site.
36. At no time may you impact more wetlands than you have purchased wetland mitigation
credits for in addition to the credits generated from the Snow Creek Mitigation Site. A
detailed accounting of all wetlands impacts that have been taken shall be submitted to
this office with the bi-weekly construction reports until all the required mitigation
credits for the project have been purchased.