HomeMy WebLinkAboutNCWRC_Comments-Letter Response 202510252200 Energy Drive | Canonsburg, PA 15317
833-MV-SOUTH | mail@mvpsouthgate.com
www.mvpsouthgate.com
October 24, 2025
Samantha Wooten
401 & Buffer Permitting Branch
North Carolina Department of Environmental Quality
Division of Water Resources
512 North Salisbury Street
Raleigh, NC 27699
Dicky Harmon
Regulatory Specialist, Raleigh Field Office
U.S. Army Corps of Engineers – Wilmington District
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
RE: Response to North Carolina Wildlife Resources Commission
Environmental Review Comments and Recommendations
Mountain Valley Pipeline, LLC – MVP Southgate Amendment Project
DWR #20181638 v4
Dear Ms. Wooten and Mr. Harmon:
Mountain Valley Pipeline, LLC (Mountain Valley) submits the enclosed responses to the North Carolina
Wildlife Resources Commission (NCWRC) comments and recommendations dated September 12,
2025, regarding the 401 Individual Water Quality Certification application for the MVP Southgate
Amendment Project.
NCWRC Comment No. 1:
We have concerns about the increase in environmental disturbance to aquatic and terrestrial resources
because of overlapping or similar construction periods and locations with other pipeline projects. Impacts
include increased sedimentation, turbidity, erosion and the disruption of wildlife behavior due to noise,
lights, pollution, water withdrawal, and habitat loss.
Mountain Valley Response to Comment No. 1:
As an initial matter, the Amendment Project does not present a risk of appreciable impacts. The
Amendment Project’s minimal potential effects associated with each of the impact types identified in the
NCWRC’s comment are detailed extensively in the Environmental Assessment and Mountain Valley’s
Biological Assessment (BA). Specifically regarding sedimentation, turbidity, and erosion, Mountain
Valley completed conservative suspended sediment modeling to identify any stream reaches that
reasonably could be expected to experience an increase in sediment concentration and sediment
deposition from the Amendment Project. As discussed in the BA, notwithstanding the conservative
nature of that modeling, the model showed that the Amendment Project is not expected to cause an
impactful sediment concentration or result in appreciable sediment deposition in any stream. As a result,
the Amendment Project is not reasonably anticipated to contribute sediment from upland construction
activities to any stream segments in North Carolina sufficient to adversely affect aquatic species.
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 2
The “overlapping” construction schedules for the Amendment Project and other projects do not present
a material risk of cumulative impacts, including to streams crossed by multiple projects. The dry ditch,
open cut crossing method is a mature practice. Instream impacts from the use of this crossing method
are generally limited in both duration and area.
The primary effects associated with temporary instream work—increases in suspended particulates and
turbidity levels—generally dissipate within one to four days. Suspended particulate and turbidity levels
in the water column attenuate not only with time but also with distance. Elevated suspended particulate
and turbidity levels in the water column tend to approach background levels within a few hundred feet
downstream of a crossing.
To create the potential for additive, synergistic, antagonistic, or other cumulative effects on water quality
in a stream crossed by multiple projects, the parties’ respective crossings would have to be completed
roughly contemporaneously (within the span of a few days) and at locations no more than a few hundred
stream-feet apart. That scenario is highly unlikely. First, many of the projects’ crossings of common
streams are much farther apart. Second, the instream work for an open cut crossing typically lasts only
a few days, and these crossings will be installed over the course of approximately one year. Even if the
overall construction schedules align, it is very unlikely that the Amendment Project and other known
project proponents will happen to cross the same stream at the same time.
In the unlikely event that the Amendment Project and other project proponents commence open cut
crossings of a single stream at the same time, the magnitude of the potentially “cumulative” short-term
effect on water quality will be minimal. The increase in turbidity levels downstream from an open cut
crossing is “small and considered to be minimal compared to increased turbidity associated with natural
runoff events.” Given that the increase in turbidity levels downstream from a single open cut crossing
would be less than the increase that would be expected from a natural runoff event, and given the wide
range of storm intensities that cause runoff events, it is reasonable to conclude that the additive effect
of open cut crossings would not produce turbidity levels that are outside the wide range of natural
variability. It is also reasonable to assume that even the “worst-case” conditions resulting from
simultaneous crossings of the same stream would return to normal within one to four days.
Nevertheless, Mountain Valley is coordinating with other known project proponents to minimize the
potential for cumulative impacts and other issues during construction. Mountain Valley will implement
the following measures for this purpose:
Construction Scheduling Coordination
Mountain Valley is actively conferring with Transcontinental Pipe Line Gas Company, Inc. (Transco) on
its Southeast Expansion Project (SSEP) to coordinate and stagger construction activities within shared
workspaces. Where practicable, Mountain Valley and Transco may utilize the same crew to perform
certain work activities for both projects in areas that utilize the same workspaces. This approach is
intended to minimize simultaneous earth-disturbing activities in close proximity, thereby reducing the
potential for compounded sedimentation and turbidity impacts to aquatic resources.
Enhanced Erosion and Sediment Controls (ESCs)
In addition to the measures outlined in the Question #4b response, Mountain Valley will deploy
enhanced ESCs at stream crossings and sensitive areas. The following measures will also be shown
on the site-specific ESC plans that will be submitted to NCDEQ-DEMLR.
a. Reinforced or enhanced ESCs, where appropriate. For example, super silt fence or triple-stack
compost filter sock;
b. Rapid stabilization techniques (e.g., hydroseeding, erosion control blankets). These measures
will be maintained and monitored throughout construction to ensure effectiveness.
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 3
Contingency Planning and Adaptive Management
Mountain Valley will be prepared to deploy supplemental ESC measures and implement temporary
remediation if cumulative impacts are observed. Adaptive management strategies will be employed
based on field conditions. Such measures will be developed with the involvement of the construction
crew and Mountain Valley’s Environmental Inspectors.
Agency Coordination and Reporting
Mountain Valley will provide regular updates to the North Carolina Department of Environmental Quality
(NCDEQ) on construction progress and ESC performance. This will include documentation of
coordination efforts with other projects to demonstrate proactive management of cumulative impacts.
NCWRC Comment No. 2a:
We understand that MVP has minimized its effects to forested areas to the extent practicable (Section
4.4.1); however, we recommend aligning the pipeline and/or roads in some locations to further minimize
forest fragmentation, specifically riparian forests, with the highest areas of concern noted below.
Figure 3: Detailed Map, Page 63, CL-063 – Consider moving the extended workspace near NC Highway
70 into the pasture/existing ROW.
Mountain Valley Response to Comment No. 2a:
The extended workspace or ATWS (additional temporary workspace) on the northeastern side of
Highway 70 must be positioned close to the road to store the bore equipment and spoil materials as the
site is prepped for the road bore crossing. Additionally, the ATWSs on the southwestern side of the road
are positioned to store equipment and materials directly associated with the road bore crossing while
avoiding overlap with an active adjacent pipeline right-of-way.
NCWRC Comment No. 2b:
Figure 3: Detailed Map, pg. 68, CL-068– Consider moving the workspace adjacent to W-B052a
(crossing #094) to outside the riparian forested area, or if possible, into the existing ROW.
Mountain Valley Response to Comment No. 2b:
The ATWSs on both sides of crossing #094 are strategically placed to facilitate the dry-ditch open-cut
crossing of the aquatic resources. These areas must be close to the crossing to make the extra
workspace useful for the crews conducting the stream crossing. The workspaces are also positioned to
avoid overlapping with an active adjacent pipeline right-of-way.
NCWRC Comment No. 2c:
Figure 3: Detailed Map, pg. 69, CL-069– Consider moving the workspace adjacent to S-B008 on the
other side of the pipeline ROW. We also recommend moving the pipeline ROW closer to the existing
ROW to minimize the area of forest that will be fragmented.
Mountain Valley Response to Comment No. 2c:
The ATWS is strategically positioned close to the start of the bore in order to store the additional
equipment and materials needed to install and implement a horizontal directional drill (HDD) crossing of
the Dan River. The workspace was also positioned to avoid overlapping an active adjacent pipeline
right-of-way.
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 4
NCWRC Comment No. 2d:
We recommend co-locating the road (TA-RO-080A) and ROW, if possible.
Mountain Valley Response to Comment No. 2d:
Temporary access road TA-RO-080A was positioned per a landowner's request to avoid the crop area
of the field. Because the right-of-way will be drilled under with the Dan River HDD, there is no planned
disturbance required in this section of right-of-way. Therefore, co-locating the road with the right-of-way
would not decrease the amount of forested clearing but rather simply change the location of the trees
cut.
NCWRC Comment No. 3:
Clearly mark wetlands that will be avoided to prevent accidental impacts by construction crews. Conduct
manual clearing of vegetation in wetlands and disallow the use of heavy, tracked equipment. Leave
vegetation where it falls rather than using heavy equipment to remove trees and other downed
vegetation, which can further damage wetlands. Clearly mark the boundary for hand clearing.
Mountain Valley Response to Comment No. 3:
Mountain Valley will employ its construction contractor with oversight from Mountain Valley’s
environmental team, who will clearly mark the Amendment Project construction right-of-way with aquatic
resource signage to help ensure that contractors do not accidentally remove more trees or cause
inadvertent impacts to wetland and waterbody resources over and above those that were included as
part of its regulatory permits and documentation when manually clearing aquatic within resources.
NCWRC Comment No. 4a:
Section 4.4.13 Water Quality: We have concerns with the potential water quality impacts associated
with the in-stream construction. MVP cites literature indicating that the increased sedimentation from
open-cut crossings would be “mostly” short-term and remain near the crossing location (i.e., a few
hundred feet); however, many of these streams have already or will be impacted by other pipeline
projects. Extensive research has been conducted on the negative impacts of sediment and turbidity on
aquatic resources, including various time scales and extent of impacts. Impacts on aquatic species
include habitat degradation, suffocation of eggs, respiratory and physiological stress, clogging of gills,
and reduced food sources. To minimize impacts on aquatic species, particularly with threatened and
endangered species downstream of some crossings, we recommend at least the following:
Open-trench crossings have been found to increase the likelihood for future lateral movement of the
stream (which could undercut or erode around the utility line), and the correction of such problems could
result in costly future maintenance and devastating impacts to natural resources. Therefore, as much
work as possible should be accomplished in the dry, and the amount of disturbance should not exceed
what can be successfully stabilized by the end of the workday. In-stream work should consider
forecasted high-flow events.
Mountain Valley Response to Comment No. 4a:
Please see response to Mountain Valley’s Responses to Comment No. 1. Mountain Valley will conduct
all open-cut stream crossings utilizing a dry ditch method. Weather forecast and potential for high-flow
events are evaluated prior to the start of and during stream crossings. After construction, the bed and
banks are restored to preconstruction contours, and the stream substrate is replaced so that the stream
can rapidly return to its preconstruction function. To facilitate successful restoration of streams, the top
1 foot of the streambed substrate (armoring layer) will be segregated and stockpiled separately from
subsoils. Following pipe installation, normal backfill cover requirements will be met. Only materials
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 5
native to the waterbody will be used. Compaction percentage of backfill will be equal to or above that of
the adjacent undisturbed areas. Trench breakers of clay, earthen fill, sand, or concrete-filled sacks may
also be used to keep backfill from sloughing in toward the center of the stream and to prevent the
pipeline bedding material from acting as a French drain. Stream banks will be restored to preconstruction
contours; restored stream bed substrate patterns, profiles, dimensions, and embeddedness will be
similar to preconstruction conditions using native material excavated at stream crossings, and foreign
objects will be removed from the stream. Excavated material not required for backfill will be removed
and disposed of at an upland site.
In addition, Mountain Valley plans to use a trenchless crossing for both the Dan River and Cascade
Creek to avoid the potential for impacts to threatened and endangered aquatic species from instream
construction.
NCWRC Comment No. 4b:
Erosion and sediment control measures should conform to the High Quality Water Zones standards
stipulated in the NC Department of Environmental Quality Erosion and Sediment Control Plan
(https://deq.nc.gov/about/divisions/energy-mineral-land-resources/energy-mineral-land-permit-
guidance/erosion-sediment-control-planning-design-manual). Sediment and erosion control measures
should use advanced methods and installed prior to any land-disturbing activity.
Mountain Valley Response to Comment No. 4b:
Although the Amendment Project does not cross through a High Quality Water (HQW) Zone, the project
will implement erosion and sediment control measures that will provide protections suitable for HQW
Zones. The following advanced measures are examples of controls that may be installed prior to any
land-disturbing activity and maintained throughout construction:
Perimeter and Runoff Controls
• Super silt fence
• Double rows of silt fence or wattle lines
• Diversion berms/waterbars and dikes
• Stabilized construction entrances
Slope Stabilization
• Hydroseeding with mulch and tackifier
• Erosion control blankets
• Temporary slope drains with riprap outlet protection
Sediment Trapping & Treatment
• Check dams (stone or wattles)
Post-Construction Stabilization
• Permanent seeding including native species
• Riprap armoring at outfalls and channelized flow areas
• Stormwater BMPs (after going through the appropriate regulatory review)
NCWRC Comment No. 4c:
The natural dimension, pattern, and profile of the streams above and below the stream crossing should
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 6
not be modified, including the width and depth of the stream channel. Consider using state-of-the-art
natural channel design and restoration techniques, including instream structures to minimize bank
erosion. We prefer natural materials such as coir fiber rolls, biodegradable erosion-control blankets, and
vegetation instead of riprap where practical.
Mountain Valley Response to Comment No. 4c:
Preconstruction elevations, contours, ordinary high-water mark, photos, and other existing information
will be used to ensure post-construction restoration restores the crossings back to the pre-crossing
condition or to a stable configuration. If the stream is experiencing significant bank erosion or other
unstable conditions (i.e., vertical bank), stream restoration practices will ensure the post-construction
area will be restored to a stable configuration based on the preconstruction contours and site
conditions. Natural materials will be used in these situations to the extent practicable.
NCWRC Comment No. 4d:
Monitoring is recommended to ensure successful channel and bank stabilization and vegetation growth,
especially since state and federal threatened and endangered species occur in the project area. Native
vegetation and bioengineered structures should be used for stream stabilization where possible.
Invasive species control should occur regularly, including prior to construction if present. Invasive
species outcompete native plants and provide minimal benefit to wildlife. Monitoring the site should
occur once per year during the growing season for three years or three bankfull events.
Mountain Valley Response to Comment No. 4d:
The restoration and monitoring of wetland and waterbody crossings will be conducted in accordance
with FERC’s “Wetland and Waterbody Construction and Mitigation Procedures” and Mountain Valley’s
Mitigation Framework. The Mitigation Framework is a voluntary plan that offers a comprehensive
approach for ensuring that temporary impacts to streams and wetlands are successfully restored to their
preconstruction conditions. Upland areas will be monitored for revegetation in accordance with the
FERC “Upland Erosion Control Revegetation and Maintenance Plan.” All these documents provide
vegetative monitoring and provisions for the monitoring of invasive species. Additionally, Mountain
Valley will adhere to its “Exotic and Invasive Species Control Plan,” which also provides the
methodologies for monitoring and control of invasive species throughout the construction right-of-way.
Finally, Mountain Valley plans to use a trenchless crossing for both the Dan River and Cascade Creek
to avoid the potential for impacts to threatened and endangered aquatic species from instream
construction activities.
NCWRC Comment No. 5:
Tricolored bats (Perimyotis subflavus) are documented in Rockingham County. Tricolored bats are a
state endangered species. Therefore, we recommend not clearing trees during critical periods of
vulnerability for bats, specifically pup rearing months (April 15-July 31) but also the coldest days within
the winter months (December 15 to February 14).
Mountain Valley Response to Comment No. 5:
Because the U.S. Fish & Wildlife Service (USFWS) has proposed listing the tricolored bat as an
endangered species under the ESA, Mountain Valley is coordinating with FERC and USFWS to address
potential impacts to the species under Section 7(a)(4) of the ESA. Among other things, Mountain Valley
has incorporated a variety of impact avoidance and minimization measures into the Amendment Project
and is preparing to submit a detailed Biological Evaluation to FERC and USFWS, analyzing potential
effects.
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 7
NCWRC Comment No. 6a:
MVP intends to withdraw 1,853,000 gallons of water from the Dan River. The following are comments
on the water withdrawal:
The water intake screen system must be incorporated into the intake design to minimize entrainment
and impingement of eggs, larvae, and juveniles. This includes a maximum intake velocity of 0.25 ft/sec
through a mesh or slotted surface with openings not to exceed 1.0 millimeter. Methodology to clean the
screen system must also be designed and discussed to minimize impacts to eggs, larvae, and juveniles.
Mountain Valley Response to Comment No. 6a:
If approved by the USFWS, Mountain Valley will withdraw water from the Dan River for hydrostatic
testing of the pipeline, HDD operations at the Dan River and Sandy River, and dust suppression
activities. Municipal water sources will be used as a secondary supply, if necessary. A total of
approximately 3,300,000 gallons of water will be used for hydrostatic testing, and an estimated
1,853,000 gallons will be required for HDD drilling operations. During dry weather conditions,
approximately 30,000 gallons of water per day may be needed for dust control.
Mountain Valley will implement the following measures during the use of the Dan River as a water
source for hydrostatic testing, dust suppression, and to facilitate the HDD:
• Use of a temporary and floating intake structure.
• Suspension of the intake well above functional substrates, preferably placed in an area >5 feet
water depth that is unsuitable for the occupation of federally listed and state listed aquatic
species (e.g., unconsolidated and shifting sand substrates).
• Adherence to time-of-year restrictions to protect sensitive fish and mussels in the Dan River from
May 15 – July 31.
• Use of holding tanks to facilitate withdrawing water over a longer period.
• Maintain minimum pass-by flows (<10% of instantaneous riverflow).
• Achieve a through-screen approach velocity less than 0.25 foot per second with a 1.0 mm mesh
screen.
• No permanent instream infrastructure will be installed.
Screen cleaning will be incorporated as part of standard operating procedures and will follow industry
standards and the manufacturer’s recommendations for method and frequency. In general, manual
cleaning of the screens would involve shutting down the intake, removing the screen, and brushing or
washing off any debris.
NCWRC Comment No. 6b:
The intake structure should be marked in a manner that will reduce hazards to navigation.
Mountain Valley Response to Comment No. 6b:
Mountain Valley will mark the location of the intake structure, which will be placed in a location
downstream from the pipeline crossing.
NCWRC Comment No. 6c:
Water withdrawals should occur in the winter months and especially not from April-July or if there is a
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 8
drought. The maximum withdrawal amount from any stream is 20% of the 7Q10 flow. For the Dan River,
the NCWRC estimated that 20% of the 7Q10 for the Dan is about 14.9 cfs (9.6 million gallons per day).
Mountain Valley Response to Comment No. 6c:
Noted. Mountain Valley will adhere to the time-of-year restriction of May 15 – July 31 and will comply
with not exceeding 20% of the 7Q10 flow limit.
NCWRC Comment No. 7:
We appreciate MVP minimizing the degradation of habitat by implementing invasive species
management practices by revegetating disturbed areas with weed-free seed mixes (Section 4.3.26).
Please ensure those seed mixes are of native species found within Rockingham County. This should
include the replacement of native vegetation not only in riparian and wetland areas, but also upland
areas in areas not bound by agreements with landowners. Use a grain, such as oats, wheat, or rye for
temporary cover and native seed mixes for permanent seeding throughout the project. We recommend
integrating some flowering herbaceous species (i.e., goldenrod, tickseed, and beebalm) to create
pollinator habitat within the project boundary. Please note that we do not recommend seeding with tall
fescue, Kobe lespedeza, sericea lespedeza, Sudangrass or Kentucky bluegrass even though NC
Department of Environmental Quality has these species on their seeding specifications.
Mountain Valley Response to Comment No. 7:
The riparian and wetland seed mixes used for the Amendment Project will consist primarily of native
species and will be specified on the erosion and sediment control plans. Mountain Valley’s
environmental personnel will review and consider the list of native seed alternatives provided by
NCWRC during development of upland seeding specifications.
NCWRC Comment No. 8:
Erosion control matting made of plastic mesh or twine should not be used in the project area, including
in uplands, because it can injure or kill wildlife.
Mountain Valley Response to Comment No. 8:
Mountain Valley will minimize the use of erosion control matting that incorporates plastic mesh/twine
along streambanks or within wetland areas to the greatest extent practicable.
Regards,
Jeffrey Klinefelter
Mountain Valley Pipeline, LLC
cc: Christian King, Burns & McDonnell Engineering Company, Inc.
Lori Ferry, Burns & McDonnell Engineering Company, Inc.
John Tessier, NextEra Energy
Olivia Munzer, NCWRC
Samantha Wooten
Dicky Harmon
October 17, 2025
Page 9
Vann Stancil, NCWRC