HomeMy WebLinkAbout20181638 Ver 4_Table 11_Bore-Crossing_Cost_20250530Table 11- Bore Crossing Method Cost
Individual Permit Application
MVP Southgate Amendment Project
Trenchless Method Activity (Units Indicated)
Trenchless Crossing Costs
Bore Pit Setup <- 20 feet ($/ft) a/
$4,567
Bore Pit Setup > 20 feet ($/ft) a/
$9,135
Bore Pit Setup 30 to 40 feet ($/ft) a/
$18,269
Conventional Bore ($/ft) b/
$1,460
Sandy River HDD ($) c/
$4,905,438
Dan River HDD ($) c/
$2,944,876
a/ Bore pit setup costs taken from MVP Mainline costs to construct.
b/ Conventional bore cost taken from contractor bids on MVP Southgate scope of work
received in December 2024.
c/ HDD costs taken from contractor bids on MVP Southgate scope of work received in
December 2024.