HomeMy WebLinkAbout20181638 Ver 4_Table 11_Bore-Crossing_Cost_20250530Table 11- Bore Crossing Method Cost Individual Permit Application MVP Southgate Amendment Project Trenchless Method Activity (Units Indicated) Trenchless Crossing Costs Bore Pit Setup <- 20 feet ($/ft) a/ $4,567 Bore Pit Setup > 20 feet ($/ft) a/ $9,135 Bore Pit Setup 30 to 40 feet ($/ft) a/ $18,269 Conventional Bore ($/ft) b/ $1,460 Sandy River HDD ($) c/ $4,905,438 Dan River HDD ($) c/ $2,944,876 a/ Bore pit setup costs taken from MVP Mainline costs to construct. b/ Conventional bore cost taken from contractor bids on MVP Southgate scope of work received in December 2024. c/ HDD costs taken from contractor bids on MVP Southgate scope of work received in December 2024.