HomeMy WebLinkAbout20181638 Ver 4_Table 09_State_Federal-Permits_20250530Table 9 - State and Federal Permit Status
Individual Permit Application
MVP Southgate Amendment Project
Federal
Anticipated Submittal/
Anticipated Permit Receipt/
Authorization or Approval a/
Agency
Initiation Date
Completion Date
Natural Gas Act, Section 7; Amendment Certificate
for construction and operation of interstate natural
Federal Energy Regulatory Commission
Feb-25
Dec-25
gas pipeline b/
Individual Section 404 Permit for impacts on
U.S. Army Corps of Engineers (USAGE)
Apr-25
May-26
waters of the U.S., including wetlands
Consultation under Section 7 of the Endangered
Species Act for potential impacts on federally
U.S. Fish and Wildlife Service
May-25
Mar-26
protected species
Virginia
Anticipated Submittal/
Anticipated Permit Receipt/
Authorization or Approval a/
Initiation Date
Completion Date
Consultation and clearance regarding potential
impacts on pre -historic and historic resources
Virginia Department of Historic Resources (VDHR),
Aug-24
Received Mar-25
eligible for listing on the National Register of
Division of Review and Compliance c/
Historic Places (NRHP)
Individual Section 401 Water Quality Certification
Virginia Department of Environmental Quality
Apr-25
Dec-25
and Water Protection Permit
(VA DEQ), Water Division
Standards and Specifications for the discharge of
VA DEQ, Water Division
In effect d/
Complete d/
construction stormwater
General Permitfor Utility Line Encroachments
Virginia Marine Resources Commission
Apr-25
Dec-25
Consultation for state -threatened and endangered
Virginia Department of Conservation and Recreation,
plant and insect species and other state-
Jul-24
Mar-25
Division of Natural Heritage
designated "Natural Heritage" resources
Consultation for state -threatened and endangered
Virginia Department of Wildlife Resources, Wildlife
Jul-24
Mar-25
animal and aquatic species
and Environmental Services Division
[fBD]
[fBD]
Road bonds and crossing permits
Virginia Department of Transportation
Prior to construction
Prior to construction
North Carolina
Anticipated Submittal/
Anticipated Permit Receipt/
Authorization or Approval a/
Agency in
Initiation Date
Completion Date
llo,dividuaoL401 Water Quality Certification,
North Carolina Department of Environmental Quality
May-25
Dec-25
sated/nn-404wetlandsand water permit
(NC DEQ), Division of Water Resources
General Permit NCG010000 to discharge
NC DEQ, Division of Energy, Mineral and Land
stormwater under the National Pollutant Discharge
May-25
Aug-25
Resources
Elimination System for Construction Activities
Consultation for state -threatened and endangered
NC DEQ, Natural Heritage Program
Jul-24
Mar-25
species
Consultation for state -threatened and endangered
North Carolina Wildlife Resources Commission
Dec-24
Mar-25
species
Consultation and clearance regarding potential
North Carolina Historic Preservation
impacts on pre -historic and historic resources
Aug-24
Feb-25
Office (NC HPO) c/
eligible for listing on the NRHP
[rBD]
[fBD]
Road bonds and crossing permits
North Carolina Department of Transportation
Prior to construction
Prior to construction
a/ Consultations will occur continuously throughout the development of the Amendment Project.
b/ FERC. 2020.171 FERC 161,232 Order Issuing Certificate re Mountain Valley Pipeline, LLC underCP19-14 (FERC eLibrary Accession Number 20200618-3159).
c/ FERC developed a Programmatic Agreement (PA) forthe Original Certificated Project, in consultation with the USACE, VDHR, NC HPO, and other parties to resolve adverse effects to
affected historic and cultural properties in accordance with 36 CFR g 800.14(b)(3). The PAwas executed on May 17, 2020, and is proposed to be renewed forthe Amendment Project.
d/ The Standards and Specifications previously approved by VA DEQ for the Mountain Valley Pipeline mainline also govern the Amendment Project.
TBD =to be determined