Loading...
HomeMy WebLinkAboutNCC240488_ESC Approval Submitted_20240221 ROY COOPER fi ,:ii8p " Governor '�'' ELIZABETH S.BISER _� ,� Secretary �`` c6 WILLIAM E.TOBY VINSON,JR NORTH CAROLINA Interim Director Environmental Quality November 15,2023 LETTER OF APPROVAL Fayetteville Public Works Commission ATTN: Misty M. Manning P.O. Box 1089 Fayetteville,NC 28302 RE: Project Name: Big Rockfish Creek Outfall—Contract 2 Acres Approved: 17.28 Project ID: CUMBE-2024-051 County: Cumberland, City: Fayetteville, Address: SR 3399/3373/4164& 1003 River Basin: Cape Fear Stream Classification: Other Submitted By: McKim &Creed, Inc.(Mark Fisher, PE) Date Received by DEMLR: October 17, 2023 Plan Type: New—Utility/Infrastructure Dear Ms. Manning: This office has reviewed the subject erosion and sedimentation control plan and hereby issues this Letter of Approval. This plan approval shall expire three (3) years following the date of approval, if no land- disturbing activity has been undertaken, as is required by Title 15A NCAC 4B .0129. Should the plan not perform adequately, a revised plan will be required(G.S. 113A-54.1)(b). As of April 1,2019,all new construction activities are required to complete and submit an electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000 Construction General Permit. After the form is reviewed and found to be complete,you will receive a link with payment instructions for the$100 annual permit fee. After the fee is processed,you will receive the COC via email. As the Financially Responsible Party shown on the FRO form submitted for this project,you MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI form may be accessed at deq.nc.gov/NCGO1. Please direct questions about the NOI form to the Stormwater Program staff in the Raleigh Central Office. After you submit a complete and correct NOI Form,a COC will be emailed to you within three business days. A$120 fee will be charged annually until a Notice of Termination is issued. This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. If the owner/operator of this project changes in the future,the new responsible party must obtain a new COC. Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on file at the job site: 1. The approved E&SC plan as well as any approved deviation. 2. The NCGO 1 permit and the COC, once it is received. 3. Records of inspections made during the previous 12 months. North Carolina Department of Environmental Quality I Division of Energy,Mineral and land Resources `�fJ rayetteville Regional Office 225 Green Street.Suite 714 Fayetteville.North Carolina 28301 ,,OR*,,c:,axi IA Departsnent Or Enrilaunentalam+� 910.433.3300 Letter of Approval Fayetteville Public Works Commission November 15,2023 Page 2 of 2 Also,this letter gives the notice required by G.S. 113A-61.1(a)of our right of periodic inspection to ensure compliance with the approved plan. North Carolina's Sedimentation Pollution Control Act is performance-oriented, requiring protection of existing natural resources and adjoining properties. If, following the commencement of this project, it is determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this office may require revisions to the plan and implementation of the revisions to ensure compliance with the Act. Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land-disturbing activity.This approval does not supersede any other permit or approval. Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility Form,which you provided.You are requested to file an amended form if there is any change in the information included on the form. This permit allows for a land-disturbance, as called for on the application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit and would require a revised plan and additional application fee.In addition,it would be helpful if you notify this office of the proposed starting date for this project. Your cooperation is appreciated. Sincerely, r Chris Baker Environmental Engineer DEMLR Enclosures: Certificate of Approval NPDES NCGO 1 Fact Sheet ec: Mark Fisher,McKim &Creed Byron Reeves, City of Fayetteville Inspections cc: DEMLR- Fayetteville Regional Office