HomeMy WebLinkAboutNCC233320_ESC Approval Submitted_20231108 Iredell County Planning & Development
1--) Erosion Control Section
I R E D E L L 349 North Center Street
COU P.O. Box 788
Statesville, NC 28687
Date: October 31512023
LETTER OF APPROVAL WITH MODIFICATIONS
Thomas M. Fitts Jr.
Fitts and Goodwin, Inc.
200 Cascade Pointe Ln., Ste. 101
Cary,NC 27513
RE: Project Name: Watertech Inc. Distribution Facility
Acres Approved with Modifications: 12.94
Project ID: STVLE-2024-023
Project Location: PIN 4715972538.000
Submitted By: Fitts and Goodwin, Inc.
Date Received: October 1011' 2023
Plan Type: New
Dear Mr. Fitts:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable with modifications and herby issue this Letter of Approval with Modifications.
Modifications must be received in this office no later than two weeks prior to the project start
date. Failure to submit modified plans can result in a violation and fine under the Iredell County
Land Development Code. The Modifications required for Approval are listed on the attached
page. The Certificate of Approval issued by Iredell County must be posted at the job site. This
plan approval shall expire three (3) years following the date of this approval as is required by
Title 15A NCAC 4B.0129 and Appendix H of the Iredell County Land Development Code.
Title 15A NCAC 4B 0118(a) and Appendix H of the Iredell County Land Development Code
requires that a copy of the approved erosion control plan be on file at the job site. Any
amendments and/or revisions to the approved plan must be reviewed and approved prior to
implementation in order for the site to remain in compliance. Failure to submit plans for approval
may result in administrative actions and/or penalties as indicated in the Iredell County Land
Development Code. Also, this letter gives notice as required by G.S. 113A-61.1(a)and Appendix
H of the Iredell County Land Development Code, of our right of periodic inspection to insure
compliance with the approved plan.
Iredell County's Sedimentation Pollution Control Program is performance-oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
Letter of Approval with Modifications
Watertech Inc. Distribution Facility
October 31512023
Page 2 of 3
commencement of this project, it is determined that the erosion and sedimentation control plan is
inadequate to meet the requirements of the Iredell County Land Development Code and the
Sedimentation Pollution Control Act of 1973, (North Carolina General Statute 113A-51 through
66), this office may require revisions to the plan and implementation of the revisions to insure
compliance with the Act and Code.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances or
rules may also apply to this Iand-disturbing activity. This approval does not supersede any other
permit or approval. It is the responsibility of the applicant to obtain all other required permits or
approvals.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the
NCG010000 Construction General Permit. After the form is reviewed and found to be complete,
you will receive a link with payment instructions for the applicable annual permit fee. After the
fee is processed, you will receive the COC via email. As the Financially Responsible Party
shown on the FRO form submitted for this project, you MUST obtain the COC prior to
commencement of any land disturbing activity. The eNOI form and fee details may be accessed
at deq.nc.gov/NCGOI. Please direct questions about the eNOI form to the Stormwater Program
staff in the Raleigh central office. If the owner/operator of this project changes in the future,the
new responsible party must obtain a new COC.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form
if there is any change in the information included on the form. In addition, it is required that this
office to be notified of the proposed starting date for this project. Failure to notify this office of
the starting date may result in a Notice of Violation and civil penalty. As required in the
approved plan construction sequencing, please schedule a preconstruction conference with our
staff prior to land disturbing activity.
Your cooperation is appreciated.
Sincerely,
7,-"cd,-. ‘1,,....,,____
Jonathan Williams, CESSWI
Erosion Control Coordinator
Enclosures: Modifications
Fact Sheet on the New NCGOI Permit
Permit
Letter of Approval with Modifications
Watertech Inc. Distribution Facility
October 31'2023
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Watertech Inc. Distribution Facility
Project ID: STVLE-2024-043
County: Iredell
Reviewed by: Jonathan Williams
Required changes are designated as "RC" under legal authority from NC
General Statutes Chapter 113A Article 4 and the Iredell County Land
Development Code.
Suggested changes are designated as "SC" for improvement of the plan.
1. Delineate on the erosion control plans locations of the temporary diversions in Phase I.
Separate Phase I and Phase 2 sheets may be needed. —RC
to bring the site to grade but are not to be removed until the site is at permanent grade and
stormwater lines are installed to carry runoff to the sediment basin.—RC
3. In thc Construction Scqucncc, add a stcp to schcdulc an initial inspection with Iredell
County Erosion Control once all measures are installed and prior to mass grading. —RC
4. In the Construction Sequence, install sediment basin before installing temporary
diversions.—RC
5. In thc Erosion and Scdimcnt Control Notcs, change all crosion control jurisdictional
authority references to Iredell County. —RC
6. Adjust sediment basin skimmer orifice size to dewater the required basin volume iii as
close to 3 days' time (2.8 days) possible. —RC
7. Provide a permanent seeding schedule detail. RC
8. Provide a matting installation detail. RC
9. Use slope drains to feed the diversion entry points into the sediment basin. Provide detail.
-SC