1 Project Name Forest Ridge Commons-Phase 1
2 Project Area(ac) 16.32
3 Coastal Wetland Area(ac) 0
4 Surface Water Area(ac) 0
5 Is this project High or Low Density? High
6 Does this project use an off-site SCM? No
COMPLIANCE WITH 02H.1003(4)
7 Width of vegetated setbacks provided(feet) 30
8 Will the vegetated setback remain vegetated? Yes
9 If BUA is proposed in the setback,does it meet NCAC 02H.1003(4)(c-d)? N/A
10 Is streambank stabilization proposed on this project? No
NUMBER AN.TYPE,QF SCMs:
11 Infiltration System
12 Bioretention Cell
13 Wet Pond 2
14 Stormwater Wetland
15 Permeable Pavement
16 Sand Filter
17 Rainwater Harvesting(RWH)
18 Green Roof _
19 Level Spreader-Filter Strip(LS-FS)
20 Disconnected Impervious Surface(DIS)
21 Treatment Swale
22 Dry Pond _
23 StormFilter
24 Silva Cell
25 Bayfilter
26 Filterra
FORMS LOADED
DFSCERTIFICATION
27 Name and Title: i Kenneth W.Smith Jr.,PE 045277
28 Organization: Smith Site Consultants,PLLC. NC Firm#P-2144
29 Street address: 121 Bulittle Drive
30 City,State,Zip: Linden,NC 28356
31 Phone number(s): 910-391-5923
32 Email: smithsiteconsultants@gmail.com
Certification Statement:
1 certify,under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision;that the
information provided in the form is,to the best of my knowledge and belief,true,accurate,and complete;and that the engineering plans,
specifications.operation and maintenance agreements and other supporting information are consistent with the information provided here.
Designer
`0111i!(]//
\\ ,�� C A. ®c,�/��i
• -- A' -7,1/ joidc7
•Ll. SEAL r - Signature of Designer
045`L77
AA •
•
Seal Date
DRAINAGE AREAS
1 Is this a high density project? Yes
2 If so,number of drainage areas/SCMs 2
3 Does this project have low density areas? No
4 If so,number of low density drainage areas 0
Is all/part of this project subject to previous rule
5 versions? No
FORMS LOADED
DRAINAGE AREA INFORMATION Entire Site 1 2
4 Type of SCM Wet Ponds Wet Pond#1 Wet Pond#2
5 Total drainage area(sq ft) 498096 131734 366362
6 Onsite drainage area(sq ft) 495885 129523 366362
7 Offsite drainage area(sq ft) 2211 2211 0
8 Total BUA in project(sq ft) 362235 sf 87463 sf 274772 sf
New BUA on subdivided lots(subject to permitting)
9 (sq ft) 290429 sf 81123 sf 209306 sf
New BUA not on subdivided lots(subject to
10 permitting)(sf) 71806 sf 6340 sf 65466 sf
11 Offsite BUA(sq ft) 2211 sf 2211 sf sf
12 Breakdown of new BUA not on subdivided lots:
-Parking(sq ft) sf sf sf
-Sidewalk(sq ft) 7675 sf 610 sf 7065 sf
-Roof(sq ft) sf sf sf
-Roadway(sq ft) 46851 sf 3519 sf 43332 sf
-Future(sq ft) 15069 sf sf 15069 sf
-Other,please specify in the comment box
below(sq ft) sf sf sf
New infiltrating permeable pavement on
13 subdivided lots(sq ft) sf sf sf
New infiltrating permeable pavement not on
14 subdivided lots(sq ft) sf sf sf
Existing BUA that will remain(not subject to
15 permitting)(sq ft) sf sf sf
16 Existing BUA that is already permitted(sq ft) sf sf sf
17 Existing BUA that will be removed(sq ft) sf sf sf
18 Percent BUA _ 51% 66% 75%
19 Design storm(inches) 1.0 in 1.0 in 1.0 in
20 Design volume of SCM(cu ft) _ 32381 cf 7528 cf 24853 cf
21 ?Calculation method for design volume Simple Method Simple Method Simple Method
ADDITIONAL INFORMATiON
Please use this space to provide any additional information about the
22 (drainage area(s):
WET POND
1 Drainage area number ( 1 I 2
2 Minimum required treatment volume(Cu ft) ) 7109 cf 22134 cf
GENERAL MDC FROM 02H.1050 '"•
3 Is the SCM sized to treat the SW from all surfaces at build-out? ( Yes Yes
4 Is the SCM located away from contaminated soils? Yes Yes
5 What are the side slopes of the SCM(H:V)? 2:1 3:1
Does the SCM have retaining walls,gabion walls or other engineered
6;side slopes? Yes Yes
Are the inlets,outlets,and receiving stream protected from erosion
7 (10-year storm)? Yes Yes
l Is there an overflow or bypass for inflow volume in excess of the
8 design volume? Yes Yes
9 What is the method for dewatering the SCM for maintenance? Drawdown Orifice Drawdown Orifice
10 If applicable,will the SCM be cleaned out after construction? Yes Yes
11 Does the maintenance access comply with General MDC(8)? Yes Yes
12 Does the drainage easement comply with General MDC(9)? Yes Yes
13 If the SCM is on a single family lot,does(will?)the plat comply with N/A N/A
General MDC(10)?
14 Is there an O&M Agreement that complies with General MDC(11)? Yes Yes
15 Is there an O&M Plan that complies with General MDC(12)? Yes Yes
16 Does the SCM follow the device specific MDC? Yes Yes
17 Was the SCM designed by an NC licensed professional? Yes Yes
WET POND MDC FROM 02H.1353
18'Sizing method used SA/DA SA/DA
19 Has a stage/storage table been provided in the calculations? Yes Yes
20 Elevation of the excavated main pool depth(bottom of sediment 273.00 250.75
removal)(fmsl)
21 Elevation of the main pool bottom(top of sediment removal)(fmsl) 273.50 251.25
22 Elevation of the bottom of the vegetated shelf(fmsl) 278.50 255.50
23 Elevation of the permanent pool(fmsl) 279.00 256.00
24 Elevation of the top of the vegetated shelf(fmsl) 279.50 256.50
25 Elevation of the temporary pool(fmsl) 280.50 257.25
26 Surface area of the main permanent pool(square feet) 3087 13726
27 Volume of the main permanent pool(cubic feet) 7737 cf 37312 cf
28 Average depth of the main pool(feet) 3.00 ft 3.20 ft
29 Average depth equation used Equation 3 Equation 3
30 If using equation 3,main pool perimeter(feet) 204.4 ft 518.2 ft
31 If using equation 3,width of submerged veg.shelf(feet) 3.0 ft 5.0 ft
32 Volume of the forebay(cubic feet) 1175 cf 5759 cf
33 Is this 15-20%of the volume in the main pool? Yes Yes
34 Clean-out depth for forebay(inches) 6 in 6 in
35 Design volume of SCM(cu ft) 7528 cf 24853 cf
36 Is the outlet an orifice or a weir? Orifice Orifice
37 If orifice,orifice diameter(inches) 1 in 3 in
38 If weir,weir height(inches)
39 If weir,weir length(inches)
40 Drawdown time for the temporary pool(days) 3 2.7
41 Are the inlet(s)and outlet located in a manner that avoids short- Yes Yes
circuiting?
42 Are berms or baffles provided to improve the flow path? Yes Yes
43 Depth of forebay at entrance(inches) 60 in 60 in
44 Depth of forebay at exit(inches) 54 in 54 in
45 Does water flow out of the forebay in a non-erosive manner? Yes Yes
46 Width of the vegetated shelf(feet) 6 ft 10 ft
47 Slope of vegetated shelf(H:V) 6:1 10:1
48 Does the orifice drawdown from below the top surface of the Yes Yes
permanent pool?
49 Does the pond minimize impacts to the receiving channel from the 1- Yes Yes
yr,24-hr storm?
50 Are fountains proposed?(If Y,please provide documentation that No No
MDC(9)is met.)
51 Is a trash rack or other device provided to protect the outlet system? Yes Yes
52 Are the dam and embankment planted in non-clumping turf grass? Yes Yes
53 Species of turf that will be used on the dam and embankment Bermuda Bermuda
54 Has a planting plan beenrovided for the vegetated shelf? Yes Yes
ADDITIONAL INFORMATION
Please use this space to provide any additional information about the
55 wet pond(s):
Wet Pond 3 5:28 PM 10/26/2023