Loading...
HomeMy WebLinkAboutNC0000272_Transition Plan_20230317Canton, NC WWTP Transition Plan and Recommendations 1 WWTP Transition Plan Phase I 1A Initial Outage Preparation(prior to beginning of mill outage) PH control Surge Volume—using Primary Clarifier Chemicals required Sulfuric Acid, C02, Coagulants/Polymers , Supplemental Nutrients 1B Beginning of Mill Outage (Similar to shutting down for annual outage) Timeframe (Weeks) Continue to run WWTP as an Activated Sludge System at full capacity Monitor flow, BOD/surrogate loading, and Food/Microorganism (F/M) ratio Phase 1 to end when flow/loading/F/M reaches 50% of normal levels—Use rolling average numbers—3-5day rolling average 2 AB or Digester (2.3 MG) AB or Digester (2.3 MG) Aeration Basin (3.4 MG) Aeration Basin (3.4 MG) #1 Primary Clarifier (1.01 MG) #2 Primary Clarifier (3.47 MG) #3 Primary Clarifier (3.47 MG) #4 Secondary Clarifier (2.82 MG) #5 Secondary Clarifier (2.82 MG) #6 Secondary Clarifier (1.85 MG) Flow Splitting Station Low Lift Pumps Bar Screens Grit Chamber City Sewer RAS Belt Presses Mill Wastewater Primary Sludge WAS Phase I Initial Shutdown Activated Sludge Full Capacity 3 WWTP Transition Plan Phase II (Time frame-Months) Tank, vessel, mill, and piping clean-up Similar to tail end of annual outages Reduced flow and Loading F/M will be reduced Begin taking excess equipment off-line Primary Clarifiers Stop C02 Secondary Clarifiers Take one of the two aeration trains out of service Continue to run activated sludge process Belt Presses Low lift pumps 4 AB or Digester Down AB or Digester (2.3 MG) Aeration Basin Down Aeration Basin (3.4 MG) #1 Primary Clarifier (1.01 MG) #2 Primary Clarifier (3.47 MG) #3 Primary Clarifier Storm Surge (3.47 MG) #4 Secondary Clarifier Emergency Use (2.82 MG) #5 Secondary Clarifier (2.82 MG) #6 Secondary Clarifier (1.85 MG) Flow Splitting Station Low Lift Pumps Bar Screens Grit Chamber City Sewer RAS Belt Presses Mill Wastewater Primary Sludge WAS Phase II Partial Shutdown Activate Sludge 5 WWTP Transition Plan Phase III (Timeframe—Months) Phase III begins when mill flow/loading approaches zero Municipal flow only approximately 1 MGD except for storm flows Long Term End Game WWTP—Flow scheme Primary Treatment Grit chamber, Bar screen, Low lift pump/s as required, flow splitting station Primary Clarification #1 Primary Clarifier-1.01 MG #2 & #3 storm surge (6.9MG) Secondary Treatment One train in ASB(Aerated Stabilization Basin) once through system 2.3 MG section aerated; 3.4 MG section final aeration and settling area 6 WWTP Transition Plan Phase III continued Secondary/tertiary Clarification Last part of aeration train (3.4 MG) #6 or #5 Clarifier #4 & #5 Out of service available for emergency use (9.6 MG) Storm surge or off-spec quality treated water Flow Measurement, Reaeration, and Discharge Flume—flow compliance Reaeration Cascade—O2 injection Final Discharge 7 AB or Digester Down AB or Digester (2.3 MG) Aeration Basin Down Aeration/ Settling (3.4 MG) #1 Primary Clarifier (1.01 MG) #2 Primary Clarifier Storm Surge (3.47 MG) #3 Primary Clarifier Storm Surge (3.47 MG) #4 Secondary Clarifier Emergency Use (2.82 MG) #5 Secondary Clarifier Emergency Use (2.82 MG) #6 Secondary Clarifier (1.85 MG) Flow Splitting Station Low Lift Pumps Bar Screens Grit Chamber City Sewer Belt Presses Primary Sludge Phase III Municipal Flow ASB once through Operation Leachate/ storm flow 8 WWTP Transition Plan Further Investigation/Data Needs O2 Addition Optimization City of Canton– WWTP data Industrial components of Canton wastewater Nitrogen and Ammonia content of Canton wastewater Normal and Maximum flows Landfill Leachate characterization Last Permit Renewal Priority Pollutant analysis Mill operator input on transition plan Treatability study to confirm needed residence time for ASB (once through) operation Sampling and analysis planned for the week of March 20. 9