HomeMy WebLinkAboutNCC231000_ESC Approval Submitted_20230418 ROY COOPER .sure,-_
Governor
ELIZABETH S.BISER
Secretary . .
BRIAN WRENN
Director
Ei vironotenrai Qualify
March 6,2022
LETTER OF APPROVAL WITH MODIFICATIONS
KLK Properties, LLC
Attention: Kenneth Baucom, Managing Member
2723 Horse Pen Creek Road, Suite 105
Greensboro,North Carolina 27410
RE: Project Name: Bridges of Cabarrus Phase 2
Acres Approved: 9.80
Project ID: CABAR-2022-024
County: Cabarrus
City: Kannapolis
Location: South Ridge Road
River Basin: Yadkin-Pee-Dee
Stream Classification: Other
Submitted By: KLK Properties, LLC
Date Received by LQS: March 01, 2022
Plan Type: Revised
Dear Mr. Baucom:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan
to be acceptable with modifications and hereby issue this letter of Approval with
Modifications. The Modifications Required for Approval are listed on the attached page. This
plan approval shall expire three (3) years following the date of approval, if no land-disturbing
activity has been undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the
NCG010000 Construction General Permit. After the form is reviewed and found to be
complete, you will receive a link with payment instructions for the $100 annual permit
fee. After the fee is processed, you will receive the COC via email. As the Financially
Responsible Party shown on the FRO form submitted for this project,you MUST obtain the
COC prior to commencement of any land disturbing activity. The eNOI form may be accessed
at deq.nc.gov/NCGO1. Please direct questions about the eNOI form to the Stormwater
Program staff in the Raleigh central office. If the owner/operator of this project changes in the
future,the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a)and the NCGO 1 permit require that the following documentation be kept on
file at the job site:
Q -4)�D E North Carolina Department ofEnvironmentalstCent u Division 0 of Energy,Mineral and Land Resources
Mooresville Regional Office I 610 East Center Avenue,Suite 30l I Mooresville,North Carolina 28115
704-663-1699
I
Letter of Approval with Modifications
KLK Properties LLC
March 6, 2022
Page 2 of 4
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also,this letter gives the notice required by G.S. 113A-61.1(a)of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance-oriented,requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project,the
erosion and sedimentation control plan is inadequate to meet the requirements of the Sedimentation
Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66),this office may
require revisions to the plan and implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws,regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land-disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any
change in the information included on the form. In addition, it would be helpful if you notify this office of
the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
jija
Zahid S. Khan, CPM, CPESC, CPSWQ
Regional Engineer
Land Quality Section
KSL
Enclosures: Certificate of Approval
Modifications Required for Approval
NCGO1 Fact Sheet
cc: Inspection Department
Timmons Group
Attn: Skylar Patton, 610 East Morehead Street, Suite 2500, Charlotte,North Carolina 28202
Letter of Approval with Modifications
KLK Properties LLC
March 6, 2022
Page 3 of 4
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Bridges of Cabarrus Phase 2
Project ID: CABAR-2022-024
• County: Cabarrus
1. The new NCGO1 Construction stormwater permit requires Ground Stabilization
and Materials Handling and Self-Inspection, Recordkeeping and Reporting
requirements on your plans. The NCGO1 compliance plan sheets for these can be found
attts:;,'deq.nc .i3c?�:ai�octtii�isio� s,'ener - :i�era1 laid esc� �rce5 ntr �--rnieral-
i and-cerrni tsistorrnwater-perrnitsi Constructio n-sw.
2. All measures, including stone drive, will be inspected after rain and at least
weekly for adequacy and needed maintenance. [N.C.G.S. 143-215.1]
3. Additional measures may be necessary during the course of this project. [15A
NCAC 4B .0115].