July 25, 2022
]LETTER OF APPROVAL 'WITH MODIFICATIONS
Vanguard Ventures, LLC
ATTN: Mr. George Barnes
3825 Barrett Dr., Suite 100
Raleigh, NC 27609
RE: Project Name: Dollar General
Acres Approved: 1.37
Project ID: RANDO-2022-042
County: Randolph
City: Asheboro
Address: 255 N.C. Hwy. 49 S
River Basin: Yadkin Pee -Dee
Stream Classification: Little River -- Class C
Submitted By: Bowman N,C., Ltd. — Mr. Matthew Lowder, P.E.
Date Received by LQS: June 28, 2022
Plan Type: Commercial
Dear Mr. Barnes:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable with modifications and hereby issue this Letter of Approval with Modifications. The
Modifications Required for Approval are listed on the attached page. This plan approval shall expire
three (3) years following the date of approval, if no land -disturbing activity has been undertaken,
as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000
Construction General Permit. After the form is reviewed and found to be complete, you will receive
a link with payment instructions for the $100 annual permit fee. After the fee is processed, you will
receive the COC via email. As the Financially Responsible Party shown on the FRO form
submitted for this project, you MUST obtain the COC prior to commencement of any land
disturbing activity. The eNOI form may be accessed at deq.nc,govINCG01. Please direct questions
about the eNOI form to the Stormwater Program staff in the Raleigh central office. If the
owner/operator of this project changes in the future, the new responsible parry must obtain a
new COC.
409_
WiNo thCatallnaDepartmencofEnvlrunmentalQuallty I DhlslonofEneNy,Mineral and UndResounces
4' nston-SaletnReglonal0ffice 14SOHanes Mill Road,Su[teWi 300I Winston-Salem, North Carolina21103
i � _5� 336,776.9800
Letter of Approval with Modifications
Vanguard Ventures, LLC
June 22, 2022
Page 2 of 3 }'
Title 15A NCAC 4B .0118(a) and the NCG01 permit require that the following documentation be
kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection
to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Program is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If following the commencement
of this project, it is determined that the erosion and sedimentation control plan is inadequate to meet
the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina General
Statute 113A-51 through 66), this office may require revisions to the plan and implementation of
the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State
water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may
also apply to this land -disturbing activity. This approval does not supersede any other permit or
approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. This permit allows for a land -disturbance, as
called for on the application plan, not to exceed the approved acres. Exceeding the acreage will be
a violation of this permit and would require a revised plan and additional application fee. You are
requested to file an amended form if there is any change in the information included on the form.
In addition, it would be helpful if you notify this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
Tamera E�gineer
4n, PE
Regional
Land Quality Section
Enclosures: Certificate of Approval
Modifications Required for Approval
NCGO1 Fact Sheet
ec: Mr. Brent Purdum (bpurdum@bowman.com)
c: WSRO file
Letter of Approval with Modifications
Vanguard Ventures, LLC
July 22, 2022
Page 3 of 3
MODIFICATIONS )REQUIRED FOR APPROVAL
Project Name: Dollar General
Project ID: RANDO-2022-042
County: Randolph
1. No major grading activities or basin construction are to take place during wet weather or
periods of predicted wet weather i.e. hurricanes
2. Install inlet protection by the end of the workday for all constructed SW inlets
3. Install silt fence below sediment basin embankment before sediment basin construction
begins
4. Inspect and clean out the stormwater system before bringing online
5. Site must be "storm ready" before any extended breaks in construction activities including
weekends. [15A NCAC 04B .0106(a)(3)]
6. Stockpiles must be located at least 50 ft. from any stormwater inlet. [NPDES NCG010000]
7. Any off site borrow and waste required for this project must come from a site with an approved
erosion control plan, a site regulated under the Mining Act of 1971, or a landfill regulated by
the Division of Solid Waste Management. Trash/debris from demolition activities or generated
by any activities on site must be disposed of at a facility regulated by the Division of Solid
Waste Management or per Division of Solid Waste Management or Division of Water
Resources rules and regulations. [15A NCAC 4B .0110]
8. Our Division maintains an interactive web -based map to help the public determine whether
development activities are subject to the post -construction state stormwater permitting program
or other stormwater permitting requirements. If your project is subject to state stormwater
permitting requirements, you must have the post -construction stormwater permit prior to
construction. The web -based map is located at:
htts:llde .nc. ov/about/divisions/ever -mineral-land-resources/ener -mineral-land-
data/stormwater-maps-gis-resources
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 1SA NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities