April 11, 2022
LETTER OF APPROVAL
Partners in Learning Child Development Center, Inc.
Attention: Norma Honeycutt, Executive Director
2386 Robin Road
Salisbury, North Carolina 28144
RE: Project Name: Partners in Learning
Acres Approved: 7.00
Project ID: ROWAN-2022-015
County: Rowan
City: Salisbury Location: Martin Luther King Jr. Avenue
River Basin: Yadkin -Pee -Dee
Stream Classification: Other
Acres Approved: 7.0
Submitted By: Summey Engineering and Associates, PLCC
Date Received by LQS: March 15, 2022
Plan Type: New
Dear Ms. Honeycutt:
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to
be acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval
must be posted at the job site. This plan approval shall expire three (3) years following the date
of approval, if no land -disturbing activity has been undertaken, as is required by Title 15A
NCAC 413.0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the
NCGO 10000 Construction General Permit. After the form is reviewed and found to be complete,
you will receive a link with payment instructions for the $ 100 annual permit fee. After the fee
is processed, you will receive the COC via email. As the Financially Responsible Party shown
on the FRO form submitted for this project, you MUST obtain the COC prior to commencement
of any land disturbing activity. The eNOI form may be accessed at deq.nc.gov/NCGOI. Please
direct questions about the eNOI form to the Stormwater Program staff in the Raleigh central
office. If the owner/operator of this project changes in the future, the new responsible party must
obtain a new COC.
Title 15A NCAC 413 .01 18(a) and the NCG0l permit require that the following documentation
be kept on file at the job site:
North Carolina Department of Envirorunental Quality I Division of Energy, Mineral and Land Resources
Mooresville Regional Office 1610 East Center Avenue, Suite 3011 Mooresville, North Carolina 28115
AR FEw Q 704-663-1699
Q
DocuSign Envelope ID: 2DBB34ED-B364-47FD-AC4D-1097B34139CD
Letter of A pproval
r-1p
Partners in Learning Child Development Center, Inc.
April 11, 2022
Page 2 of 2
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G. S. I I 3A-6 1. 1 (a) of our right of periodic inspection
to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate to meet
the requirements of the Sedimentation Pollution Control Act of 1973 (North Carolina General
Statute I I 3A-51 through 66), this office may require revisions to the plan and implementation of
the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and
State water quality laws, regulations, and rules. In addition, local city or county ordinances or
rules may also apply to this land -disturbing activity. This approval does not supersede any other
permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form
if there is any change in the information included on the form. In addition, it would be helpful if
you notify this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
EDo uSign d by,
Zahid S. Khan, CPM, CPESC, CPSWQ
Regional Engineer
Land Quality Section
KSL
Enclosures: Certificate of Approval
cc: Surnmey Engineering Associates, PLCC
Attention: Zach Gardner
Post Office Box 968
Asheboro, North Carolina 27204
= = 4-,
OWN
COO
cl
m ".41 Erl POW
4*
CA
Ila—
PON
4-o
P..5
PC
-4..1
00
0 P*
00
COO let
*pm
-+-a "o 0 4*
Q&A About the New NCG01 Permit
Why do construction sites have to do this extra application step?
DEMLR is required by the EPA to issue a specific COC to every construction
site that disturbs one acre or more. DEMLR is working to create a form
that combines the E&SC plan approval and e-NOI processes,, but that will
take more time. For now, DEIVILR has created an efficient e-NOI process.
If an E&SC Plan is approved before April 1, which permit applies?
Projects with already approved E&SC Plans will automatically follow the
new NCGO1 permit, but will not need to fill out an e-NOI or pay an annual
permit fee. However, the permittees should print the new permit and the
two standard detail sheets and have them on site.
Will DEMLR offer tools to help permittees comply with the new NCG01?
Yes, DEMLR will provide two sample plan sheets at deg.nc.gov/NCGO1 that
can be placed into the E&SC plan set. The first covers the site stabilization
and materials handling portions of the permit. The second sheet covers
the inspection, record -keeping and reporting portions of the permit.
How will the new e-NOI submittal and COC process work?
Permittees will apply for E&SC Plan approvals from DEMLR or the local
E&SC program like before. The E&SC approval letter will instruct the
permittee to visit deq.nc.gov/NCG01 to submit an e-NOI form to DEIVILR.
The permittee may begin the construction activity after receipt of the COC
(within three days*). The permittee must print and retain a copy of the
permit and the COC on site. Initially, the COC will be issued for free but on
or around June 1, 2019, a $100 annual general permit fee will be charged.
Who is allowed to submit an e-NOI form?
Submittal must be by a responsible corporate officer that owns or
operates the activity, such as a president, secretary, treasurer, or vice
president or a manager that is authorized in accordance with IV.13.6 of the
NCGO1 permit. Additional signatory options are set forth in IV.13.6 of the
permit. it is possible for consultant to prepare the e-NOI ' save it as a draft,
and email it to the responsible entity for signature & submittal.
What happens to the COC when the construction activity is complete?
When a project is complete, the permittees will contact DEMLR or the local
delegated program to close out the E&SC Plan. After DEMLR or the local
E&SC program inform the permittee of the project close out via inspection
report, the permittee will visit decI.nc.gov/NCG01 to submit an e-NOT.
Will there be a grace period for adherence to the new process?
DEIVILR does not have the authority to grant a grace period from a
federally mandated permit. Permittees will be informed of the new
process via web site, E&SC Plan approval letters and list servs. if a
construction activity disturbs one acre or more (or is part of common plan
of development that disturbs one acre or more) fails to submit an e-NOI
after approval of its E&SC Plan, this is a violation of federal permitting
requirements and the permittee could be subject to a penalty assessment.
How does the new NCGO1 affect the
delegated local E&SC Programs?
Local programs will continue to review
and approve E&SC plans. However,
they will no longer send copies of the
NCGO1 with E&SC Plan approvals.
DEMLR will provide sample language to
use in local E&SC Plan approvals to
advise permittees that they must
submit an e-NOI to DEIVILR.
Local programs are not required to
check if permittees have submitted e-
NOls to DEIVILR. However, if they wish
to do this voluntarily, there will be a
tool available on DEMLR's web site for
them to view a list of construction
projects that have submitted e-NOIs.
When local programs close out an E&SC
Plan, the close-out letter will advise
permittees that they must submit an e-
NOT. DEMLR will provide sample
language.
Local programs may approve E&SC
plans that meet state sediment laws
and rules even if those plans are not
compliant with all of the NCG01
requirements. However, their
permittees will be required to add two
plan sheets (which will be provided by
DEMLR) to their E&SC Plans to ensure
that they fully comply with the ground
stabilization, materials handling, and
inspection, record -keeping and
reporting portion of the NCGO1 permit.
Or 24 business hours for a project
approved under the DEMLR Express
review program.
1�act Sheet on the New NCG01 Permit
April 2019
The NC Construction General Permit (also known as NCGOV) was renewed on April 1, 2019. The updated permit
does not significantly change the measures that are required to be implemented on construction sites. However,
there are some organizational and technical updates to the permit as described below. Most notably, there is a new
process in which construction sites will obtain official coverage under an NCGO1 permit through an electronic
process. DEMLR worked With a broad team of stakeholders to make all of these updates. If you have questions,
contact Annette Lucas at Annette. lucasP ncde nr.g or (919) 707-3639.
Organizational Updates
The new permit:
• Repeats state requirements for E&SC
Plans and organizes them with federal
construction activity requirements;
• Is clearly organized by topic; and
• Has less text and more tables.
Technical Updates
The new permit:
• Requires that the E&SC Plan meet
SWPPP requirements (p. 2);
• Provides a list of items that must be
included in the SWPPP, such as the
construction sequence, plans,
calculations, etc. (p. 2-4);'
• Has updated language on bypasses and
upsets that is tailored to construction
activities (p. 10);
• Puts all timeframes for inspections,
record -keeping and reporting in
11 calendar days" for clarity and
consistency (p. 11-14);2
• Changes the inspection frequency
(during business hours) to at least
once per 7 calendar days and after
every storm > 1.0 inch (previously 0.5
inch);' and
• Excludes weekends, state and federal
holidays from normal business hours
unless construction activities take
place (p. 23).
This list is based on website guidance
by the DEMLR Sediment Program.
The number of calendar days was
selected to be as equivalent as
possible with the previous permit.
The intent is to provide predictability
to the inspection schedule.
Acronyms to Know
COC: Certificate of Coverage, proof of coverage under an NCGO1 permit
DEMLR: NC Division of Energy, Mineral, and Land Resources
E&SC: Erosion & Sedimentation Control
e-NOI: Notice of Intent, application form for the NCGO1 permit
e-NOT: Notice of Termination, form for closing out the NCG01 permit
SWPPP: Stormwater Pollution Prevention Plan, required by the NCGOI
The NCG01 Process
The new NCGO1 applies to permits approved on or after April 1, 2019.
Permittees will no longer receive a copy of the NCG01 permit in the mail
with their E&SC Plan approvals and be considered as covered under the
permit. Federal rules require that DEMLR receive an NO[ on each
construction project and issue each construction project its own COC.
Under the new NCGO1 process, construction sites will continue to
receive approval for E&SC Plans from either DEMLR or the delegated
local E&SC program just like before. After receiving E&SC Plan approval,
permittees will officially obtain coverage under the NCGO1 by
completing an e-NOI (available at deg.nc.gov/NCG01). The e-NOI will
only take about 20 minutes to fill out and submit on-line.
Initially, there will be no charge associated with applying for an NCGO1
permit but on or around June 1, 2019, DEMLR will begin charging a $100
annual general permit fee as required per §143-215.3D.
DEMLR is working on creating a single application form that will allow an
applicant to simultaneously apply for an E&SC permit and an NCGO1
COC. That effort is part of a larger Permit Transformation project at
DEMLR.