HomeMy WebLinkAboutSWA000145_Construction Sequence_20220503BCSC ��`� ��• BATEMAN CIVIL SURVEY COMPANY 2524 Reliance Avenue Phone: 919.577.1080 Apex, North Carolina 27539 info@batemancivilsurvey.com DATE: March 21, 2022 PROJECT: Middleton Farms- Construction Sequence PHASE I CONSTRUCTION SEQUENCE: 1. EROSION AND SEDIMENT CONTROL (E&SC) PERMIT AND A CERTIFICATE OF COVERAGE (COC) MUST BE OBTAINED BEFORE ANY LAND DISTURBING ACTIVITIES OCCUR. 2. OWNER/DEVELOPER/CONTRACTOR SHALL OBTAIN A COPY OF THE APPROVED EROSION CONTROL PLAN AND MAINTAIN A COPY OF THE PLAN ON SITE THROUGHOUT DURATION OF CONSTRUCTION. 3. OWNER/CONTRACTOR SHALL NOTIFY AND REQUEST BY COR AND NCDEQ DEMLR AT PERM ITPORTAL.RALEIGHNC.GOV FOR A PRE -CONSTRUCTION MEETING PRIOR TO BEGINNING ANY LAND DISTURBANCE ACTIVITIES. 4. CONTRACTOR TO DIG A TEST PIT WITHIN THE LIMITS OF THE BOTTOM OF THE STORMWATER CONTROL MEASURE. CONTRACTOR TO HAVE A LICENSED SOIL SCIENTIST PERFORM AN INFILTRATION TEST AT THE BOTTOM ELEVATION OF THE SCM AND IMMEDIATELY REPORT THE INFILTRATION RATE TO THE ENGINEER. 5. OWNER/CONTRACTOR SHALL NOTIFY NCDEQ DEMLR AT PERM ITPORTAL.RALEIGHNC.GOV A MINIMUM OF 72 HOURS BEFORE START OF CONSTRUCTION ON EACH PHASE. 6. ONLY CLEAR/GRADE ENOUGH TO INSTALL SEDIMENT CONTROL DEVICES AS SHOWN IN PHASE I. 7. INSTALL CONSTRUCTION ENTRANCE, CLEAN WATER DIVERSION DITCH AND TEMPORARY PIPE AS INDICATED ON PLAN. INSTALL SILT FENCE, SILT FENCE OUTLETS AROUND THE PERIMETER OF THE SITE. DISTURB ONLY THE AREAS NECESSARY FOR INSTALLATION. ALL DITCHES WILL BE LINED TO TOP OF BANK. B. CONTRACTOR SHALL IMMEDIATELY SEED, MULCH AND TACK ANY BARE SOILS BETWEEN THE DOWNSTREAM TOE OF BASIN OR DIVERSIONS IMMEDIATELY AFTER INSTALLATION. 9. INSTALL SILT BAG INLET PROTECTION AS SHOWN ON PLANS, SILT BAG INLETS SHALL BE CONTINUOUSLY MONITORED DURING OPERATION. 10. ADJUST EROSION AND SEDIMENT CONTROL MEASURES AS NECESSARY FOR PROPER OPERATION. INSTALL ADDITIONAL EROSION CONTROL MEASURES IF DETERMINED NECESSARY BY INSPECTOR. 11. INSPECT ALL EROSION CONTROL DEVICES AFTER EVERY RAINFALL EVENT AND AT LEAST ONCE PER WEEK. REPAIR AND CLEAN OUT AS REQUIRED. 12. NOTIFY NCDEQ DEMLR AT PERM ITPORTAL.RALEIGHNC.GOV FOR AN INSPECTION AFTER THIS IS COMPLETED. 13. PROCEED TO PHASE 2 OF THE EROSION CONTROL SEQUENCE WHEN PHASE 1 MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED. ALL SEDIMENT BASINS AND RELEVANT DIVERSIONS WILL BE MAINTAINED UNTIL PROJECT BUILD OUT. 14. WHEN THE PROJECT IS COMPLETE, THE PERMITTEE SHALL CONTACT DEMLR TO CLOSE OUT THE E&SC PLAN. 15. THE PERIMETER SILT FENCING SHALL BE MAINTAINED UNTIL ALL CONSTRUCTION IS COMPLETED AND PERMANENT GROUND COVERAGE IS ESTABLISHED. 16. PER NPDES REQUIREMENTS, A RAIN GAUGE, SELF -INSPECTION RECORDS, PERMIT, CERTIFICATE OF COVERAGE, AND S&E PLAN ARE REQUIRED TO BE MAINTAINED ON SITE AND ACCESSIBLE DURING INSPECTION. IT IS RECOMMENDED THAT THESE ITEMS BE PLACE IN A PERMITS BOX AT THE BEGINNING OR ENTRANCE OF PROJECT. Bateman Civil Survey Company, PC Page 2 PHASE II EROSION CONTROL CONSTRUCTION SEQUENCE: 1. MAINTAIN ALL EXISTING EROSION CONTROL FEATURES PREVIOUSLY CONSTRUCTED AND ASSOCIATED WITH PHASE 2 EROSION CONTROL. 2. CONTINUE BRINGING FILL INTO THE SITE. IMPORTED MATERIAL WILL REQUIRE A PERMITTED SITE APPROVAL BEFORE THIS PROCESS BEGINS. ALL FILL SHALL BE BROUGHT INTO THE SITE AND EVENLY SPREAD OUT THROUGH THE SITE AS SHOWN IN LIFTS OF NO MORE THAT 1.0' AT A TIME. FILL SHALL BE ROLL COMPACTED BY A DOZER OR EQUIVALENT AS IT IS PLACED. 3. BEGIN INSTALLATION OF THE STORM PIPE SYSTEM FROM JB201 TO OCS204.ONCE THIS RUN IS COMPLETE, INSTALL SKIMMER SEDIMENT BASIN. 4. AFTER THE SEDIMENT BASIN IS CONSTRUCTED, CONTINUE INSTALLING STORM DRAINAGE SYSTEM FROM OUTLET POINT (LOW END) AND WORK UPSTREAM. PIPE INLET PROTECTION SHALL BE UTILIZED AT THE END OF EACH WORKDAY TO ASSURE PIPE NETWORK IS NOT INUNDATED WITH SEDIMENT. 5. INSTALL SILT BAG INLET PROTECTION AS SHOWN ON PLANS, SILT BAG INLETS SHALL BE CONTINUOUSLY MONITORED DURING OPERATION. 6. INSTALL SITE IMPROVEMENTS, STORMWATER DRAINAGE SYSTEM, UTILITY SERVICES, SIDEWALKS AND DRIVES AS SHOWN ON THE APPROVED PLANS. ALL OPEN TRENCHES FOR UTILITY AND STORMWATER INSTALLATION SHALL BE PROTECTED FROM SEDIMENTATION BY PILING EXCAVATED MATERIAL ON THE UPHILL SIDE OF EXCAVATION. 7. INSTALL ADEQUATE EROSION AND SEDIMENT CONTROL MEASURES AND/OR INCREASE MAINTENANCE FREQUENCY WHERE APPROVED MEASURES FAIL TO PREVENT ACCELERATED EROSION, OFF -SITE SEDIMENTATION, OR REPETITIVE NON-COMPLIANCE ISSUES. ALL MEASURES MUST BE INSTALLED PER PLAN DETAIL. ENSURE CONSTRUCTION TRAFFIC IS LIMITED TO THE CONSTRUCTION ENTRANCE ONLY. 8. GROUND COVER SHALL BE PROVIDED AS FOLLOWS: FOR ALL AREAS OF MODERATE AND/OR STEEP SLOPES, PROVIDE TEMPORARY GROUND COVER OF THE SLOPE HAS NOT BEEN DISTURBED FOR A PERIOD OF FOURTEEN DAYS. SLOPES GREATED THAN 3:1 REQUIRE GROUND COVER IN 7 DAYS. PROVIDE GROUND COVER SUFFICIENT TO RESTRAINEROSION ON ANY PORTION OF THE SITE UPON WHICH FURTHER LAND -DISTURBING ACTIVITY IS NOT BEING UNDERTAKEN WITHIN FOURTEEN (14) CALENDAR DAYS OF TEMPORARILY OR PERMANENTLY SUSPENDING LAND DISTURBING ACTIVITY. ESTABLISH PERMANENT GROUND COVER SUFFICIENT TO RESTRAIN EORSION WITHIN FOURTEEN (14) CALENDAR DAYS FOLLOWING COMPLETION OF CONSTRUCTION OR DEVELOPMENT AND/OR PRIOR TO FINAL INSPECTION. INSTALL SURB & GUTTER AND GRAVEL BASE. 10. MODIFICATIONS TO THE APPROVED AND PERMITTED PLANS SHALL BE APPROVED BY EROSION CONTROL INSPECTIONS PRIOR TO REMOVAL OR INSTALLATION. CONTACT THE EROSION CONTROL INSPECTOR TO OBTAIN SIGN -OFF ON THE PLANS. 11. MAINTAIN ALL EROSION AND SEDIMENT CONTROL MEASURES IN GOOD WORKING ORDER. SILT FENCE, INLET PROTECTION, AND OTHER SIMILAR MEASURES MUST BE CLEANED OUT BEFORE THEY ARE HALF FULL. CLOGGED STONE FILTERS MUST BE REFRESHED/REPLACED. SILT FENCE CAN NOT HAVE HOLES OR TEARS. 12. IF THE SEDIMENT BASIN IS DRAINED FOR MAINTENANCE OR REMOVAL PURPOSES, IT SHOULD BE FILTERED THROUGH A SILT BAG THAT IS CONTINUOUSLY MONITORED DURING OPERATION. 13. ONCE GRADING IS COMPLETE, ALL UTILITIES, AND ALL STORM SYSTEMS ARE INSTALLED AND ALL AREAS UPGRADIENT FROM THE SEDIMENT BASIN AND THE SITE IS COMPLETELY AND PERMANENTLY STABILIZED PER THE NPDES PLAN AND ABOVE, BEFORE BASIN IS REMOVED. REMOVAL OF THE SEDIMENT BASIN OR CONVERSION TO PERMANENT SCM, PROCEED AS FOLLOWS: CONSULT WITH THE EROSION AND SEDIMENT CONTROL INSPECTOR PRIOR TO BEGINNING REMOCAL OR CONVERSION OF SEDIMENT BASIN. Bateman Civil Survey Company, PC Page 3 PUMP DOWN BASIN- USE APPROVED DEWATERING MEASURES. EFFLUENT MUST BE FILTERED. REMOVE ACCUMULATED SEDIMENT, SEDIMENT MUST BE DISPOSED OF IN AN APPROVED AREA. REMOVE TEMPORARY SKIMMER AND BAFFLES. REMOVE TEMPORARY ORFICE PLUGS FROM RISER AND CLOSE RISER DRAIN. 14. ADJUST EROSION AND SEDIMENT CONTROL MEASURES AS NECESSARY FOR PROPER OPERATION. INSTALL ADDITIONAL EROSION CONTROL MEASURES IF DETERMINED NECESSARY BY INSPECTOR. 15. INSPECT ALL EROSION CONTROL DEVICES AFTER EVERY RAINFALL EVENT AND AT LEAST ONCE PER WEEK. REPAIR AND CLEAN OUT AS REQUIRED. 16. NOTIFY NCDEQ DEMLR AT PERM ITPORTAL.RALEIGHNC.GOV FOR AN INSPECTION AFTER THIS IS COMPLETED. 17. EROSION AND SEDIMENT CONTROL (E&SC) PERMIT AND A CERTIFICATE OF COVERAGE (COC) MUST BE OBTAINED BEFORE ANY LAND DISTURBING ACTIVITIES OCCUR. 18. PROCEED TO PHASE 3 OF THE EROSION CONTROL SEQUENCE WHEN PHASE 2 MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED. 19. WHEN THE PROJECT IS COMPLETE, THE PERMITTEE SHALL CONTACT DEMLR TO CLOSE OUT THE E&SC PLAN. 20. THE PERIMETER SILT FENCING SHALL BE MAINTAINED UNTIL ALL CONSTRUCTION IS COMPLETED AND PERMANENT GROUND COVERAGE IS ESTABLISHED.