Loading...
HomeMy WebLinkAboutSW6110105_Calculations/Geotechnical Report_20110307Stormwater Narrative Fort Bragg SOF Operations Additions This project is located on Lamont Road, near MCKellars Road, in Fort Bragg, North Carolina. The project consists of constructing three new additions to existing Building0-1900-M. No new parking will be added except for 2 handicapped parking spaces. The area is currently developed and landscaped. All disturbed areas will be seeded or sodded to establish a permanent vegetative grass cover. This project falls in the category of a high -density project. The site is divided into three independent drainage basins. The drainage from two of the drainage areas will be routed to an underground infiltration trenches using roof drain collection, catch basins, curb and gutter, curb inlets, and storm drainage piping. The design of the infiltration trenches are to capture the 1" storm and fully infiltrate it into the ground; therefore, 100%treatment of the TSS load will be accomplished, as well as reducing the post -developed discharge of this volume to 0 cfs. The infiltration trenches have drawdown times of 18 hours or less. The third drainage basin is currently 100%impervious and will claim exemption from adding new stormwater BMPs to satisfy Session Law requirements. The application form for this project contains some areas that are not applicable to this project site. This site is located on federally owned property within a military installation. Section VI Item 2 — there are no deed restrictions or protective covenants required, as this is on a military installation. Section VI Item 8c — NCSR numbers are not assigned to roads within the Fort Bragg military installation. Section VI Item 8h and Item 8m — there are no surface waters or wetlands on this project site. Section VI Item 8i — there are no property lines on Fort Bragg; a limits of construction line is included on the drawings graphically only. Section VI Item 8p—vegetative buffers are not required for this project. Section VI Item 9 — soils borings were conducted in the area of the infiltration trenches for the purpose of locating the SHWT; no water or evidence of the SHWT was encountered in the shallow excavations except for movement around a localize rock. Several other borings were conducted around the site and only one encountered water at a depth of 35' below existing grade. SHWT elevation is set at 35' below existing grade based on these findings. Section IV Item 10—there is no property deed, as this project is on Fort Bragg military installation. Section IV Item 11—the property is owned by the federal government, not an LLC. Section VII does not apply. Section IX does not apply, as this land is owned by the federal government. }�Cypress Creek—���^�,� 1 IL 1,3 ���,r{jrryy r ,Is r�•y, �+ Ly{r.,,g_•�%.'.x � Ir,... 1•y '!'-,l^r:. 1� 4-' .� r'� �� '"ir,i� r"C'7 .,�t��_,� ^J rA `-• � �'�..F� f 4 � r-+: 1 ram% y - �. a,b !,�1� '.1 f.� ,•„wi _ �~�! �X r ,1. tir :l • � r J 4: � /• ` •'ter �., y �. �.� C�� �� � T �� _ � �� r I i e j j tea.,,.: •., �� \ \ ``M9�5 94Q \ \ Fort Bragg - SOTF Operations Bldg. Addition Inlet Design, AE#2009-030 Catch Basin Capacity: (from TM 5-820-4) From Figure 3-3, Q/L = 0.7 cfs/ft for head=0.4'. The grate size is 2.75' x 2'. The functional perimeter of the grate = 2(2.75') + 2(number of grates)(2'). Number of Grates Functional Perimeter L ft Q/L (cfs/ft) Q (cfs) 50% Clogging cfs 1 9.50 0.7 6.65 3.33 2 13.50 0.7 9.45 4.73 3 17.50 0.7 12.5 6.13 4 21.50 0.7 15.05 7.53 5 25.50 0.7 17.85 8.93 Catch Basin # I has Q = 0.60 cfs; therefore, use I grate. Catch Basin #5 has Q = 0.20 cfs; therefore, use I grate. Catch Basin #6 has Q = 0.56 cfs; therefore, use I grate. Catch Basin #7 has Q = 0.08 cfs; therefore, use I grate. Catch Basin #9 has Q = 0.34 cfs; therefore, use I grate. Catch Basin # 10 has Q = 0.34 cfs; therefore, use 1 grate. Catch Basin # I I has Q = 0.50 cfs; therefore, use 1 grate. Storm Drainage Design: The storm drainage design is per the standard Savannah standards utilizing Forms 1178, 1155, and 1156. The design incorporates a retention basin between Manholes 7A and 7B and Catch Basin 7 and a retention basin between Catch Basins 9 and 10. The detention basin segments are omitted from the above mentioned Forms and are calculated below. Pipe segment from Manhole 3 to Manhole 8 are a relocation of an existing storm drainage system and duplicates the existing condition. Stormwater Treatment Design: Manholes 7A and 7B along with Catch Basin 7 are connected by 270' of 48" diameter retention basin. The 48' pipe is perforated and surrounded by gravel to allow water to escape the pipe and infiltrate into the ground. The exit from the pipe at Catch Basin 7 is through a 24" pipe whose crest is aligned with the crest of the 48"; therefore, only the lower half of the 48" pipe can be considered to capture stormwater for infiltration. In addition, 1.5' of gravel on each side of the pipe and below the pipe will capture stormwater in its 40% void space. The site requires the first 1" of rainwater be captured and treated for removal of 85% of the Total Suspended Solids (TSS). The captured water must be released at no more than the pre -development runoff rate. The captured water will be infiltrated into the ground, which qualifies for 100% removal of TSS and reduces the post - development discharge for this volume to 0 cfs. Simple Method for Volume Required R=0.05+0.9*1A=0.05+0.9*0.406=0.42 V = 3630 * Ro * Rv * A = 3630 * 1.0" * 0.42 * 0.84ac = 1281 cf Since using infiltration trench without a bypass or overflow discharge onto a vegetative buffer, 2.5 times the calculated volume requirement will be provided. Adjusted Volume required = 1281 cf * 2.5 = 3203 cf. Volume in pipe = [(21)2 7r x 270']/2 = 1696 cf. Volume in gravel = 0.40(270'xTx3.5' — 1696 cf) = 1968 cf Total Volume = 1696 cf+ 1968 cf= 3664 cf. > 3203 cf. OK Infiltration rate in area 4.5 in/hr. Drawdown = depth/rate = 3.5' x (12 in/ft) / 4.5 in/hr = 9.3 hrs. < 120 hrs. OK. Predevelopment I-yr discharge Q = CIA = 0.4(0.13 in/hr)(0.84ac) = 0.04 cfs Manholes 9 and 10 are connected by 40' of 2-60" diameter retention basin. The 2-60' pipes are perforated and surrounded by gravel to allow water to escape the pipe and infiltrate into the ground. The exit from the pipe at Catch Basin 10 is through a 12" pipe whose crest is aligned with the crest of the 2-60"; therefore, only the lower 4' of the 2-60" pipes can be considered to capture stormwater for infiltration. In addition, 2.5' of gravel on each side of the pipes and below the pipes will capture stormwater in its 40% void space. The site requires the first 1" of rainwater be captured and treated for removal of 85% of the Total Suspended Solids (TSS). The captured water must be released at no more than the pre - development runoff rate. The captured water will be infiltrated into the ground, which qualifies for 100% removal of TSS and reduces the post -development discharge for this volume to 0 cfs. Simple Method for Volume Required R=0.05+0.9*1A=0.05+0.9*1.0=0.95 V=3630*Rn*Rv*A=3630* 1.0" * 0.95 * 0.3 lac = 1069 cf Since using infiltration trench without a bypass or overflow discharge onto a vegetative buffer, 2.5 times the calculated volume requirement will be provided. Adjusted Volume required = 1069 cf * 2.5 = 2673 cf. Volume in pipes = 2 x [(2.5')' a x 40']0.82 = 1335 cf. Volume in gravel = 0.40(40'x20'x6.5' — 1335 co = 1442 cf Total Volume = 1335 cf+ 1442 cf= 2777 cf. > 2673 cf. OK Infiltration rate in area 6.5 in/hr. Drawdown = depth/rate = 6.5' x (12 in/ft) / 4.5 in/hr = 17.33 hrs. < 120 hrs. OK. Predevelopment 1-yrdischarge Q = CIA = 0.67(0.13in/hr)(0.3 I ac) = 0.03 cfs Sheet 1 of 4 Date: 12/14/2009 Designed by: John Peterson, PE Table I Drainage (Roadways and Built -Over Areas) Drain -Inlet Capacities Drainage Section: Project: SOTF Ops Bldg. Additio A = Area (Acres) O = CIA C = Imperviousness Factor I = Intensity (In./Hr.) Design Storm: 10 yr. (Intensity -Duration Curve) 2.8 In./Hr. Location: Ft.Bragg Checked by: Scott Martin, PE Division Office: District Office: Savannah, GA Inlet No. Drainage Area (DA.) In Acres Total A C Average Rough- ness Factor "n., Average Slope "S' in Percent Length L (Feet) Drain -Inlet Capacity Critical Contribution to System Remarks Actual or Effective LengN Feet Equivalen L For n = 0.40 And S = 1 Adopted L For t� Computatio Critical Time, I. Min. Storm Intensity (1) Rate of Supply c.f.s. Critical Time, I. Min. Storm Intensity (1) Rate of Supply c.f.s. Paved Unpavetl Bare Turf C=1.0 C=0.6 C=0.4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1A 0.29 0.29 0.01 5 8.0 2.32 10 6.7 1.94 Roof Drain 1 0.09 0.09 0.01 0.0 65 16 16 10 1 6.7 0.60 1 Catch Basin 2 Existing Catch Basin 5 0.10 0.04 0.40 9.0 112 37 37 20 5.0 0.20 Catch Basin 6 0.08 0.08 0.11 0.40 10.0 35 11 11 20 5.0 0.56 Catch BasJBasin 7BB 0.11 0.11 0.01 5 8.0 0.88 10 6.7 0.74 Roof Drai 78A 0.12 0.12 001 5 8.0 0.96 10 6.7 0.80 Roof Drai 7B Manhole 7AA 0.03 0.03 0.01 5 8.0 0.24 10 6.7 0.20 Roof Drai 7A Manhole 7 0.04 0.02 0.40 5.0 54 24 24 20 5.0 0.08 Catch Bas e -ExistingCatch Gt5A5 Farm 1178 Oct 1987 Note: "Full Size" copies furnished on request to District Project Manager. Sheet 2 of 4 Date: 12J1412009 Designed by: John Peterson, PE Table I Drainage (Roadways and Built -Over Areas) Drain -Inlet Capacities Drainage Section: Project: SOTF Ops Bldg. Addilio A = Area (Acres) O = CIA C = Imperviousness Factor I = Intensity (In./Hr.) Design Storm: 10 yr. (Intensity -Duration Curve) 2.8 In./Hr. Location: FLBragg Checked by: Scott Martin, PE Division Office: District Office: Savannah, CA Inlet No. Drainage Area (DA.) In Acres Total A C Average Rough- ness Factor .W. Average Slope "S" in Percent Length L (Feet) Drain -Inlet Capacity Critical Contribution to System Remarks Actual or Effective Length Feet Equivalen L For n = 0.40 And S = 1 Adopted L For 16 Computation Critical Time, to Min. Storm Intensity (1) Rate of Supply c.f.s. Critical Time, t� Min. Storm Intensity (1) Rate of Supply c.f.s. Paved Unpaved Bare Turf C=1.0 C=0.6 C=0.4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 9A 0.05 0.05 0.01 5 8.0 0.40 10 6.7 0.34 Roof Drain 9T 0.02 0.02 0.01 2.0 5 0 0 1 10 6.7 0.13 Trench Drain 9 0.05 0.05 0.01 1 7 35 1 1 10 6.7 0.34 Catch Basin 108 0.06 0.06 0.01 5 8.0 0.48 10 6.7 0.40 Roof Drain 10A 0.06 0.06 0.01 5 8.0 0.48 10 5.7 0.40 Root Drain 10T 0.02 0.02 0.01 2.0 5 0 0 10 6.7 0.13 Trench Drain 10 0.05 0.05 0.01 1.7 35 1 1 10 6.7 0.34 Catch Basin 11 0.02 0.20 0.10 0.40 3.5 100 53 53 20 5.0 0.50 Existing Catch Basin ULSAS Form 11 /6 Oct 1987 Note: "Full Size" copies furnished on request to District Project Manager. tantrim ff. For Airfields - Suppl,r Canot, Nos. (Based on Design For Tuned Areas: 2-Yr. Ste=) m1111mor Ommm oum ©©o©0000mmmmmmmmmmmmmmm® mmmmm�mmmmmmmmmmmmmmmmmmm• ammam�mmmmmmm mmmmmmmmmm® ammamammmmmmmmmmmmmmmmmm® mmmmm�mmmmmmmmmmmmmmmmmmm. mmmmm�mmmmmmmmmmmmmmmmmmm., ammmmammmmmmmmmmmmmmmmmmm., �mmo��mmmmmmmmmmmmmmmmmm�. mmmm�mmmmmmmmmmmmmmmmmmm.' mmmmm�mmmmmmmmmmmmmmmmmmm. mmmmm�mmmmmmmmmmmmmmmmmmm. mmmmmammmmmmmmmmmmmmmmmmm. mm®mmammmmmmmmmmmmmmmmmmm. mmmm��mmmmmmmmmmmmmmmmmm� SAS Foon 1155 on. ea Previous emeon is obsolete. Note, 'Full Size- copies furnished on request to District Project Manager. Sheet 4 of 4 Designetl by: John Peterson, PE Table III, Airfield Drainage, Roads & Builtover Areas Size and Profile of Underground Storm Drains Drainage Section Prolech SOTF Ops Bldg. Addition Date: 12/14I2009 Location: FLBragg Computed by: John Petersen. PE Checked by: Scott Martin, PE Division Office: Checked by: Scott Martin, PE District Office: Savannah, GA Pipe'n' = 0.012 Inlet or Junction Numbers Distance Between Design Points, in Feel, Measured to G.L. of Inlet or Junction Hydraulic Design Data on Underground Storm Drains Construction Data Notes Design Discharge Capacity, In c.f.s. Trail Design Adapted Design Length of Pipe Between Design Point, In Feet Elevator, of Invert at Design Points, (Col. 2) In Feet Pip. Slope Beoveen Design Points, FIJFt. Mean Velocity of Design Discharge In FUSec. Required Size of Pipe, In Inches Selected Size o/ Pipe, In Inches Hydraulic Grade Line Thru Pie Length Heart Loss at Change in Section Elevation Hydraulic Grade Line, Col. 11, Plus Heart Loss, Col. 15 TT Velocity of Inflow, M In FUSec. Velocity Head N 2g Loss CoefFF cient, K Heart Loss, In Feet, =KN 2g Pipe Slope In Hht. Rise In Feet Elevation at C.L. of Upstream Design Point Incoming Pipe Outgoing Pipe 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2 1 50 2.55 0.003 3.1 15 15 0.003 0.15 283A0 3.1 0.15 0.80 0.12 283.52 50 282A5 11 10 57 2.08 0.030 8.5 12 12 0.030 1.71 296.71 8.5 1.13 0.40 O45 297.16 57 295.71FF SAS Farm 1156 Oct. 84 Previous edition Is obsolete. Note:'Full Size' copies furnished on request to District Project Manager. GEOTECHNICAL ENGINEERING REPORT PROPOSED SOF OPERATIONS ADDITIONS FORT BRAGG, NORTH CAROLINA S&ME Project No. 1031-09-121 Prepared for: Cromwell Architects Engineers 101 S. Spring Street Little Rock, Arkansas 72201 Prepared By: 409 Chicago Drive #116 Fayetteville, North Carolina 28306 October 29, 2009 -I 11W, , ,., . ,, �, . - ,..., , n t1n raj 1,1. October 29, 2009 Cromwell Architects Engineers 101 S. Spring Street Little Rock, Arkansas 72201 Attention: Mr. Joe Hilliard, P.E. Reference: Geotechnical Engineering Report Proposed SOF Operations Additions Fort Bragg, North Carolina S&ME Project No. 1031-09-121 Dear Mr. Hilliard: S&ME, Inc, is pleased to submit this geotechnical engineering report for the proposed new additions to the existing building located at SOF Operations complex at Fort Bragg, North Carolina. Our exploration was performed in general accordance with our proposal No. FAY-159-09, dated May 21, 2009. The purpose of this exploration was to explore general subsurface conditions at the site and evaluate those conditions with regard to site preparation and foundation support for the new building additions. This report presents a summary of pertinent project information, results of our field and laboratory testing, and our geotechnical recommendations and conclusions. Authorization to proceed with this exploration and report was provided through your execution of our "Agreement for Services" Form AS-071 which was incorporated into our proposal. S&ME, Inc. appreciates this opportunity to be of service to you. Please call if you have questions concerning this report or any of our services. Respectfully submitted, S&ME, Inc. � ll ��,.�9/ M. N. Khan..... ' ' w John R. Browning, P.E. Staff Professional J Senior Engineer �Sant. Kea r, 2u .= Project Geo chnicai NC Registration No 239,>6,b' vt`, S&ME Inc. NC PE Finn License No. F-0176 Y Attachments N:\1031UtEPORTS\2009\1031-09-121 SOF Operations Addition\1031-09-121 SOFOpernlions Additions FINALdoc S&ME, INC. / 409 Chicago Drive, Suite 116 / Fayetteville, NO 28306 / p 910.323.1091 f9l0.323.3499/ww%v.srneinc.com Geotechnical Engineering Report SBME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Braqq, North Carolina October 29. 2009 TABLE OF CONTENTS 1. PROJECT DESCRIPTION...................................................................................... 3 2. GEOLOGY.................................................................................................................3 3. EXPLORATION PROCEDURES........................................................................... 3 4. SUBSURFACE CONDITIONS .................................................. 4 4.1 Surface Conditions.............................................................................................. 5 4.2 Fill....................................................................................................................... 5 4.3 Natural Soils........................................................................................................ 5 4.4 Subsurface Water................................................................................................ 5 4.5 Laboratory Test Results...................................................................................... 5 5. CONCLUSIONS AND RECOMMENDATIONS.................................................. 6 5.1 Limitation of Report........................................................................................... 6 5.2 General Assessment............................................................................................ 6 5.3 Foundation Recommendations............................................................................ 7 5.3.1 Shallow Foundations........................................................................... 7 5.3.2 Foundation Alternatives...................................................................... 8 5.3.3 Anticipated Settlements.................................................................... 10 5.3.4 Foundation Evaluation...................................................................... 10 5.3.5 Slabs..................................................................................................11 5.4 Below -Grade Wall Design Considerations....................................................... 11 5.5 Seismic Considerations..................................................................................... 13 5.5.1 Site Class........................................................................................... 13 5.5.2 Potential Liquefaction....................................................................... 13 5.6 Construction Considerations............................................................................. 13 5.6.1 Site Preparation................................................................................. 13 5.6.2 Subgrade Evaluations........................................................................ 14 5.6.3 Excavations.......................................................................................14 5.6.4 Use of on -Site Soils.......................................................................... 14 5.6.5 Structural Fill.................................................................................... 15 5.6.6 Materials Testing During Construction ............................................ 15 2 Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Braqq, North Carolina October 29. 2009 1. PROJECT DESCRIPTION The subject site is located on Fort Bragg at the northeast comer of McKellers and Lamont Roads. Based upon the information provided and gathered during the site visits, the project is expected to include construction of two one-story additions (Gym and Dining Areas) to the existing building on the north-west side and a two story infill building addition (CDD/Signal Area) between existing buildings on the north-east side. Estimated total building area additions are in the range of 61,000 square feet. Besides the building additions the project also includes stormwater retention areas. S&ME, Inc.'s Stormwater Testing Services Report was submitted on October 8, 2009. The planned buildings will consist of load bearing masonry walls with slab -on -grades and elevated slabs. Structural loading information for the building additions were provided by Cromwell Architects Engineers. Maximum column loadings of 100 kips for the dining facility, 110 kips for the gym, and 160 kips for the CDD/Signal buildings are planned. The infill building will consist of continuous footings constructed adjacent to existing building foundations with maximum wall loads of 6 kips per linear foot. Site grading information was not available; however, based upon the planned construction, we assume that there will be grade changes of less than 2 feet. 2. GEOLOGY The site is located on the southwestern edge of the Coastal Plain Physiographic Province of North Carolina. The Coastal Plain Province is typically characterized by marine and eolian sediments that were deposited during the transgressive and regressive depositional sequences of the oceans moving into and out of North Carolina. As such, the Coastal Plain Province is characterized by subdued topographic features and flat, low-lying terrain. Near surface soils often consist of more recent undifferential deposits of interbedded sands, silts and clays. Deeper deposits also consist of sand, silts and clays but can not be defined as particular formations with distinguishable characteristics and engineering properties. K1111111111[*A 1541:7� � L91 1J -Illiq 4 Dili:T*9 S&ME, Inc. drilled eight (8) soil test borings (designated B-1 through B-8) to obtain subsurface information within the proposed building addition footprints. Boring locations were selected and located in the field by S&ME personnel by measuring distances from the existing site features. Since the borings were established without survey control, their locations should be considered approximate. The approximate boring locations are shown on the Boring Location Plan, Figure 1 in the Appendix of this report. Geotechnical Engineering Report SWE Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 The borings were drilled to depths ranging from 10 to 50 feet below existing grades. Borings were performed using 3 Y<-inch hollow stem augers and mud rotary drilling procedures with a CME-750 drill rig equipped with a hydraulic automatic hammer. Samples of subsurface soils were obtained at 2.5-foot intervals above a depth of 10 feet and at 5-foot intervals below 10 feet using a split spoon sampler. Standard penetration testing (SPT) was performed in conjunction with split -spoon sampling in general accordance with ASTM D 1586. Split -spoon samples obtained from standard penetration testing were transported to our laboratory and visually classified in general accordance with Unified Soil Classification System (USCS) guidelines. Standard penetration tests were performed with the attached autohammer and not with a traditional rope, cathead and safety hammer. Research has shown that the standard penetration resistance (N-value) determined by the autohammer is different than the N- value determined by the safety hammer method. Most correlations that are published in the technical literature are based on the N-value determined by the safety hammer method. This is commonly termed N6o as the rope and cathead with a safety hammer delivers about 60 percent of the theoretical energy delivered by a 140 pound hammer falling 30 inches. Several researches have proposed correction factors for the use of hammers other than the safety hammer. The correction is made by the following equation: N6o = Nfield *CE Nfidd is the value recorded in the field and N60 is the value to be used in correlation. CE is the energy correction factor for the hammer used. A correction factor of 1.3 is typically used for the autchammer used during drilling. The boreholes were backfilled using auger cuttings after completion of field operations and after a selected waiting period. Generalized Subsurface Profile drawing (Figure 2) and Boring Logs presenting specific subsurface information from the borings are included in the Appendix. Stratification lines shown on the Boring Logs and profile are intended to represent approximate depths of changes in soil types. Natural transitional changes in soil types are often gradual and vary in both the horizontal and vertical directions. Since ground surface elevations were not available, the test boring depths are referenced from the existing ground surface. 4. SUBSURFACE CONDITIONS Details of subsurface conditions encountered in borings are presented on the Boring Logs in the Appendix, and represent our interpretation of subsurface conditions encountered based upon visual examination of split -spoon samples. General subsurface conditions are discussed in the following paragraphs. Geotechnical Engineering Report SWE Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Braqq, North Carolina October 29, 2009 4.1 Surface Conditions Approximately 3 to 9 inches of topsoil was present at the surface of borings B-1 to B-6. Approximately 7 to 10 inches of concrete was encountered at the surface of borings B-7 and B-8. 4.2 Fill Fill was encountered below topsoil in boring B-5, and below concrete in borings B-7 and B-8 and extended to depths ranging from approximately 3 to 8 feet. In boring B-5 the fill consists of medium dense silty and clayey sands (classified as SM, SC-SM and SC). In borings B-7 and B-8, the fill consists of loose to medium dense silty sands (classified as SP-SM). Standard penetration test (SPT) "N-values" in the fill ranged from 4 to 24 blows per foot (bpf). The SPT N-values at B-5 and B-7 indicate the fill is well compacted whereas at B-8, where about 3 feet of fill exists, these soils appear poorly compacted. Fill soils were typically damp to moist. 4.3 Natural Soils Natural soils were encountered below the topsoil and fill and extend to the boring termination depths. In general, the natural soils consisted of inter -bedded layers of silty and clayey sands (classified as SM, SP, SP-SM, SP-SC, SC-SM and SC). Standard penetration test (SPT) N-values ranged from 7 to 45 blows per foot (bpf) in the sands indicating loose to very dense relative density. Sandy and silty clays (classified as CL and CH) were encountered in borings B-3, B-5, B-7, and B-8 at depths below 27 to 37 feet. The SPT N-values in clays ranged from 5 to 58 bpf, indicating firm to very hard consistency. Natural soils were dry to wet. 4.4 Subsurface Water At the time of boring completion, groundwater was not observed in the borings. Most boreholes had to be backfilled immediately after drilling due to safety concerns. A temporary PVC pipe was inserted into the borehole at B-3 and the water level was measured at 37.5 feet below ground surface after 8 days. It is important to realize that water levels will fluctuate due to such things as season, weather conditions and near -by construction activities. In addition, there is the potential for "perched" water conditions at the ground surface or in the near -surface sand layers because of the underlying less permeable materials (silty or clayey soils), especially after rainfall. Long term monitoring of water levels requires installation of piezometers (temporary groundwater monitoring wells) which was beyond the scope of our report. 4.5 Laboratory Test Results Laboratory testing included natural moisture content and pI-I/resistivity testing on split - spoon samples, and modified Proctor compaction testing on a bulk sample obtained from boring B-6 from an approximate depth of about 1 to 10 feet beneath the existing ground surface. The test results were used to confirm our field classifications and provide index Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 and engineering properties for use in our engineering evaluation. The results of the modified Proctor compaction test indicate a maximum dry density of 119 pounds per cubic foot (pcf) with optimum moisture content 9.4 percent. Laboratory testing of bulk soil samples indicates resistivity values ranging from about 5,733 to 8,229 ohm -centimeters and pH values ranging from 6.2 to 6.9. It has been our experience that soils with the above resistivity and pH values are generally considered to have a slight corrosion potential. As such, it is our opinion that any underground metal pipes will not require cathodic protection. All laboratory testing was performed in general accordance with applicable ASTM standards and results are attached in the Appendix. 5. CONCLUSIONS AND RECOMMENDATIONS 5.1 Limitation of Report This report has been prepared in accordance with generally accepted engineering practice for specific application to this project. Any wetland, environmental, or contaminant assessment efforts are beyond the scope of this geotechnical exploration; and therefore, those issues are not addressed in this geotechnical exploration report. The recommendations contained in this report are based on the applicable standards of our profession at the time this report was prepared. No other warranty, express or implied, is made. Analysis and recommendations submitted in this report are based upon the data obtained from the geotechnical exploration, our engineering analysis and our understanding of the proposed construction. The nature and extent of variations between and outside of the boring locations may not become evident until construction. If variations appear evident, then it will be necessary to re-evaluate the recommendations of this report. In the event that the assumptions presented in this report regarding site grades, structural loads, or location of the proposed structures are incorrect, the recommendations contained in this report should be reviewed and modified or verified in writing. We strongly recommend S&ME be provided the opportunity to review the final design plans and specifications in order that earthwork and foundation recommendations are properly interpreted and implemented. The recommendations in this report are contingent on S&ME, Inc.'s observation and monitoring of grading and construction activities. 5.2 General Assessment The following conclusions and recommendations are based upon a review of test boring and laboratory data, our understanding of planned construction, our engineering analysis Geotechnical Engineering Report SWE Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29. 2009 and experience with similar projects and subsurface conditions in the Fort Bragg area. If structural loads or design grades change significantly from those presented in this report, we should be contacted to confirm or modify recommendations as necessary. Additionally, if subsurface conditions different than those indicated by this report are encountered during construction, these differences should be reported to us for review and comment. In general, the subsurface conditions at this site appear suitable for support of the proposed one and two story building additions, however, loose fill soils exist at B-8. These soils will require repair (undercut and replacement) prior to slab construction. Based on the test boring data, the existing fill appears to be generally free of debris and organics and has received adequate compaction, except at B-8, for support of this structure. If necessary, excavated fill soils can be reused as structural fill. Structural fill placed on site should be placed in 8 to 10 inch lifts and compacted to at least 95% of the soil's modified Proctor maximum dry density. The Geotechnical Engineer should verify prior to concrete placement whether the exposed foundation bearing soils are suitable for the design soil bearing pressure. When reviewing our recommendations, please note that the site has been previously developed (fill has been placed and numerous utility lines installed). Based on our experience, unexpected conditions often exist at previously developed sites. Unexpected conditions may consist of low -consistency fill soils (which exist at B-8), debris -laden fill, active or abandoned utilities, and other conditions. Any unexpected conditions encountered on site can be addressed by engineering evaluations during construction. Our recommendations regarding site preparation, subgrade repair, field evaluations, and foundation support are presented in the following sections of this report. 5.3 Foundation Recommendations 5.3.1 Shallow Foundations The proposed structures may be supported on shallow foundations bearing in approved existing fill soils, natural soils, or new well compacted fill soils. Footings may be designed for an allowable soil bearing pressure of 2,500 pounds per square foot (psf). Continuous wall footings should be a minimum of 18 inches wide and column footings should be at least 24 inches wide to help prevent localized or "punching" shear failure which can occur with very narrow footings. Foundations should be embedded at least 18 inches below finished grades to provide adequate embedment against frost penetration. New foundations should be designed with sufficient separation from the existing building foundations so as not to undermine them during excavation or cause foundation stress overlap. If foundation stress overlap cannot be avoided then the affected existing foundations should be evaluated for additional settlement. Also if significant fill loading will occur adjacent to existing structures the effect of this loading on the structure should be evaluated. Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29. 2009 If perched water or groundwater collects in foundation excavations, it should be removed promptly to help prevent softening of foundation supporting soils. To further reduce the potential for deterioration of bearing soils, we recommend that foundation excavation and placement of concrete be conducted on the same day if practical. 5.3.2 Foundation Alternatives We understand that at the gym addition, the existing foundations and finished floor elevations are about 8 to 10 feet below the final grades for the new gym addition. We understand the existing grades in the new gym addition area are close to the proposed final grade. An existing foundation wall allows this grade separation. In order to prevent additional loading on the existing lower footings, a system of grade beams supported by a deep foundation will be constructed along the column lines closest to the existing structure. A deep foundation system capable of supporting the column's axial and bending moment loads will be required to transfer loads below the lower foundation wall footings. Helical piers and drilled shafts are acceptable alternatives to support these cantilevered columns. Due to vibration concerns we did not consider a driven pile solution. Helical piers have been proposed beneath wall footings at the CDD/Signal addition building. The helical piers will help transfer loads to a deeper bearing stratum without imposing additional loads onto the existing footings. It is our opinion, that helical piers can support the adequate design loads in this area. It is our opinion the drilled shafts and helical piers will create a stiff foundation (assumed negligible settlement) relative to the new surrounding shallow spread footings. Therefore, new surrounding shallow spread footings adjacent to shaft or pier supported footings may experience greater than 1/2 inch of differential settlement. The structural engineer should determine if these magnitudes of settlement are acceptable for the planned structure. 5.3.2.1 Helical Piers Helical piers are installed by turning a steel pier with a helical tip to a depth where competent bearing soils exist. Once the pier is installed to suitable bearing materials, it is mechanically attached to the footing. Design and installation of helical piers is typically a design -build component, with the installer detenn fining the number of piers, allowable capacity and depth of installation. It is our understanding that specified helical piers can be hydraulically turned into the dense or stiff soils with sufficient torque to develop design capacities ranging from approximately 5 to 10 kips. Helical piers would need to be installed to depths of at least 15 to 20 feet below existing grades in the areas of borings B-7 and B-8 to bear in dense to very dense soils (CDD/Signal addition) . The piers should be spaced accordingly depending on the actual structural loading per linear foot of wall. Geotechnical Engineering Report SWE Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 5.3.2.2 Drilled Shafts Drilled shaft design parameters are presented in the following sections. Because of the concern of ground loss and reduction of foundation soil support for the lower gym wall footing, we recommend that the drilled shaft be cased the entire length during the drilling and concreting operations. Axial Capacity Based on encountered subsurface conditions, allowable resistance values in the following table may be used in designing the drilled shaft foundation system for axial loads. These values include a factor of safety of at least 2.0. DEPTH SIDE FRICTIONAL ALLOWABLE END (feet) SOIL TYPE CS US ; RESISTANCE BEARING' CLASS (kst) {ksf) 0-10 Clayey Sands. SC N/A N/A 10 - 17 Silty Sands SM 0.75 N/A 17 - 32 Fine Sands SP 1.2 10 32 — 41 Sandy Clay CL 0.2 3 41 - 50 Fine Sands SP 1.0 10 We recommend that the upper ten feet of depth be neglected in the side frictional resistance calculations due to the potential disturbance of the upper soils during the construction process. Also installation of a drilled shaft deeper than about 32 feet may encounter groundwater which will require in addition to the steel casing a drilling fluid be used so that unbalanced hydrostatic forces do not disturb the bearing soils. Lateral Resistance The following design values are intended to be used with the MILE 4.0 plus computer program for the analysis of drilled shafts subjected to lateral loading. We recommend that a groundwater level corresponding to a depth of 32 feet below the existing ground surface be used in the analysis. Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 S0D' De 0t feet TYPE' uses J LPILE SOIL COHESION ,F.gNG EN �, �� vCLASS ,TYPE �(Ps>) t de eesvtip WEIGHT W'(pc�' n t / -', IAI.Lti Clayey 0-10 Sands SC Sand 0 30 115 60 -- silty 10— 17 Sands SM Sand 0 28 120 20 -- Fine 17-32 SP Sand 0 35 120 125 — Sands 32-41 Cl yy CL Clay* 750 0 110 too 0.01 Fine 41-50 SP Sand 0 32 120 125 — Sands * Stiff Clay with Free Water ** K refers to modulus of horizontal subgrade reaction used in LPILE plus computer code and assumes "static' loading as described by LPILE user manual. 5.3.3 Anticipated Settlements Our settlement analysis indicates that total settlement due to the anticipated structural loads (i.e., 100 to 160-kip columns, <6-kips/foot walls) and a design soil bearing pressure of 2,500 psf will be about 1 inch or less. Differential settlements within the new structure are estimated at 1/2 inch or less. However if the new building will be structurally connected to the existing structure, differential settlement between the two structures could approach the total settlement value. Also as mentioned above with the new gym wall adjacent to the existing wall being supported on a deep foundation, the differential settlement of surrounding new shallow foundations and this wall could approach the total settlement value. The above settlements assume that footings are evaluated in the field and uniform and adequate bearing conditions exist. The structural engineer should determine if these magnitudes of settlement are acceptable for the planned structure. 5.3.4 Foundation Evaluation We recommend that the project Geotechnical Engineer or his representative observe the foundation bearing conditions prior to placement of reinforcing steel and concrete. This evaluation should include the performance of shallow hand auger borings with dynamic cone penetrometer (DCP) testing to depths of 3 to 4 feet to evaluate the suitability of underlying soils for foundation support. Evaluation of all foundation bearing soils is strongly recommended since many of the footings may bear in existing fill soils. Foundation excavation or exposure to the environment will cause the bearing surface soils to loosen or soften. Softened/loosened soils at the foundation surface bearing should be removed or densified in -place with acceptable compaction equipment such as a "jumping jack" or vibratory plate compactor. Any excessively loose/soft soils or other 10 Geotechnical Engineering Report SWE Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 unsuitable materials should be repaired prior to concrete placement. Repairs are typically performed by undercutting loose/soft soils and backfilling with washed stone (NCDOT No. 57 stone). Monitoring of the installation of helical piers and drilled shafts should be performed by the project Geotechnical engineer to verify that the intent of the design plans and specifications has been met. 5.3.5 Slabs Slabs may be supported on suitable in -place soils as determined by a geotechnical engineer in the field, or on properly placed and compacted new fill, provided the site preparation and fill placement procedures outlined in this report are implemented. Provided that the subgrade preparation and fill placement recommendations described herein are implemented, a modulus of subgrade reaction value of 120 psi/inch may be used to design the at -grade slabs. The slab should be separated from continuous wall and interior column footings to allow for relative displacement. Any "thickened slab" areas or "turned down" edges should be considered part of a shallow foundation system. We recommend that a minimum 4 inch layer of compacted NCDOT crushed aggregate base course (ABC stone) be placed beneath floor slabs as soon as possible after grading of the building pad. The ABC stone layer will provide a more stable and durable construction surface and greater uniformity in slab support. Exposure to the enviromnent and construction activities will weaken the subgrade soils. Therefore, we recommend that subgrade soils in slab areas be evaluated prior to ABC stone placement. If deterioration of the soils has occurred, in place densification or undercutting may be necessary. 5.4 Below -Grade Wall Design Considerations The location and depths of below -grade walls with respect to our borings are not known at the time of this report. Once additional information is available, we should be contacted for any additions or revisions to our recommendations that may be appropriate. The site's below -grade walls should be designed to withstand loading from lateral earth pressures from surrounding soil and surcharge loads from nearby footings or slabs. The lateral earth pressures presented below assume the walls will not be subjected to hydrostatic loading conditions, that is, water will not be present behind the walls due to surface water or groundwater. Recommended parameters for design of below -grade walls are given in the table below. 11 Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 Design Parameters for Below Grade Walls Parameter Value Soil Friction Angle (�) for On Site Sandy Soils 300 At -Rest Earth Pressure Coefficient (Ka) 0.50 Active Coefficient Earth Pressure (Ka) 0.33 Passive Earth Pressure Coefficient (Kp) 3.00 Moist Unit Weight ofBackfill 125 pcf Friction Coefficient b/w Foundation and Bearing Soil 0.35 Based on the parameters given above, fixed walls (such as basement walls) that are not allowed to rotate (at -rest condition) should be designed using a triangular earth pressure distribution having an equivalent fluid weight of 63 pounds per cubic foot (pcf) per foot of wall height, assuming full wall drainage is provided. For walls that will be allowed to rotate (i.e. retaining walls), then the equivalent fluid weight would be 41 pcf. Retaining walls should have adequate factors of safety against overturning, sliding, and global failure. The structural engineer should select the appropriate loading condition based on the below -grade wall configuration. Lateral pressures from any surcharge loads (traffic, adjacent foundation elements) should be added as a uniform rectangular soil pressure equal to 50% the vertical pressure applied over the full height of the wall. The lateral earth pressure distribution presented above assumes no wall friction between the wall and soil backfill (S = 0 degrees), the backfill soils consist of on site sandy soils (SM, SP, SC), the backfill is level and has been properly placed and compacted, and that water is not allowed to accumulate behind foundation walls. Exterior grades should promote rapid drainage away from the structure. Free draining clean stone backfill (such as NCDOT No. 57) should be placed behind the wall (separated from the backfill soils with a nonwoven geotextile fabric) or prefabricated drainage panel should be applied to the back of the wall to prevent the build up of hydrostatic pressures (utility break, long rainfall event, etc.). The wall should have an internal drainage system or have weep holes that allows any collected water to drain away from the wall. Backfill soils placed behind below ground walls should be granular and compacted to at least 95% of the soil's modified Proctor maximum dry density (ASTM D 698) and within 2% of the optimum moisture content. Operating heavy compaction equipment within 5 feet of the walls can create lateral earth pressures in excess of those recommended for design. As such, hand -operated equipment should be used within 5 feet of below -grade walls. 12 Geotechnical Engineering Report SBME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 5.5 Seismic Considerations 5.5.1 Site Class A Seismic Site Class was determined based on the soil conditions encountered by the borings and in accordance with the 2006 Intemational Building Code. Based on the soil strength information (Standard Penetration Test (SPT) "N-value") obtained at boring B-3, a `Site Class D' is recommended for the design of the structure. 5.5.2 Potential Liquefaction The liquefaction] susceptibility of the on -site soils was evaluated using the 2006 International Building Code design earthquake.2 Liquefaction is the loss of a soil's shear strength due to the increase in pore -water pressure resulting from seismic vibrations. Soils most susceptible to liquefaction generally consist of saturated, loose, "clean" (i.e., plasticity indices less than 5), fine (10% size ranging from 0.07 to 0.25 mm) sands. The results of the liquefaction analysis indicate that the sands at this site have a relatively low potential for liquefaction due to the design earthquake. 5.6 Construction Considerations If during foundation excavation subsurface conditions are encountered that are different from our boring exploration, we recommend that S&ME be informed of such conditions. This information will help us in making recommendations regarding such options as densification and/or additional localized undercutting at the foundation bearing level. Prior to any additional fill placement or construction of the slabs on grade, we recommend the subgrades be proofirolled with a loaded dump truck to identify any unstable areas that may require repair. The proofroller should make at least two complete passes over the subgrade areas at walking speed. Surface repair could include undercutting and replacement, drying and recompaction, or other measures recommended by the geotechnical engineer. 5.6.1 Site Preparation Site preparation should begin with the removal of all existing concrete walkways, existing concrete slabs, trees, vegetation, topsoil and other unsuitable surface materials within the proposed construction limits. Stripping should occur for a minimum of 10 feet beyond building footprints. Topsoil may be stockpiled on site and reused in landscaped areas. Any voids created from the removal of underground objects should be backfilled with compacted structural fill. Experience indicates that backfill associated with existing Liquefaction is the loss of a soil's shear strength due to the increase in pore water pressure resulting from seismic vibrations. 2 The 2006 IBC design earthquake has a 93 % probability of non-cxcecdancc in 50 years. Our liquefaction analysis was based on an earthquake with a magnitude of 7.3 and ground surface acceleration of 0.13g 13 Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 utilities is often poorly compacted. Also, cracked or deteriorated pipes can collapse or serve as conduits for subsurface erosion, either of which can result in excessive settlement and damage to structures. We recommend that existing utilities located within the proposed building areas be removed and the trenches properly backfilled with suitable compacted structural fill. Utilities that will remain in -place should be evaluated on a case -by -case basis. This evaluation should include assessment of backfill, conduit type, future loading, and the proximity of utilities to the new building. 5.6.2 Subgrade Evaluations After the site clearing, grabbing and topsoil stripping operations are completed, and prior to new fill placement and slab on grade construction, exposed subgrades should be evaluated by the project Geotechnical Engineer. This evaluation helps to reveal the presence of any unstable or otherwise unsuitable near -surface materials. This evaluation should consist of proofrolling of the building area using a loaded tandem -axle dump truck. Any areas which are observed to rut, pump or deflect excessively during proofrolling will require undercutting and replacement or subgrade repair. Specific recommendations regarding subgrade repair are best given in the field by the Geotechnical Engineer at the time of evaluation. Because of the very loose fill soils found at B-8 to a depth of about 3 feet, undercut and replacement of these soils will be required. 5.6.3 Excavations Difficult to excavate materials were not encountered within the depths of the borings. Our experience indicates that the on site soils can likely be excavated using conventional grading equipment. During foundation and utility excavations, excavation sidewalls will likely remain stable for only a brief period of time. Backfilling of undercut foundations (if necessary) should be conducted as soon as practical to limit sidewall caving and any groundwater infiltration into the excavation. Any material that caves into the design undercut should be removed prior to backfilling. Foundation undercut should be performed in sections or one at a time, and NCDOT No. 57 stone should be stockpiled at the site for immediate backfilling in an effort to prevent sidewall sloughing. Forming may also be required. All excavations should be sloped or shored in accordance with local, state, and federal regulations, including OSHA (29 CFR Part 1926) excavation trench safety standards. The contractor is solely responsible for site safety. This information is provided only as a service, and under no circumstances should S&ME be assumed to be responsible for construction site safety. 5.6.4 Use of on -Site Soils The on -site natural and clean existing fill soils should be suitable for reuse as structural fill provided the soil moisture contents can be properly controlled during placement and compaction and that soils are relatively free of organics (less than 3%). Some moisture conditioning may be required to achieve adequate compaction. Drying can normally be accomplished by aerating the soils during favorable weather conditions (i.e. sun and wind). 14 Geotechnical Engineering Report S&ME Project No. 1031-09-121 Proposed SOF Operations Additions, Fort Bragg, North Carolina October 29, 2009 5.6.5 Structural Fill If any off -site structural fill is required to be placed within the building additions, it should have a low plasticity (plasticity index less than 20%), be free of debris, and relatively free of organics (less than 3% by dry weight). Structural fill should have a minimum dry density of 100 pounds per cubic foot based on the laboratory modified Proctor (ASTM D1557) test. We recommend the fill soils have Unified Soil classifications of SP, SW, SM or SC. All structural fill should be placed in 8 to 10-inch loose lifts and compacted to at least 95 percent of the modified Proctor maximum dry density (ASTM D1557). Soil moisture should be maintained within two (2) percent of the optimum moisture content during compaction. Site preparation including fill placement and compaction should be observed by the project Geotechnical Engineer or a qualified soils technician. A sufficient number of density tests should be conducted on each soil lift to evaluate whether adequate compaction has been achieved prior to additional fill placement or foundation construction. 5.6.6 Materials Testing During Construction Field evaluations and testing will be very important during construction. It is recommended that a soils technician working under the direction of the project Geotechnical Engineer be present during subgrade preparation, additional fill placement and foundation installation. During the fill placement activities, it is recommended that the soils technician perform field density tests to confirm compaction of fill soils is achieved. It is recommended that all foundation bearing surfaces be evaluated by the project Geotechnical Engineer or senior engineering technician under his direction prior to concrete placement. 15 October 8, 2009 Cromwell Architects Engineers 101 South Spring Street Little Rock, Arkansas 72201 Attention: Mr. Joe Hilliard, P.E. Reference: Stormwater Testing Services Proposed SOF Operations Addition Ft. Bragg, North Carolina S&ME Project No. 1031-09-121 Dear Mr. Hilliard: S&ME, Inc. is pleased to provide this report for stormwater testing services at the above - referenced site. S&ME was requested by you to perform these services in preparation for the planned site improvements. S&ME has conducted these services in general accordance with S&ME Proposal No. FAY-169-09 dated May 21, 2009. Project Background The project site is located on the existing SOF campus located in the western portion of Fort Bragg. We understand an expansion to the facility is planned. The new site work will include additional buildings, and stormwater Best Management Practices (BMP) facilities planned in three areas of the site. Two of the test areas are located in landscaped areas, and the third is located between to sections of the existing building and was covered with concrete at the time of our evaluation. Concrete coring was, performed at this location to access the underlying soil. Apparent grading activities have occurred at the campus, the extent of which is not known. Findings Seasonal High Water Table Evaluations and In -Situ Soil Permeability Testing The seasonal high water table evaluations were performed on October 1, 2009 by advancing hand auger borings to depths ranging from approximately 72 to 96 inches below the existing ground surface at the approximate locations, B-1, B-6 and B-7/B-8, as shown on Figure 1. S&ME, INC. / 409 Chicago Drive, Suite 116 / Fayetteville. NC 28306 1 p 910.323.1091 / 910.323.3499 / www.smeinc.com Stormwater Testing Services S&ME Project No. 1031-09-121 Proposed SOF Operations Addition, Ft. Bragg NC October B. 2009 Soils were evaluated under the guidance of a Licensed Soil Scientist for evidence of seasonal high water table influence. This evaluation involved looking at the actual moisture content in the soil and observing the matrix and mottle colors. Depending on the soil texture, the soil color will indicate processes that are driven by seasonally high water table fluctuations, such as iron reduction and oxidation and organic matter staining. A hand auger boring profile sheet that provides a description of the observed soil horizons and the determined seasonal high water tables has been included with this report. The soils at the test locations were observed to range from fine sand to clay. Apparent fill material was encountered at location B-7 where the upper approximately 44 inches appeared to be fill material. Topsoil/fill material was encountered at locations 13-1 and B-6, and rock was encountered at B-1 preventing evaluation of the soils below 6 feet. The seasonal high water table was determined to be greater than 8 feet below the existing ground surface at locations B-6 and 13-7/13-8, respectively. The seasonal high water table was not encountered above the rock at location B-1; however, soil wetness conditions were encountered in the soil above the rock. A large rock outcropping was observed at the ground surface approximately 20 feet south-southeast of B-1. See Table I below for the seasonal high water table depth at each test location. S&ME performed the in -situ soil hydraulic conductivity testing by using a compact constant head permeameter at the test locations. Hand auger borings were advanced to depths ranging from approximately 48 to 72 inches below the existing ground surface with a 2-inch diameter bucket. A planer auger was used to clean the bottoms of the holes and give them a cylindrical shape. The water dissipating unit was lowered to the bottom of each hole, and water was dispensed from the permeameter. The water was allowed to move through the unit until steady-state flow was achieved, and then flow rates were recorded. The last three measurements at each location were averaged to achieve the most representative value to express the saturated hydraulic conductivity. The depth interval of the test corresponded to a layer of material approximately 6 inches thick at the selected testing depth. The permeability rates were calculated as ranging from 0 to 8.83 inches per hour. See the Table 1 below for the hydraulic conductivity rates for each test location. Please note that due to the presence of concrete at locations B-7 and B-8 and our efforts to reduce number of cores, the seasonal high water table evaluation was performed at B-7 and the hydraulic conductivity testing was performed at B-8. TABLE 1 TEST. „ LOCATION . TESTING INTERVAL inches below surface) SEASONAL HIGH WATER TABLE inches below surface HYDRAULIC CONDUCTIVITY RATE B-1 42 to 48 inches > 6 feet 0.00 inches/hour 0.01 cin/hour B-6 54 to 60 inches > 8 feel 8.83 inches/hour I3-7/13-8 66 to 72 inches > 8 feet 4.58 inchesihour 3 Stormwater Testing Services SWE Project No. 1031-09-121 Proposed SOF Operations Addition, Ft. Bragg, NC October B 2009 See Figure 1 (attached) for the approximate test locations. The presence of rock encountered at approximately 6 feet below the existing ground surface at location B-1 could be resulting in perched water above the rock, thus resulting in a low hydraulic conductivity rate. Excavation of the rock in this area could be a possibility; however, North Carolina Division of Water Quality (DWQ) design and citing requirements for specific BMPs should be reviewed prior to soil improvement activities in order to maintain compliance with the requirements. Please note that these seasonal high water table evaluations are based on secondary evidence and not on direct groundwater level measurements. Groundwater levels fluctuate for numerous reasons, and these findings do not indicate that groundwater levels have not or will not rise above the noted depths. Closing S&ME appreciates the opportunity to provide these services to you. If you have any questions, please contact us. Sincerely, S&ME, Inc. Paul Masten Staff Professional Senior Review by: Robert P. Willcox, Jr., L.S.S. PAM:RPW/jns A�— Brian D. Keaney, P.E. Project Engineer Attachments: Figure 1 — Approximate Test Location Sketch Soil Boring Profiles y --I I.._. I i r - �I N j B-7 i'11, Arai® B-8 � ArAIM4 14-I'AFY >.'ro r. [I'll -AV'=''+Iz✓ URC. R!->JL '470 WATAF.." Yll ' A•,u u,+n ra - . F:l'Y NEO )LO'T H V'AK IX%Vl,:1 W',II J-CY LI:C , •y -O-T FFtSr I 1 .G II118l1i I 1Y`_I i= t 3_I:1I4C Y4 aHi 2' 1 I fll n t:X a+.YITIRY I F T li` + Approximate I` Location of + Rock Outcrop - ,. t I + g -A I !% I>, Nclf skITASy II , ilsr B� ._. .. �r ..,�—:._�.. .: , �I o I J i it .. I. ---'�77—, - � --.;9.-�'?.� -•� ---_ � I , i - +a,l o t s�tral.,. Ir,l i, + I � ..cam i yry Ill1's\tI , I ...... • r..._.-.<`-----w..—a���—. !i I.S. �:: I 11`\\,j �V� - � ✓ 1 i ,� IC15 T, IIlIII Iii.� `II tl r p + 1. �i • / '.:� FIW C LOT%B'�'t i` Lt:.!.i,171 I u•I r�.... ttY,' t, Y i sli >• ,,_ N:.IdME TIER UIN—VI. SAk 1..,u` 111.1 Note: Drawing provided to S&ME by Cromwell Architects and Engineers personnel. LEGEND SCALE: UNKNOWN STORMWATER TESTING LOCATION SKETCH FIGURE CHECKED BY: PAM SOF OPERATIONS ADDITION NUMBER ® Approximate *S&ME1 FORT BRAGG, NORTH CAROLINA Test Location DRAWN BY: JNS DATE: 105-09 1 S&ME PROJECT NUMBER: 1031-09-121 .as Seasonal High Water Table Evaluations Soil Descriptions SOF Operations Addition Fort Bragg, North Carolina S&ME Project No. 1031-09-121 Matrix Mottle Depth HucNalue HucNalue Location Horizon(Inches) /Chroma /Chroma Texture/Structure B-I Ap 0-3 1 OYR 4/2 Loamy sand, granular Bw 3-72+ 7/5YR 4/6 Sandy loam, weak sub -angular blocky R 72+ Rock Seasonal High Water Table not determined due to presence of rock at 72 inches. Soil wetness observed in the Bw horizon above the rock. B-6 Fill 0-6 1 OYR 3/1 Fill, topsoil Fill 6-17 5YR 4/6 Apparent fill E 17-26 2.5Y 6/6 Fine sand, single grain EB 26-56 l0YR 5/6 Loamy sand, granular Btl 56-96+ 5YR 4/6 Sandy clay loam, moderate blocky Seasonal High Water Table > 8' below the existing ground surface. B-7/B-8 Fill 0-36 2.5Y 5/3 Fill 36-44 2.5Y 616 Btl 44-63 7.5YR 4/6 Bt2 63-92 7.5YR 4/6 Bt3 92-96+ 5 YR 3/4 10YR 4/2 Fill 10YR 5/6 1 OYR 4/2 Fill Sandy clay loam, moderate blocky 7.5YR 5/8 Clay, strong blocky Sandy clay loam, moderate blocky Seasonal High Water Table > 8' below the existing ground surface. BORING LOCATION PLAN SOF Operations Additions Fort Bragg, North Carolina Job No. Scale: Figure No. Prepared by 1031-09-121 Not Shown mnk LEGEND TO SOIL CLASSIFICATION AND SYMBOLS SOIL TYPES (Shown in Graphic Log) Fill Asphalt Concrete Topsoil Gravel CONSISTENCY OF COHESIVE SOILS STD. PENETRATION RESISTANCE CONSISTENCY BLOWS/FOOT Very Soft 0 to 2 Soft 3 to 4 Firm 5 to 8 Stiff 9 to 15 Very Stiff 16 to 30 Hard 31 to 50 Very Hard Over 50 RELATIVE DENSITY OF COHESIONLESS SOILS Sand RELATIVE DENSITY Very Loose Silt Loose Medium Dense Dense Clay Very Dense Organic Silty Sand Clayey Sand Sandy Silt Clayey Silt Sandy Clay Silty Clay Partially Weathered Rock Cored Rock WATER LEVELS (Shown in Water Level Column) SL = Water Level At Termination of Boring 7_ = Water Level Taken After 24 Hours � = Loss of Drilling Water HC = Hole Cave STD. PENETRATION RESISTANCE BLOWS/FOOT 0to4 5to10 11 to 30 31 to 50 Over 50 SAMPLER TYPES (Shown in Samples Column) Shelby Tube m Split Spoon m Rock Core No Recovery TERMS Standard - The Number of Blows of 140 lb. Hammer Falling Penetration 30 in. Required to Drive 1.4 in. I.D. Split Spoon Resistance Sampler 1 Foot. As Specified in ASTM D-1586. REC - Total Length of Rock Recovered in the Core Barrel Divided by the Total Length of the Core Run Times 100%. RQD - Total Length of Sound Rock Segments Recovered that are Longer Than or Equal to 4" (mechanical breaks excluded) Divided by the Total Length of the Core Run Times 100%. *S&ME ENGINEERING • TESTING ENVIRONMENTAL SERVICES 0 5 10 15 20 n 25 x a w 30 0 35 40 45 50 55 B-1 N 15 B-2 N 15 7 83 N 13 B-4 N �'I 13 B-5 N 15 B-6 N 18 B-7 N 16 B-8 N 4 �' I �� .,. 11 22 .12 9 24 ' 8 �1 9 HC HC- 13 8 15 12 19 9 20 9 14 15 33�- 24 21 �' 18 25 28 BT@10' -� _.� 3T@10' ' 35 _.'� 17 -' 27 12 17 36 i -' 19 '�,'. 41 14 '� 21 11 ' 11 10 27 12 12 6 .': 18 BT @ 30' BT @ 30' BT @ 30' 5 7 18 1 10 6 58 BT@40' BT@40' 19 20 BT@50' ® Topsoil '. �'�:_ SM, Silty Sand FA SC, Cayey Sand SC/SM, Clayey Sand ❑�'' SP/SM, Poorly -graded Sand with Silt ® CL, Low Plasticity Clay SP/SC, Poorly -graded Sand with Clay ® Fill SP, Poorly -graded Sand Concrete ® CH, High Plasticity Clay N = Standard Penetration Test resistance value (blows per foot). The depicted stratigraphy is shown for illustrative purposes only. The actual subsurface conditions will vary between boring locations. JOB NO: 1031-09-121 Generalized Subsurface Profile 409 Chicago Drive, Suite 116 S&MEProject: SOFOperationsAddition Figure 2 - - Fayetteville, NC 28306 DATE: 10/28/09 Location: Fort bragg, NC PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-1 SBME Project No. 1031-09-121 DATE DRILLED: 9/29109 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 10.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING FASTING: DRILLING METHOD: TA" H.SA. w -> w BLOW COUNT O > Z 9 o- ICORE DATA STANDARD PENETRATION TEST DATA w w w o w a s o(Nwsm)_ > o w w -- /REMARKS c7 ¢ w N E Z 3 E 10 20 30 6080 TOPSOIL SILTY SAND (SM) 1 6 7 6 15 medium dense, orange -red with brown, fine to medium, moist 2 6 6 5 5 HC _ 3 5 5 6 13 CLAYEY SAND (SC) medium dense, re -orange, fine, damp - q 6 6 8 14 10 Boring terminated at 10 feet NOTES: 1. THIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUST ONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCE WTM A�TMD-1586. 3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 0. WATER LEVEL IS AT TIME OF EXPLORAT/ONAND WILL VARY. Page 1 of 1 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-2 S&ME Project No. 1031-09-121 WATER LEVEL: NORTHING: I EASTING: U > p -> w z c> BLOW COUN I CORE DATA STANDARD PENETRATION TEST DATA w F= L7 o MATERIAL DESCRIPTION m w ti 1- x z �' o (blowslk) o a W a a REMAR s z 3 0 h e A_ ,E, 10 20 30 6080 TOPSOIL CLAYEY SAND (SCSM) 7 1 5 7 8 is medium dense, red -brown, with silt, trace gravel, damp . CLAYEY SAND (SC) 2 6 10 12 22 medium dense to loose, red -orange, with silt, j trace gravel, fine, damp 3 3 5 8 CLAYEY SAND (SC) medium dense, red, fine, damp 4 a 7 8 15 10 j SILTY SAND (SM) medium dense, red -brown, some clay, fine to coarse, moist 5 4 4 7 11 15 SAND (SPSM) dense, red, with silt, fine to coarse, poorly graded, moist 6 11 17 18 35 ) f. SAND(SPSM) medium dense, yellow -tan, with silt, and clay lenses, fine to medium, poorly graded, damp 7 5 9 10 19 25 ;.{. i. SILTY SAND (SCSM) medium dense, yellow -tan, with clay, fine to medium, moist 8 3 5 5 : : 10 30 Boring terminated at 30 feet 1. THIS LOG IS ONLY A PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUSTONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCE WRH ASTM D-1586. 3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOTEXACT. G. WATER LEVEL IS AT TIME OF EXPLORATIONAND WILL VARY. Page 7 Or 7 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-3 SBME Project No. 1031-09-121 DATE DRILLED: 9I29/09 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 50.0 ft DRILLER: Jason White WATER LEVEL: 37.5 feet after 8 days HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: FASTING: DRILLING METHOD: 3'/." H.SA. j -- w O BLOW COUNT /CORE DATA STANDARD PENETRATION TEST DATA w w o MATERIAL DESCRIPTION w> m a W - > ❑ W a REMARKS 0N 3 w Q F 2 0 y Z 10 20 30 6080 TOPSOIL SILTY SAND ISM) 1 4 4 9 13 .�.:. medium dense, brown -red, with clay, fine, damp CLAYEY SAND (SCSM) medium dense, brown -red, with silt, fine, moist 2 5 5 7 12 5 CLAYEY SAND (SC) medium dense, red, with silt, fine, &mP 3 6 7 B 15 .:.:, SILTY SAND (SM) ..I . dense to loose, brown -orange, trace clay, fine to 4 7 75 18 33 t0 medium, moist 5 3 3 4 7 15 L:. SAND (SPSM) medium dense to very dense, red -orange, with } silt, fine to coarse, poorly graded, moist 5 4 7 10 ! 17 20 . a. {.. } e. 7 16 22 19 41 25 {. `I .. SAND (SPSM) }'! dense, red -orange, with silt, fine to medium, poorly graded, moist B 9 12 15 27 30 ..{. �. SANDY CLAY (CL) firm to stiff, light gray, with silt, moist - 9 2 2 3 5 NOTES: 1. THIS LOG /S ONLYA PORTION OF A REPORT PREPARED FOR THE NAMED PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA/N GENERAL ACCORDANCE WRH AS�TM PIW6. 1 STRATIFICATION AND GROUNDWATER DEPTHS ARE NOTEXACT. s. WATER LEVEL IS AT TIME OF EXPLORATIONAND WILL VARY. krU Page 1 of 2 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-3 S&ME Project No. 1031-09-121 NOTES: CME 750 MATERIAL DESCRIPTION SANDY CLAY (CL) firm to stiff, light gray, with silt, moist (continued) 40 SAND (SPSC1 medium dense, orange -yellow, with silty r,10y, fine to coarse, poorly graded, wet 45' SAND (SPSM) medium dense, orange -yellow, with silt, fine, `}.}. poorly graded, wet 50 Boring terminated at 50 feet 1. MIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECTAND MUST ONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TESTDATA IN GENERAL ACCORDANCE WO A$TM D-1596. 1 STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 4 WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. after 8 NORTHING: I EASTING: i ^ W a- bLUW WUfVI ICORE DATA STANDARD PENETRATION TEST DATA w 'j r w U cl m (NoasRt) 3 Q m W W J O aW m ¢ /REMARKS W a z 3 0 In y 4 2 10 20 30 6080 i 10 3 2 8 10 5 9 10 19 12 5 10 10 .: 20 Page 2 of 2 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-4 SBME Project No. 1031-09-121 DATE DRILLED: 9/30/09 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 30.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: 3%" H.SA. w -. w BLOW COUNT O > e- ICORE DATA STANDARD PENETRATION TEST DATA w F x L7 i- w [i z c� o w (blons10) . v o MATERIAL DESCRIPTION w > Ja a a REMARKS > 0a 3 w < a N ul y :� 42 _ „E, 10 20 30 6080 z L, I. TOPSOIL SAND (SPSM) 1 4 6 7 13 } medium dense, brown, with silt, fine to medium, _ poorly graded, damp CLAYEY SAND (SC) j f 2 4 4 5 9 5 medium dense, red, fine to medium, damp CLAYEY SAND (SCSM) T. 5 6 6 medium dense, red -brown, with silt. Sra to 3 12 ' j. medium, damp SAND (SPSM) 1. 9 12 12 10 .7..}'. dense, brown -tan, with silt, fine to medium, poorly 4 24 graded, damp to moist T. SILTY SAND ISM) loose, red -brown, fine to medium, moist 5 3 4 4 e 5 - SAND (SPSM) dense, red -orange, with silty clay, fine to coarse, poorly graded, moist 6 6 11 16 ! 27 SILTY SAND (SM) medium dense, red -orange to orange -tan, fine, moist 7 6 6 8 14 25 B 4 6 6 2 30 Boring terminated at 30 feet NOTES: 1. THIS LOG IS ONLYA PORTION OFA REPORTPREPARED rOR THE NAMED PROJECT AND MUSTONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCE WRH AS�TM D.1586. 3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 4, WATER LEVEL IS AT TIME OFEXPLORAPONAND WILL VARY. • Page 1 of 1 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-5 SBME Project No. 1031-09-121 - DATE DRILLED: 9130109 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 40.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split sn NORTHING: FASTING: DRILLING METHOD: Wash Borin w -- w BLOW COUNT U > 0 .9 e- ICORE DATA STANDARD PENETRATION TEST DATA w ^ = 0 o MATERIAL DESCRIPTION �- . > w Li u W z O (blvxs10) w w W v a REMAR S > 3 w ¢ H:R N y s=` F a 10 20 30 6080 Z </ TOPSOIL FILL: CLAYEY SAND (SC) 1 5 7 8 15 medium dense, brown -orange, with silt, fine to medium, damp FILL: SILTY SAND (SM) 2 10 12 12 24 5 dense, orange -tan with dark gray, some clay, fine, moist 3 6 9 70 I 19 FILL: CLY SAND (SCMI AY=S medium dense, brown -gray, with silt, fine to medium, moist 10 4 7 9 12 21 SILTY SAND ISM) medium dense, brown -red, some clay, fine, damp CLAYEY SAND (SC) medium dense, red, fine to medium, moist to damp 4 4 5 5 9 15 3 5 7 12 20 6 SAND (SIP) medium dense, yellow -white, with silt, fine to medium, poorly graded, damp 7 7 9 12 21 25 CLAYEY SAND (SC) j medium dense, light gray, fine, moist 30 j B 4 5 7 2 SILTY CLAY (CL) stiff to firm, brown -tan to light gray, damp y 3 3 a 7 NOTES: I. THIS LOG IS ONLYA PORTION OFA REPORTPREPARED FOR THE NAMED PROJECT AND MUST ONLYSE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA IN GENERAL ACCORDANCE WRH ASTM D 1686. 3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 4. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. Page 1 of 2 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-5 SBME Project No. 1031-09-121 DATE DRILLED: 9/30109 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 40.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: Wash Boring BLOW COUNT U j p DATA ICORE STANDARD PENETRATION TEST DATA _ U puwSlfl)w j o MATERIAL DESCRIPTION a wo REMAR S > 7 C w < z 3 E 10 20 30 6080 SILTY CLAY (CL) stiff to firm, brown -tan to light gray, damp (continued) 0 2 2 4 s 40 Boring terminated at 40 feet i NUILS: 1. THIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUST ONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TESTDATA IN GENERAL ACCORDANCE W/TH ASTM D-IM6. 1 STRATIFICAT/ONAND GROUNDWATER DEPTHS ARE NOTEXACT. d. WATER LEVEL IS AT TIME OF EXPLORATION AND WILL VARY. IRA Page 2 of 2 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B$ SBME Project No. 1031-09-121 DATE DRILLED: 9130I09 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 10.0 ft DRILLER: Jason White WATER LEVEL: Dry at TOB HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: 3%" H.S.A. W -- w BLOW COUNT o j 0 0 `c 1CORE DATA STANDARD PENETRATION TEST DATA w w 0 z o (blowslft) o- 0 MATERIAL DESCRIPTION r < v w 0 J J— 4 (REMARKS Z 0 4 w a a 3 m ran 10 20 30 6080 TOPSOIL SAND(SPSM) 1 5 10 8 18 medium dense to loose, tan to orange -brown, with silt, fine to medium, poorly graded, dry to damp 4 4 4 2 8 SAND (SC) I jCLAYEY medium dense, red, fine, damp r+c 3 4 a 5 9 1/4 6 9 9 8 10 Boring terminated at 10 feet NOIhs: 1. THIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUSTONLY BE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TESTDATA IN GENERAL ACCORDANCE WITH AS�TM D.1586. 3. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. <. WATER LEVEL IS AT TIME OFEXPLORATION AND WILL VARY. Page 1 of 1 M-7 "i., gg 4 i 3 i.ts ww PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-7 SBME Project No. 1031-09-121 DATE DRILLED: 1011/09 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 30.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: 31/." H.S.A. U j O0 -mow Z BLOWCOUNT /CORE DATA STANDARD PENETRATION TEST DATA w w Q_ o MATERIAL DESCRIPTION d a W a w< z REMARKS > z 3 Vl to 10 20 306080 CONCRETE 1 5 9 7 16 FILL: SAND (SPSM) medium dense, tan to dark gray, with silt, fine to 6 10 11 ...I medium, poorly graded, damp - 2 21 5 3 5 4 3 7 // �: CLAYEY SAND (SC) loose to dense, brown -orange to red -brown, with 10/ silt, fine to medium, damp to dry 3 e 12 4 ? 20 5 9 12 13 25 10 j ..J... j, SAND (SPSM) very dense, brown -red, with silty clay, fine to f coarse, poorly graded, moist 4 21 24 B 45 CLAYEY SAND (SC) 20 j medium dense, tan -light gray, fine, damp 7 4 8 9 17 i SAND (SC) jCLAYEY medium dense, tan -pink, with silt, and clay B I 6 5 6 11 25 OR,lenses, fine to medium, moist CLAY (CH) firm, gray, damp 9 3 2 4 6 30— Boring terminated at 30 feet NOTES: 1. THIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUSTONLYBE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TEST DATA/N GENERAL ACCORDANCE WRH AS�TM D1586. 3. STRATIFICATION AND GROUNDWATER DEPTNS ARE NOT EXACT. 4. WATER LEVEL IS AT TIME OFEXPLORATION AND WILL VARY. Page 1 of 1 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B-8 SBME Project No. 1031-09-121 DATE DRILLED: 1011109 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 40.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: 3'/." H.S.A. p> w 0O -,w BLOW COUNT I CORE DATA STANDARD PENETRATION TEST DATA w C7 o MATERIAL DESCRIPTION r^ °� w ti z (blmslft) Q w w Of a REMARKS > U' h w Q m Z uQj 10 20 30 6080 ..,I CONCRETE FILL: SAND (SPSM) .I 1 2 2 2 4 loose, brown -gray, with silt, fine to medium, poorly graded, damp CLAYEY SAND (SC) Amedium 2 3 3 6 9 5 dense, red -orange, with silt, fine, dry SILTY SAND ISM) medium dense. tan -brown, fine, damp 3 3 4 5 9 CLAYEY SAND (SCSM) dense, red -brown, with silt, fine to medium, moist 4 11 13 15 26 0 to—. SILTY SAND ISM) medium dense to dense, brown -orange, trace clay, fine, moist 8 9 13 15 6 22 6 10 15 21 36 20 SILTY SAND ISM) medium dense, brown -pink, fine to medium, wet 7 5 5 6 25 - .J SAND(SPSM) medium dense, tan to gray -brown, with silt, trace clay, fine to medium, poorly graded, wet . '�.{. B 6 9 9 18 30 �f. 9 5 7 11 : ::::: 18 NOTES: 1. THIS LOG IS ONLYA PORTION OFA REPORTPREPARED FOR THE NAMED PROJECT AND MUST ONLY BE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TESTDATA IN GENERAL ACCORDANCE WITH AS�TV D-1586. 3.. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 4 WATER LEVEL IS AT TIME OFEXPLORAPON AND WILL VARY. Page 1 of 2 PROJECT: SOF Operations Addition Fort bragg, NC BORING LOG B$ SB,ME Project No. 1031-09-121 DATE DRILLED: 1011109 ELEVATION: NOTES: DRILL RIG: CME 750 BORING DEPTH: 40.0 ft DRILLER: Jason White WATER LEVEL: HAMMER TYPE: Auto LOGGED BY: M. Khan SAMPLING METHOD: Split spoon NORTHING: EASTING: DRILLING METHOD: 31/.'• H.SA. w --w BLOWCOUNT p z ` 1 CORE DATA STANDARD PENETRATION TEST DATA w r^= c0 r^ w U z o (Noaslfi) w0 o MATERIAL DESCRIPTION W m REMAR S > (7 � J w Q !- w 0 e e E E Z 10 20 30 6080 is SILTY CLAY (CL) very hard, light gray -white, dry - 10 12 21 37 40— I Boring terminated at 40 feet NOTES: 1. THIS LOG IS ONLYA PORTION OFA REPORT PREPARED FOR THE NAMED PROJECT AND MUSTONLY BE USED TOGETHER WITH THAT REPORT. 2 BORING SAMPLING AND PENETRATION TESTDATA IN GENERAL ACCORDANCE WRHASTM D-1586. J. STRATIFICATION AND GROUNDWATER DEPTHS ARE NOT EXACT. 4. WATERLEVELISATTIMEOFEXPLORATIONANDWILL VARY. Page 2 of 2 Fora No. TR-D698-2 Revision No.: 0 -� a NMI E Moisture -Density Report IS Revision Date: 11121107 Quality Assurance . ;.. S&ME, Inc. 409 Chicago Dr.,;Suite 116, Fayetteville, NC 28306 S&ME Project #: 1031-09-121 Report Date: 10/15/09 Project Name: SOF Operations Addition Test Date(s): 10/7-10/14/09 Client Name: Cromwell Architects Addition Client Address: 101 South Spring St., Little Rock, AR 72201 Boring #: 6 Sample #: 1 Sample Date: 10/5/2009 Location: Not Applicable Offset: Not Applicable Depth: 1'-10, Sieve Size used to separate the Oversize Fraction: #4 Sieve px 3/8 inch Sieve ❑ 3/4 inch Sieve ❑ Mechanical Rammer ❑ Manual Rammer NI Moist Preparation ❑ Dry Preparation O ReferencesYConuuents7Devmtionsi. ND.Not Determined �^ ^ ASTM D 221G Labor t6ry Duemiinutiou of Water (Nlotsture) Content of Soil and Rork by Mass r 4 ASTM D,1557: Laboratory Comuaction Charaeterisnes of Soil Usne Modified Effrnf David B. Carver. E.T. Branch Manager Technical Responsibility Signature Position Date This report shall not be reproduced, emept in full, without the written approval of S&ME, Inc. S&ME,lnc. - Corporate 3201 Spring Forest Road B-6 mod Prociorx(s Raleigh, NC 27616 Page I of I Form No: TR-D2216-T265-2 �\ Revision No. 0 _'® Revision Date: 02122108 Laboratory Determination of Water Content ��ii�� ASTM D 2216 ❑ AASHTO T 265 ❑ Quality Assurance S&ME; Inc: Raleigh '3201 Spring Forest Road; Raleigh, North Car6lina-27616 Project #: 1031-09-121 Report Date: 10/8/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/8/09 Client Name: Client Address: I Sample by: S&ME, hie. Sample Date(s): 10/1/09 Sampling Method: Boreholes Drill Rig: NA Method:. A %) ❑ B(O1% ❑, Bp/ancelD,';_ I024. Ca1GbrahonDate=;,-,;11112108 ' Boring No. K} ` Sample No 'Samples' = „Depth .. ; � Tare# t. r.. s ��° Tare Weight �+ ' v TareWt+ Wet Wt TareWt+�+I,;iWater y DrySWt , - t� : Welght Percent t Moisture ' ft or m ' grams.z grain's grams a r :x grams' B-1 S-1 I- 8 ft. 30 111.90 165.55 160.33 5.22 10.8% B, S-2 1 - loft. 34 114.96 2C5.71 203.71 2.00 2.3% B-7/8 S-3 6 -10 ft. 24 118.47 164.62 1 158.01 6.61 16.7% Notes /Deviations /References AASHTO T 265: Laboratory Determination of Moisture Content of Soils ASTM D _2216 Laboratory Deterinmahon of� Water (Moisture)'Content of Soil and Rock tiyMasst��' ,,a =;< <,?` 5 ?"' ' ---;; .. _._. .. .r, - , Mal Kraian NA Technician Name Signature Certification Type/No. Date Mal Kraian Laboratory Manager Technical Responsdality Signata'e Position Date '!'his report shall not be reproduced, except in full, wilhout the written approval ofS&ME, Inc. S&ME, Ina - Corporale 3201 Spring Forest Road Moisture Table.xls Raleigh, NC. 27616 Page I of I Form No: TR-D4972-1 Revision No. 0 Revision Date: 07110108 pH of Soil ASTM D 4972 Method A Quality Assurance S&ME, Inc; Raleigh, 3201 Spring Forest Raod, Raleigh, North Carolina 27616 1 `. Project #: 1031-09-121 Report Date: 10/8/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/8/09 Client Name: Cromwell Architects Client Address: Boring: B-1 Sample #: S-1 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Depth (fit): 1 - 8 ft. pHMeter Calibration Buffer Solution Results pH buffer 7.0 Z 03 pH buffer 4.01 4.02 pH buffer 10.0 10.03 Buffer Temperature. 0 C 23.4 Measuring pH of Soil Measurements Weigtht of Air Dry Soil (g) 30.11 Distilled Water (ml) 30 Temperature 0C 23.7 pH Readings 6.64 Notes /Deviations /References: ASTM D 4972: Standard Test Method for pH of Soils Mal Kraian Technician Name Date Signature Level/Certi�calion Mal Kraian Technical Responsibility Signaha'e Laboratory Manager Position Dote This report shall not be reproduced, except in fidt, without the written approval ofS&ME, Inc. S&ME, Inc. - Corporate 3201 Spring Forest Road B-1 S-1 (1 - 8f) pH.xhs Raleigh, NC.. 27616 Page 1 of I Pane No: TR-G57-2 Revision No. 0 Revision Date: 07111108 Soil Resistivity - ASTM G 57 QualityAssurance S&ME, Inc ..- Ralatgh; 3201 Spring Forest Road, Raleigh, North Carolina 27616 Project #: 1031-09-121 Report Date: 10/9/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/9/09 Client Name: Cromwell Architects Client Address: Boring: B-1 Sample #: S-1 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Depth (ft): 1 - 8 ft. Brown Siltv SAND Moisture Content Determination As Received Condition 10.8% After 24-hr Condition 19.2% Resistivity (ohms - cm) As Received Condition 25800 After 24-hr Condition 8133 Notes /Deviations /References: ASTM G 57: Field Measurements of Soil Resistivity Using the Wenner Four -Electrode Method Mal Kraian Technical Responsibility Signature Labotatory Manager Position Date This +'eport shall not be reproduced, except in full, wi0mut the wrilten approval ofS&ME. Inc. S&ME, Inc. - Corporate 3201 Spring Forest Road B-1 S-1 (I - 8 ft) Resisliviry.sls Raleigh, NC.. 27616 Page I of I Fonn No: TR-D4972-1 Revision No. 0 Revision Date: 07110108 pH of Soil ASTM D 4972 Method A Quality Assurance S&AH, Inc. Raleigh, 3201 Sprang Forest Raod, Raleigh, North Carolina 27616 - Project #: 1031-09-121 Report Date: 10/8/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/8/09 Client Name: Cromwell Architects Client Address: Boring: B-6 Sample #: S-2 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Denth (ft): 1 - loft. pHMeter Calibration Buffer Solution Results pH buffer 7.0 7.03 pH buffer 4.01 4.02 pH buffer 10.0 10.03 Buffer Temperature °C 23.4 Measuring pH of Soil Measurements Weigtht of Air Dry Soil (g) 30.04 Distilled Water (ml) 30 Temperature °C 23.3 pH Readings 6.24 Notes /Deviations /References: ASTM D 4972: Standard Test Method for pH of Soils Mal Kraian Technician Name Mal Kral an Technical Responsibility Date signature Signaeve Laboratory Manager Position This report shall not be reproduced, except in fill, wilhma the written approval ofS&ME, Inc. Level/Cerliifcation Date E&MF, Inc. - Corporate 3201 Spring Forest Road R-6 9-2 (1 - 10 fi) plI.xls Raleigh, NC.. 27616 Page 1 of I Form No: TR-G57-2 Revision No. 0 Revision Date: 07111108 Soil Resistivity ASTM G 57 Quality Assurance S&ME, Inc. - Ralaigh, 3201 Spring Forest Road, Raleigh, North Carolina 27616 Project #: 1031-09-121 Report Date: 10/9/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/9/09 Client Name: Cromwell Architects Client Address: Boring: B-6 Sample #: S-2 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Depth (ft): 1 - loft. Sample Description: Tan -Brown Silty SAND (Visual) Moisture Content Determination As Received Condition 2.4% After 24-hr Condition 19.1 % Resistivity (ohms - CM) As Received Condition 37500 After 24-hr Condition 5733 Notes /Deviations /References: ASTM G 57: Field Measurements of Soil Resistivity Using the Wenner Four -Electrode Method Mal Kraian Teehnienl Responsibility Labotatory Manager Signature Position Date This report shall not be reproduced, except in fill, without the written approval ofS&ME, Inc. S&ME, Inc. -Corporate 3201 Spring Forest Roar! B-6S-2 (I - I Off) Resistivity.xls Raleigh, NC., 27616 Page 1 of I Form No: TR-D4972-1 Revision No. 0 Revision Date: 07110108 pH of Soil ASTM D 4972 Method A QualityAssurance S&ME, Inc. Raleigh, 3201 Spring Forest Raod, Raleigh, North Carolina 27616 Project #: 1031-09-121 Report Date: 1018/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/8/09 Client Name: Cromwell Architects Client Address: Boring: B-7/8 Sample #: S-3 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Depth (ft): 6 - 10 ft. Sample Description: Red -Brown Silty Clayey SAND (Visual) pH Meter f'e/ibration Buffer Solution Results pH buffer 7.0 Z 03 pH buffer 4.01 4.02 pH buffer 10.0 10.03 Buffer Temperature oC 23.4 Measuring pH of Soil Measurements Weigtht of Air Dry Soil (g) 29.98 Distilled Water (ml) 30 Temperature 0C 23.4 pH Readings 6.86 Notes/Deviations/References: ASTM D 4972: Standard Test Method for pH of Soils Mal Kraian Technician Name Mal Kraian Technical Responsibility Date Eignnlnre signature Laboratory Manager Position This repor! shall not be reproduced, except in fill, without the wrillen approval of S&ME. Inc. Level/Cernfication Date S&ME, Inc. - Corporate 3201 Spring Forest Road R-7&8 S-3 (6 - ]Oft) pH.xls Raleigh, NC.. 27616 Page 1 of 1 Form No: TR-G57-2 Revision No. 0 Revision Date: 07111108 Soil Resistivity ASTM G 57 Quality Assurance S&1VIE, Inc. - Ralaigti,3201 Spring Forest Road, Raleigh, North Carolina 27616 ' Project #: 1031-09-121 Report Date: 10/9/09 Project Name: SOF Operations Additions Test Date(s): 10/7 - 10/9/09 Client Name: Cromwell Architects Client Address: Boring: B-7/8 Sample #: S-3 Sample Date: 10/1/09 Location: Site -Borehole Offset: NA Depth (ft): 6 - 10 ft. Sample Description: Red -Brown Silty Clayey SAND (Visual) Moisture Content Determination As Received Condition 16.7% After 24-hr Condition 135.5% Resistivity (ohms - cm) As Received Condition 26000 After 24-hr Condition 1 8229 Notes /Deviations /References: 0 ASTM G 57: Field Measurements of Soil Resistivity Using the Wenner Four -Electrode Method Mal Kraian Technical Responsibility signaau'e Labotatory Manager Position Date This report shall not be reproduced, except in jdl, without the written approval ofS&ME, Inc. S&ME, Inc. - Corporate 3201 Spring Forest Road R-7&8 S-3 (6 - 10 fl), Resislivity.xls Raleigh, NC.. 27616 Page I of I