HomeMy WebLinkAboutNCC205233_ESC Approval Submitted_20201116ROY COOPER Governor MIC"AEL S. REGAN Secretary BR1AN WRENN Director NORTH CARD INA, EnvironMentW QUWItY November 2, 2020 LETTER OF APPROVAL WITH MODIFICATIONS Barnhill Contracting Company Attn: Ms. Shannon K. Douglas, Vice President 841 Sun Gro Drive Elizabeth City, NC 27909 RE: Project Name: Manning Stockpile Area Project 1D: Marti-2021-003 County: Martin City: Williamston Address: Jones Road River Basin: Roanoke Date Received by LQS: October 29, 2020 Submitted By: Barnhill Contracting Company Plan Type: New / Express Dear Madam, Acres Approved: 6.0 This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be acceptable and hereby issue this Letter of Approval. The enclosed Certificate of Approval must be posted at the job site. This plan approval shall expire three (3) years following the date of approval, if no land -disturbing activity has been undertaken, as is requited by Title 15A NCAC 4B .0129. As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCGO10000 Construction General Permit. After the form is reviewed and found to be complete, you will receive a link with payment instructions for the $100 annual permit fee. After the fee is received, you will receive the COC via email. You MUST obtain the COC prior to commencement of any land disturbing activity. The eNOI form may be accessed at deq.nc.gov/NCG01. Please direct questions about the eNOI form to Annette Lucas at Annette. lucas ncdenr. gov or Paul Clark at Paul.clark ncdenr. ov. If the owner/operator of this project changes in the future, the new responsible party is required to apply for his/her own COC. Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on file at the job site: D �Q7> North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land itesources Washington Rrgional Office l 943 Washington Square Mall I Washington, North Carolina 27689 tiA fir^+^ ���^^ 252.94b.b481 I • The approved E&SC 2, The NCGOI plan as well asand the COC, any approved deviation. I Records of inspections made during it is received. g the previous 3O Also quidays. this letter gives the notice re to ensure compliance with the a red by G.S, 113A-6I.1 a pproved plan, i) of our right of periodic inspection North CaroIina's Sedimentation Pollution Protection of existing natural resources and adjoining trol Act is Performance -Oriented, Of this project, the erosion and sedimentation control P llOwin the coed, requiring g Properties. If, following the commencement Of the Sedimentation Pollution Control Act of 1973 control plan is inadequate to meet the requirements through bb), this office may require revisions to the plan and imaz Ieina me atiteral Statute I I3A-5I insure compliance with the Act. P on of the revisions to Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to this land -disturbing activity. This approval does not supersede any other permit or approval. Please note that this approval is based in part on the accuracy of the information provided in the Financial Responsibility Form, which you provided. You are requested to file an amended form if there is any change in the information included on the form. In addition, it would be helpful if you notify this office of the proposed starting date for this project. Sincerely, zz �,- Samir Dumpor, PE Regional Engineer cc w/o enc: Dustin Faulkner, Barnhill Contracting Company (email) WaRO Division of Water Resources (email) PROJECT INFORMATION SHEET APPROVAL DATE: November 2, 2020 RESPONSIBLE PARTY: Barnhill Contracting Cam an PROJECT NAME COUNTY: OFF -SITE BORROW AND/OR DISPOSAL SITE: START-UP DATE: CONTRACTOR: ON -SITE CONTACT: ON -SITE PHONE NO.: OFFICE PHONE NO.: Manning Stockpile Area Martin NO.: Marti-2021-003 NO.: COMPLETE & RETURN THIS FORM PRIOR TO THE START OF CONSTRUCTION TO: N.C.D.E.Q. LAND QUALITY SECTION ATTN: James Edwards 943 WASHINGTON SQUARE MALL WASHINGTON, NORTH CAROLINA 27889 james.edwards@ncdenr.gov 1. The developer is responsible for the control of sediment the ldeveloperapproved mu t takethoseerosion and sedimentation control measures prove CGS 113A-57(3)). additional steps necessary to stop sediment from leaving this site (N Each sediment storage device must be inspected after each storm event (NCGS 113A- 54.1(e)). Maintenance and/or clean out is necessary anytime the device is at 50%capacity. All sediment storage measures will remain on site and functional until all grading and final landscaping of the project is complete (I5A NCA 2. The developer is responsible for obtaining all permits and approvals necessary for the development of this project prior to the commencement of this land disturbing activity. This could include our agency's Stormwater regulations and the Division of Water Resources' enforcement requirements within Section 401 of the Clean Water Act, the U.S. Army Corps of Engineers' jurisdiction of Section 404 of the Clean Water Act, the Division of Coastal Management's CAMA requirements, the Division of Solid Waste Management's landfill regulations, the Environmental Protection Agency and/or The U.S. Army Corps of Engineers jurisdiction of the Clean Water Act, local County or Municipalities' ordinances, or others that may be required. This approval cannot supersede any other permit or approval. 3. Adequate and appropriate measures must be properly installed downstream, within the limits of disturbance, of any land disturbing activity to prevent sediment from leaving the limits of disturbance, entering existing drainage systems, impacting an on -site natural watercourse or adjoining property. (NCGS 113A-57) w I A I