HomeMy WebLinkAbout20090900 Ver 1_Emails_20090916Gilleski, Lia
From: Williams, Andrew E SAW [Andrew.E.Williams2@usace.army.mil]
Sent: Wednesday, September 16, 2009 3:43 PM
To: Gilleski, Lia
Cc: Karoly, Cyndi
Subject: Burning Tree Drive Improvements Project
Lia
Thank you for discussing this project with me today. As I stated, I met with representatives of the Town of Chapel Hill for
this project in July. We discussed the different components, and at the time, based on the discussions and information I
had, I suggested that the project would be permitted using multiple NWPs. However, after receiving the PCN and
reviewing the plans, it seems that the project should be permitted using only a NWP 3 and a NWP 18. The NWP 3 would
cover all of the work at the existing culverts and the NWP 18 would cover the work below the OHWM of the pond. Would
you please re-issue the 401 certification for only a NWP 3 and NWP 18? Please let me know if you need any additional
information. Thanks.
Andrew Williams
Regulatory Project Manager
U.S. Army Corps of Engineers
Wilmington District, Raleigh Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
919-554-4884 ext. 26