HomeMy WebLinkAboutNCG140325_NOD_20190910ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
S. DANIEL SMITH
Director
NORTH CAROLINA
Environmental Quality
September 10, 2019
CERTIFIED MAIL: 7019 0700 0000 8867 9822
RETURN RECEIPT REQUESTED
McDowell Concrete Supply LLC
Attn: Patrick Boone
Post Office Box 1147
Marion, North Carolina 28752
Subject: NOTICE OF DEFICIENCY (NOD-2019-PC-0195)
NPDES Stormwater General Permit NCG140000
Certificate of Coverage NCG140325
McDowell Concrete Supply
McDowell County, North Carolina
Dear Mr. Boone:
On August 29, 2019, Isaiah Reed from the Asheville Regional Office of the Division of
Energy, Mineral and Land Resources (DEMLR), conducted a compliance inspection for the
McDowell Concrete facility located at 105 S Garden Street, McDowell County, North
Carolina. A copy of the Compliance Inspection Report is enclosed for your review. The
inspection and file review revealed that the subject facility is covered by NPDES
Stormwater General Permit NCG140000 under Certificate of Coverage NCG140325. Permit
coverage authorizes the discharge of stormwater from the facility to receiving waters
designated as an Unnamed Tributary of Youngs Fork (Corpening Creek), a Class C
waterbody in the Catawba River Basin.
As a result of the inspection, the following deficiencies are noted:
1) Stormwater Pollution Prevention Plan (SWPPP)
A Stormwater Pollution Prevention Plan (SWPPP) has not been developed, recorded, or
properly implemented.
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
D_EWrii;
Asheville Regional Office 12090 U.S. Highway 701 Swannanoa, North Carolina 28778
828.296.4500
2) Qualitative Monitoring
Qualitative monitoring has not been conducted and recorded in accordance with permit
requirements.
3) Additional Deficiencies
Add summary of each deficiency added.
Requested Response
You are asked to respond to this office, in writing, within 30 calendar days from receipt of
this notice. Your written response should include a reasonable explanation as to why the
above stated deficiencies have occurred, as well as a Plan of Action to prevent them from
recurring.
Action Items
Immediately begin efforts to comply with General Permit NCG140000, including but not
limited to:
1. Develop, implement, and maintain an acceptable SWPPP.
2. Begin monitoring at all outfalls.
3. Corrective action for each deficiency noted.
Thank you for your attention to this matter. This office requires that the deficiencies, as
noted above and detailed in the enclosed inspection report, be properly resolved.
Failure to address the deficiencies could result in the issuance of a Notice of
Violation, which could be subject to a civil penalty assessment of up to $25, 000 per
day for each violation. Should you have any questions or concerns, please contact Isaiah
Reeed or myself at (828) 296-4500.
Sincerely,
Stanley E. Aiken P c
Regional Engineer
Land Quality Section
Enclosure:
Inspection Report
ec: Alaina Morman, Environmental Specialist
Stan Aiken, Regional Engineer
Compliance Inspection Report
Permit: NCG140325 Effective: 08/01/17 Expiration: 06/30/22 Owner: McDowell Concrete Supply LLC
SOC: Effective: Expiration: Facility: McDowell Concrete Supply, LLC
County: McDowell S Garden St
Region: Asheville
Marion NC 28752
Contact Person: Patrick Boone Title: Phone: 828-652-5721
Directions to Facility:
System Classifications:
Primary ORC:
Secondary ORC(s):
OnSlte Representative(s):
Related Permits:
Inspection Date: 08/29/2019
Primary Inspector: Isaiah L Reed
Secondary Inspector(s):
Certification:
Phone:
Entry Time: 09:OOAM Exit Time: 09:45AM
Phone: 828-296-4614
Reason for Inspection: Routine Inspection Type: Compliance Evaluation
Permit Inspection Type: Ready Mix Concrete Stormwater/Wastewater Discharge COG
Facility Status: Compliant Not Compliant
Question Areas:
Storm water
(See attachment summary)
Page 1 of 3
Permit: NCG140325 Owner -Facility: McDowell Concrete Supply LLC
Inspection Date: 08129/2019 Inspection Type : Compliance Evaluation Reason for Visit: Routine
Inspection Summary
On August 29, 2019 this facility was inspected for compliance. I met with Tommy Stevenson on site. During the inspection,
the following items were noted:
1) No Stormwater Pollution Prevention Plan (SWPPP) was available at the time of the inspection. The permittee is directed
to immediately Locate/create, maintain, and implement a SWPPP as outlined in the NCG140000 general Permit.
2) No Analytical monitoring records were available at the time of the inspection. The permittee is directed to immediately
locate at monitoring data for the facility from the past 3 years.
3) No Qualitative monitoring records were available at the time of the inspection. The permittee is directed to immediately
locate at monitoring data for the facility from the past 3 years.
This facility will be re -inspected on or after October 16, 2019. If the above items have not been addressed, further action will
be taken.
If you have any questions, please contact this office at (828) 296-4614.
Page 2 of 3
Permit: NCG140325 Owner - Facility: McDowell Concrete Supply LLC
Inspection Date: 08/29/2019 Inspection Type: Compliance Evaluation Reason for Visit: Routine
Stormwater Pollution Prevention Plan
Yes No NA NE
Does the site have a Stormwater Pollution Prevention Plan?
❑
0 ❑ ❑
# Does the Plan include a General Location (USGS) map?
❑
M ❑ ❑
# Does the Plan include a "Narrative Description of Practices"?
❑
❑ ❑
# Does the Plan include a detailed site map including outfall locations and drainage areas?
❑
❑ ❑
# Does the Plan include a list of significant spills occurring during the past 3 years?
❑
0 ❑ ❑
# Has the facility evaluated feasible alternatives to current practices?
❑
0 ❑ ❑
# Does the facility provide all necessary secondary containment?
❑
0 ❑ ❑
# Does the Plan include a BMP summary?
❑
0 ❑ ❑
# Does the Plan include a Spill Prevention and Response Plan (SPRP)?
❑
0 ❑ ❑
# Does the Plan include a Preventative Maintenance and Good Housekeeping Plan?
❑
M ❑ ❑
# Does the facility provide and document Employee Training?
❑
❑ ❑
# Does the Plan include a list of Responsible Party(s)?
❑
❑ ❑
# Is the Plan reviewed and updated annually?
❑
0 ❑ ❑
# Does the Plan include a Stormwater Facility Inspection Program?
❑
0 ❑ ❑
Has the Stormwater Pollution Prevention Plan been implemented?
❑
0 ❑ ❑
Comment: No Stormwater Pollution Prevention Plan was available at the time of the inspection.
Qualitative Monitoring Yes No NA NE
Has the facility conducted its Qualitative Monitoring semi-annually? ❑ 0 ❑ ❑
Comment: No Qualitative Monitoring records were available at the time of the inspection.
Analytical Monitoring Yes No NA NE
Has the facility conducted its Analytical monitoring? ❑ ❑ ❑
# Has the facility conducted its Analytical monitoring from Vehicle Maintenance areas? ❑ ❑ 0 ❑
Comment: No Analytical Monitoring records were available at the time of the inspection.
Permit and Outfalls
Yes No NA NE
# Is a copy of the Permit and the Certificate of Coverage available at the site?
❑
MIJEJ
# Were all outfalls observed during the inspection?
0
❑
❑ ❑
# If the facility has representative outfall status, is it properly documented by the Division?
❑
❑
M ❑
# Has the facility evaluated all illicit (non Stormwater) discharges?
❑
MEJEJ
Comment
Page 3 of 3