HomeMy WebLinkAboutNC0024406_Fact Sheet_20190814DEQ/DWR
FACT SHEET FOR NPDES PERMIT DEVELOPMENT
Minor Modification
NPDES No. NCO024406
Facility Information
Applicant/Facility
Name:
Duke Energy Carolinas, LLC- Belews Creek Steam Station
Applicant Address:
13339 Hagers Ferry Road; Huntersville, North Carolina 2807
Facility Address:
3195 Pine Hall Road; Belews Creek, NC 27009
Permitted Flow
N/A
Type of Waste:
Industrial (- 100%); Domestic (< 1%)
Prim.SIC Code: 4911
Facility/Permit
Status:
Class I /Active; Renewal
County:
I Stokes County
Miscellaneous
Receiving Stream:
Belews Lake (001,
005, 007), UT to
Dan River (003,
003A) , Dan River
006
Regional Office:
Winston-Salem
(WSRO)
Stream
Classification:
C (Belews Lake),
WS-IV (Dan River
and UT to Dan
River)
State Grid / USGS
Quad:
1318SE/Belews
Lake
303(d) Listed?
No
Permit Writer:
Sergei Chernikov,
Ph.D.
Subbasin:
03-02-01
Date:
10/29/2018
Drainage Area (mi2):
501 (Dan River)
001: Lat. 36° 16' 49.5" N
003: Lat. 36° 18' 22.0" N
006: Lat. 36° 18' 34.8" N
Long. 80' 03' 39.8" W
Long. 80' 04' 50.7" W
Long. 80° 04' 36.1" W
Summer 7Q 10 (cfs)
80 (Dan River)
Winter 7Q 10 (cfs):
160 (Dan River)
30Q2 (cfs)
195 (Dan River)
Average Flow (cfs):
576 (Dan River)
IWC (%):
26.5
BACKGROUND
Duke Energy's Belews Creek Steam Station is a coal fired steam electric plant in Stokes
County. The facility is subject to the federal effluent guidelines 40 CFR Part 423.
In addition to NPDES Permit NC0024406, the facility also holds the following permits:
01983R12 (air permit), NCD000856591 (Hazardous wastes), and 85-03 (industrial
landfill).
Duke Energy requested a Modification to the permit that allows the ash basin decanting
flow to be released through Internal Outfall 006A/External Outfall 006. The request has
been granted.
A new RPA has been conducted based on the projected maximum decanting flow of 5.5
MGD. Based on the results of the RPA, Daily maximum and Monthly average limits for
lead have been reduced (Outfall 006A). The Supplement to Permit Cover Sheet and
Pagel of 3
Condition A. (4.) have also been amended to allow decanting flow to be released through
Internal Outfall 006A.
All remaining terms and conditions of the permit remain unchanged.
The facility operates the following outfalls:
• Outfall 001: once through cooling water consisting of intake screen
backwash, recirculating cooling water, station equipment cooling water and
once -through cooling water, this Outfall discharges to Belews Lake.
• Outfall 003: ash basin discharge consisting of waste streams from the power
house and yard holding sumps, ash sluice lines, chemical holding pond,
coal yard sumps, stormwater, coal pile collection basins (collecting contact
stormwater from coal piles), remediated groundwater, emergency release of
anhydrous ammonia, seepage from coal ash basin, emergency overflow from
the retention basin, emergency overflows from the existing effluent channels,
and treated FGD wastewater from internal outfall 002. The wastewater from
this outfall discharges to Unnamed Tributary (UT) to Dan River.
Internal outfall 002: FGD wastewater (discharging to ash pond)
• Outfall 003A/006. Upon completion of construction, discharge from the new
lined retention basin. Basin will accept wastes from holding basin, ash
contact water, various sumps, coal pile runoff, stormwater runoff, cooling
tower blowdown, FGD wastewater, and various low volume wastes such as
boiler blowdown, oily waste treatment, wastes/backwash from the water
treatment processes, coal pile collection basins (collecting contact
stormwater from coal piles), plant area wash down water, cooling tower
blowdown, equipment heat exchanger water, remediated groundwater,
emergency overflow (rain in excess of designed storm event), toe drain
(potential discharge to outfall 006 only), emergency release of anhydrous
ammonia, release of ammonia during quarterly testing, and treated domestic
wastewater. Outfall 003A discharges to UT to Dan River via the Outfall 003.
Upon completion of construction all waste streams previously discharged to
ash basin, will be re-routed to the new retention basin. During the transition
period, wastewater from the ash pond can also be discharged from Outfall
003. Construction of new Outfall 006 has been completed. Outfall 006 will
discharge to Dan River. This Outfall will be used for decanting and
dewatering of the ash basin.
• Outfall 005. This is a former stormwater outfall SW002, consists of once
through non -contact chiller water and stormwater. The wastewater from this
outfall discharges to Belews Lake.
• Internal Outfall 006A. This is a temporary internal outfall for decanting and
dewatering of the ash basin, it will discharge through new Outfall 006.
• Outfall 007 (lat. - 36016'51.604"; long. 80003'52.995"). This is an emergency
spillway for South Coal Basin. This outfall discharges to Belews Lake. The
spillway is designed for a flood greater than 100-year event. Sampling of this
spillway is waived due to unsafe conditions associated with sampling during
overflow event.
• Internal outfall 009. Domestic wastewater plant. The wastewater from this
outfall discharges to UT to Dan River via Outfall 003 or to Dan River via
Outfall 006.
• Toe Drain Outfall 111 (lat. - 36017'54.94"; long. - 80.04'32.57")- potentially
contaminated toe drain. This outfall discharges to UT to Dan River.
Page 2 of 3
PROPOSED CHANGES
• Internal Outfall 006A now allows discharge of the wastewater from the
decanting procedure.
• The Water Quality Based Effluent Limits (Monthly Average and Daily Maximum)
for Total Lead have been reduced (Internal Outfall 006A) due to the increase in
the flow through this Outfall. The projected decanting flow is 5.5 MGD.
PROPOSED SCHEDULE
Draft Permit Modification to Public Notice: August 21, 2019
Permit Modification Scheduled to Issue: October 18, 2019
STATE CONTACT
If you have any questions on any of the above information or on the attached permit,
please contact Sergei Chernikov at (919) 707-3606 or sergei.chernikov@ncdenr.gov.
Page 3 of 3