HomeMy WebLinkAbout20191004 Ver 1_Field Site Review_20190730Site Information
Site Information
Date: *
Prepared By:
Meeting Type:*
USACE AID:
7/30/2019
Erin Davis
Field Site Review
NCDWR ID: 20191004
NCDWR Version 1
Weather:
Coordinates:
Attendees
USACE - Kim
DWR - Mac, Erin
RS - Alex, Barry
Project Review Checklist
(provide additional detail in notes section on next
Project Name:*
Durant's Neck
Type of Site:*
Bank Stream and Wetland Site
Sponsor/Provider:
*Bank Stream and Wetland Site
County:*
Perquimans
HUC and Basin:* Tar -Pamlico - 03020101
Degrees North Degrees West
General Site Issues/Concerns
Stream Issues/Concerns
Wetland Issues/Concerns
17 Vegetation Composition or
Density
Ir Planted Stem Vigor (due to soil,
browsing)
17 Invasive/Exotic Species
Ir Beaver/Feral Hogs
(management plan)
17 Soil (manipulation, compaction,
fertility)
Ir Livestock Present/Evidence of
Livestock Access
F- Crossings or Utility Lines
F- BMPs or Alternate Approaches
,F- Fencing Issues or Fencing
Needed
Ir Ponds Within Project Area
17 Incised/Entrenched
'7 Headcuts Present/Forming
17 Stream Structures
Failing/Piping
F- Excess Sediment/Aggradation
17 CrosslSections
Missing/Indicate Problems
Ir Bank Instability/Failure
17 Bench Rills/Erosion
(constructed bench or P2 valley)
Ir Excess Sinuosity (lack of flow)
r Braided/Anabranch Channel
IF- Evidence of Excessive
Hydrology
F- Evidence of Insufficient
Hydrology
r Hydric Soil Indicators/Soil
Series
IF- Surface Roughness or Bedding
Ir Channel Relocation/Riparian
Connectivity
17 Hydroperiod Length or
Start/Stop Date
17 Inappropriate Credit Ratio
Proposed
Ir JD Needed to Confirm
Approach
17 Continuity/Fragmentation
Ir Easement Issues (existing farm,
CE, NRCS funding)
17 Easement Encroachments
(livestock, clearing)
Ir Easement Marking/Signage
17 Insufficient Project Size
Ir Adjacent Property Owner
17 T&E Species
Ir Section 106 (historic
listing/tribal issues)
17 Insufficient Stream Drainage
Area
Ir Insufficient Hydrology (if raising
channel bed)
17 Vegetation in Channel (stream
vs wetland)
17 Flow Obstructions (undersized
pipes, fords)
17 Substrate Concerns
(embeddedness, particle size)
Ir Live Stakes Absent/Failing
17 Evidence of Water Quality
Issues
Ir Inlstream Habitat Weak/Missing
17 Stream Buffer Width Inadequate
Ir Missing Gauge Data
(preconstruction or monitoring)
17 Gauge Location/Placement
Ir Gauge Maintenance
17 Drainage Ditches/Swales
Present
Ir Field Tiles/Subsurface
Drainage
17 Continued Ag Use Adjacent to
Wetland
Page 2 --
Notes and Sketches, etc
Invasives- phrag, multiflora, cattail, wisteria, lespedeza, sweetgum,
Preservation HW - photos of flow in March, currently dry (soil saturated,
some standing water, wrack line), reference reach, buffer 100', defined
accredulations on LiDAR to determine stream vs wetland, wetland area -
standing water & OBL veg & herps, connects to creek to southwest (culvert
road crossing backwater?),
UT -10 —400' ditch/channel, all herb veg, has topo, has hydric soil;
UT -4 preservation area appears to have a channel (possibly dug - straight)
within wetland,
UT -4 near top water in channel, maybe impoundment source or
groundwater? Planted with corn, like the additional buffer!
UT -5 flow concerns, ditch appears filled in, hydric soil,
UT2 top - water present, raising bed?
UT1 &2 bottom - nice wetland / large cypress & willows (minus cattail &
phrag ), impindament holding back water, concern about impact - temp &
permanent - current wetland is high functioning system,
Gauges on all restoration reaches - discussion on flowing vs standing
water
Mac - concern about fragmentation, but like additional areas captured
"fingers" in preservation,
HW design - starter channel & add wood (from offsite),
Crossings- keeping all crossings between restoration & preservation
reaches, All crossings have duckbill risers,
More marsh treatments planned
JD not yet done, will be critical - Kyle & Anthony
Phrag will be an issue during maintenance!
Watts - reference
Credit Release/Site Closeout Information
(For nDnitoring or closeout review only)
............................................................................................................
Stream Credits
Warm Cool Cold
Requested
Approved*
Wetland Credits
Riparian Riverine Riparian Non-Riverine Non -Riparian Coastal
Requested
Approved*
*The updated credit ledger for the project, which includes this release, rrust be approved by the Roject fvbnager.
Result of Monitoring Report or Closeout
Signature *
cti,.ti,
Date 7/30/2019