HomeMy WebLinkAbout20190992 Ver 1_19-06-26_AJD_Non-JD Pond OWD_U-2719_I-440_Wake_20190723U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action Id. SAW-2012-01414 County: Wake County U.S.G.S. Quad: Cary
NOTIFICATION OF JURISDICTIONAL DETERMINATION
Applicant: North Carolina Department of Transportation
Philip Harris III
Address: 1598 Mail Service Center
Raleigh, NC, 27699
Telephone Number: 919.707.6111
Size (acres) N/A Nearest Town Ralei h
Nearest Waterway Walnut Creek River Basin Neuse
USGS HUC 03020201 Coordinates Latitude: 35.77275 Longitude:-78.72057
Location description: Approved JD is limited to vicinity of Feature OWD as indicated on the attached revised Figure
3H, I-440, U-2719, Approved JD — Non 404 Feature, revised on 6/26/2019; Overall project area is the existing I-440
Beltline corridor, from south of SR 1313 (Walnut Street) to north of SR 1728 (Wade Avenue), west of downtown
Raleigh, NC
Indicate Which of the Following Apply:
A. Preliminary Determination
_ There are waters, including wetlands, on the above described project area, that may be subject to Section 404 of the
Clean Water Act (CWA)(33 USC § 1344) and/or Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403). The
waters, including wetlands, have been delineated, and the delineation has been verified by the Corps to be sufficiently
accurate and reliable. Therefore this preliminary jurisdiction determination may be used in the permit evaluation process,
including determining compensatory mitigation. For purposes of computation of impacts, compensatory mitigation
requirements, and other resource protection measures, a permit decision made on the basis of a preliminary JD will treat all
waters and wetlands that would be affected in any way by the permitted activity on the site as if they are jurisdictional
waters of the U.S. This preliminary determination is not an appealable action under the Regulatory Program
Administrative Appeal Process (Reference 33 CFR Part 331). However, you may request an approved JD, which is an
appealable action, by contacting the Corps district for further instruction.
B. Approved Determination
There are waters of the U.S., including wetlands, on the above described project area subject to the permit requirements
of Section 404 of the Clean Water Act (CWA) (33 USC § 1344). Unless there is a change in the law or our published
regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification.
_ We recommend you have the waters of the U.S. on your property delineated. As the Corps may not be able to
accomplish this wetland delineation in a timely manner, you may wish to obtain a consultant to conduct a delineation that
can be verified by the Corps.
_ The waters of the U.S., including wetlands, on your project area have been delineated and the delineation has been
verified by the Corps. We strongly suggest you have this delineation surveyed. Upon completion, this survey should be
reviewed and verified by the Corps. Once verified, this survey will provide an accurate depiction of all areas subject to
CWA jurisdiction on your property which, provided there is no change in the law or our published regulations, may be
relied upon for a period not to exceed five years.
_ The waters of the U.S., including wetlands, have been delineated and surveyed and are accurately depicted on the plat
signed by the Corps Regulatory Official identified below on . Unless there is a change in the law or our
published regulations, this determination may be relied upon for a period not to exceed five years from the date of this
notification.
X There are no waters of the U.S., to include wetlands, present on the above described Approved JD area, which are subject
to the permit requirements of Section 404 of the Clean Water Act (33 USC 1344). Unless there is a change in the law or
our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this
notification.
Page 1 of 2
SAW-2012-01414
Placement of dredged or fill material within waters of the US, including wetlands, without a Department of the Army permit
may constitute a violation of Section 301 of the Clean Water Act (33 USC § 1311). Placement of dredged or fill material,
construction or placement of structures, or work within navigable waters of the United States without a Department of the
Army permit may constitute a violation of Sections 9 and/or 10 of the Rivers and Harbors Act (33 USC § 401 and/or 403). If
you have any questions regarding this determination and/or the Corps regulatory program, please contact Eric Alsmeyer at
(919) 554-4884 X 23 or Eric.C.Alsmever(ausace.armv.mil.
C. Basis For Determination: See attached Approved JD forms.
D. Remarks: Desktop JD is based on a based on a 9/26/2013 JD site inspection.
E. Attention USDA Program Participants
This delineation/determination has been conducted to identify the limits of Corps' Clean Water Act jurisdiction for the
particular site identified in this request. The delineation/determination may not be valid for the wetland conservation
provisions of the Food Security Act of 1985. If you or your tenant are USDA Program participants, or anticipate participation
in USDA programs, you should request a certified wetland determination from the local office of the Natural Resources
Conservation Service, prior to starting work.
F. Appeals Information for Approved Jurisdiction Determinations (as indicated in Section B. above)
If you object to this determination, you may request an administrative appeal under Corps regulations at 33 CFR Part 331.
Enclosed you will find a Notification of Appeal Process (NAP) fact sheet and Request for Appeal (RFA) form. If you request
to appeal this determination you must submit a completed RFA form to the following address:
US Army Corps of Engineers
South Atlantic Division
Attn: Jason Steele, Review Officer
60 Forsyth Street SW, Room 10M15
Atlanta, Georgia 30303-8801
In order for an RFA to be accepted by the Corps, the Corps must determine that it is complete, that it meets the criteria for
appeal under 33 CFR part 331.5, and that it has been received by the Division Office within 60 days of the date of the NAP.
Should you decide to submit an RFA form, it must be received at the above address by 8/23/2019.
It is not necessary to submit an RFA form to the Division Office if you do not object to the determination in this
correspondence.
Corps Regulatory Official:
Date: June 26, 2019 Expiration Date: June 26, 2014
MATTH EWS.MONTE.K.1284
867633
2019.06.26 12:56:56-04'00'
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete our Customer Satisfaction Survey, located online at
http:Hcop2smgpu.usace.g,M.mil/cm apex/Pp=136:4:0.
Page 2 of 2
SAW-2012-01414
NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS A
REQUEST FOR APPEAL
A licant: Philip Harris III, PhD, NCDOT
File Number: SAW-2012-01414
Date: June 26, 2019
Attached
is:
See Section below
INITIAL PROFFERED PERMIT (Standard Permit or Letter ofpermission)
A
PROFFERED PERMIT Standard Permit or Letter ofpermission)
B
PERMIT DENIAL
C
APPROVED JURISDICTIONAL DETERMINATION
D
PRELIMINARY JURISDICTIONAL DETERMINATION
E
SECTION I - The following identifies your rights and options regarding an administrative appeal of the above decision.
Additional information may be found at http://www.usace.army.mil/Missions/CivilWorks/Re ug latoryProgramandPermits.aspx or
Corps regulations at 33 CFR Part 331.
A: INITIAL PROFFERED PERMIT: You may accept or object to the permit.
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature
on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the
permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit.
• OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request that the
permit be modified accordingly. You must complete Section II of this form and return the form to the district engineer. Your
objections must be received by the district engineer within 60 days of the date of this notice, or you will forfeit your right to appeal
the permit in the future. Upon receipt of your letter, the district engineer will evaluate your objections and may: (a) modify the
permit to address all of your concerns, (b) modify the permit to address some of your objections, or (c) not modify the permit
having determined that the permit should be issued as previously written. After evaluating your objections, the district engineer
will send you a proffered permit for your reconsideration, as indicated in Section B below.
B: PROFFERED PERMIT: You may accept or appeal the permit
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature
on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the
permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit.
• APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein, you
may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form
and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of
this notice.
C: PERMIT DENIAL: You may appeal the denial of a permit under the Corps of Engineers Administrative
Appeal Process by completing Section II of this form and sending the form to the division engineer. This form
must be received by the division engineer within 60 days of the date of this notice.
D: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or
provide new information.
• ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the date of
this notice means that you accept the approved JD in its entirety, and waive all rights to appeal the approved JD.
• APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers Administrative
Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by
the division engineer within 60 days of the date of this notice.
E: PRELIMINARY JURISDICTIONAL DETERMINATION: You do not need to respond to the Corps
regarding the preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved
JD (which may be appealed), by contacting the Corps district for further instruction. Also you may provide new
information for further consideration by the Corps to reevaluate the JD.
SECTION II - REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT
SAW-2012-01414
REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your
objections to an initial proffered permit in clear concise statements. You may attach additional information to
this form to clarify where your reasons or objections are addressed in the administrative record.)
ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps
memorandum for the record of the appeal conference or meeting, and any supplemental information that the
review officer has determined is needed to clarify the administrative record. Neither the appellant nor the Corps
may add new information or analyses to the record. However, you may provide additional information to clarify
the location of information that is already in the administrative record.
POINT OF CONTACT FOR QUESTIONS OR INFORMATION:
If you have questions regarding this decision and/or the
If you only have questions regarding the appeal process you may
appeal process you may contact:
also contact:
District Engineer, Wilmington Regulatory Division, Attn:
Mr. Jason Steele, Administrative Appeal Review Officer
Eric Alsmeyer
CESAD-PDO
Raleigh Regulatory Field Office
U.S. Army Corps of Engineers, South Atlantic Division
3331 Heritage Trade Drive, Suite 105
60 Forsyth Street, Room 1OM15
Wake Forest, NC 27587
Atlanta, Georgia 30303-8801
Phone: (919) 554-4884, ext. 23
Phone: 404 562-5137
RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government
consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15 day
notice of any site investigation, and will have the opportunit to participate in all site investigations.
Date:
Telephone number:
Signature of appellant or agent.
For appeals on Initial Proffered Permits send this form to:
District Engineer, Wilmington Regulatory Division, Attn: Eric Alsmeyer, 69 Darlington Avenue, Wilmington, North
Carolina 28403
For Permit denials, Proffered Permits and approved Jurisdictional Determinations send this form to:
Division Engineer, Commander, U.S. Army Engineer Division, South Atlantic, Attn: Mr. Jason Steele,
Administrative Appeal Officer, CESAD-PDO, 60 Forsyth Street, Room 1OM15, Atlanta, Georgia 30303-8801
Phone: (404) 562-5137