HomeMy WebLinkAbout20190992 Ver 1_17-06-21-NCDOT_U-2719-PJD_20190723U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action Id. SAW-2012-01414 County: Wake U.S.G.S. Quad: Cary
NOTIFICATION OF JURISDICTIONAL DETERMINATION
Applicant: Philip Harris, III, P.E.,
Pro aect Development and Environmental Analysis Branch
North Carolina Department of Transportation
1598 Mail Service Center
Raleigh, NC, 27699-1598
Telephone Number: 919-707-6111 (Jason Dilday)
Size (acres) N/A Nearest Town Raleigh
Nearest Waterway Walnut Creek River Basin Neuse
USGS HUC 03020201 Coordinates Latitude: 35.778, Longitude:-78.717
Location description: Study Area for existing I-440 Beltline, from south of SR 1313 (Walnut Street) to north of SR 1728
(Wade Avenue), west of downtown Raleigh, NC
Indicate Which of the Following Apply:
A. Preliminary Determination
X There are waters, including wetlands, on the above described project area, that may be subject to Section 404 of the Clean
Water Act (CWA)(33 USC § 1344) and/or Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403). The
waters, including wetlands, have been delineated, and the delineation has been verified by the Corps to be sufficiently accurate
and reliable. Therefore this preliminary jurisdiction determination may be used in the permit evaluation process, including
determining compensatory mitigation. For purposes of computation of impacts, compensatory mitigation requirements, and other
resource protection measures, a permit decision made on the basis of a preliminary JD will treat all waters and wetlands that
would be affected in anyway by the permitted activity on the site as if they are jurisdictional waters of the U.S. This preliminary
determination is not an appealable action under the Regulatory Program Administrative Appeal Process (Reference 33 CFR Part
331). However, you may request an approved JD, which is an appealable action, by contacting the Corps district for further
instruction.
B. Approved Determination
_ There are waters of the U.S., including wetlands, on the above described project area subject to the permit requirements of
Section 404 of the Clean Water Act (CWA) (33 USC § 1344). Unless there is a change in the law or our published regulations,
this determination may be relied upon for a period not to exceed five years from the date of this notification.
_ We recommend you have the waters of the U.S. on your property delineated. As the Corps may not be able to accomplish
this wetland delineation in a timely manner, you may wish to obtain a consultant to conduct a delineation that can be verified by
the Corps.
_ The waters of the U.S., including wetlands, on your project area have been delineated and the delineation has been verified
by the Corps. If you wish to have the delineation surveyed, the Corps can review and verify the survey upon completion. Once
verified, this survey will provide an accurate depiction of all areas subject to CWA and/or RHA jurisdiction on your property
which, provided there is no change in the law or our published regulations, may be relied upon for a period not to exceed five
years.
_ The waters of the U.S., including wetlands, have been delineated and surveyed and are accurately depicted on the plat signed
by the Corps Regulatory Official identified below on . Unless there is a change in the law or our published
regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification.
_ There are no waters of the U.S., to include wetlands, present on the above described project area which are subject to the permit
requirements of Section 404 of the Clean Water Act (33 USC 1344). Unless there is a change in the law or our published
regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification.
Page 1 of 2
SAW-2012-01414
Placement of dredged or fill material within waters of the US, including wetlands, without a Department of the Army permit may
constitute a violation of Section 301 of the Clean Water Act (33 USC § 1311). Placement of dredged or fill material, construction or
placement of structures, or work within navigable waters of the United States without a Department of the Army permit may
constitute a violation of Sections 9 and/or 10 of the Rivers and Harbors Act (33 USC § 401 and/or 403). If you have any questions
regarding this determination and/or the Corps regulatory program, please contact Eric Alsmever at (919) 554-4884 X 23 or
Eric.C.Als meyer(a,usace.army. mil.
C. Basis For Determination: The study area contains jurisdictional waters of the US, Swift, Walnut and Horse Creeks,
Simmons Branch, and tributaries, with ordinary high water marks, impoundments, and adjacent wetlands. These waters are tributaries
of the Neuse River, a Section 10 Water.
D. Remarks: This JD was confirmed by field inspection on 9/26/2013, and desktop review on 6/20/2017 (Features in
Addendum). The drawings on the attached Figures "I-440, U-2719, Wake County, North Carolina, Jurisdictional Features", 3A
through 3M, dated NOV 2013, and Figures 1, 3A, and 3N, dated February 2017, generally depict the approximate boundaries and
locations of potential jurisdictional waters of the US within the subject study area.
E. Attention USDA Program Participants
This delineation/determination has been conducted to identify the limits of Corps' Clean Water Act jurisdiction for the particular site
identified in this request. The delineation/determination may not be valid for the wetland conservation provisions of the Food Security
Act of 1985. If you or your tenant are USDA Program participants, or anticipate participation in USDA programs, you should request
a certified wetland determination from the local office of the Natural Resources Conservation Service, prior to starting work.
**It is not necessary to submit an RFA form to the Division Office if you do not object to the determination in this correspondence.**
MATTHEWS.MONTE.K.1284867633 DN:t=US,ally signed GovernMATTHment,
ou= oD, 1284867633
DN: c=US, —U.S.o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=MATTHEWS.MONTE.K.1284867633
Date: 2017.06.21 10:04:30-04-00'
Corps Regulatory Official:
Date: June 21, 2017 Expiration Date: N/A
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete our Customer Satisfaction Survey, located online at
http:HcoKpsmgpu.usace.anny.mil/cm apex/f?p=136A:0.
Copy Furnished: Atkins North America Inc.
Jill Gurak
1616 East Millbrook Road, Suite 310
Raleigh, NC, 27607-4968
SAW-2012-01414
NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND
REQUEST FOR APPEAL
Applicant: Philip Harris, III, P.E.
File Number: SAW-2012-01414
Date: June 21, 2017
NC Department of Trans ortation
Attached
is:
See Section below
❑
INITIAL PROFFERED PERMIT (Standard Permit or Letter of permission)
A
❑
PROFFERED PERMIT (Standard Permit or Letter of permission)
B
❑
PERMIT DENIAL
C
❑
APPROVED JURISDICTIONAL DETERMINATION
D
®
PRELIMINARY JURISDICTIONAL DETERMINATION
E
SECTION I - The following identifies your rights and options regarding an administrative appeal of the above decision.
Additional information may be found at http://www.usace.g=.mil/Missions/CivilWorks/Re ug latoD ProgramandPennits.aspx or
Corps regulations at 33 CFR Part 331.
A: INITIAL PROFFERED PERMIT: You may accept or object to the permit.
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your
signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all
rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the
permit.
• OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request
that the permit be modified accordingly. You must complete Section II of this form and return the form to the district
engineer. Your objections must be received by the district engineer within 60 days of the date of this notice, or you will
forfeit your right to appeal the permit in the future. Upon receipt of your letter, the district engineer will evaluate your
objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your
objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After
evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in
Section B below.
B: PROFFERED PERMIT: You may accept or appeal the permit
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final
authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your
signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all
rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the
permit.
• APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein,
you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of
this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days
of the date of this notice.
C: PERMIT DENIAL: You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by
completing Section II of this form and sending the form to the division engineer. This form must be received by the division
engineer within 60 days of the date of this notice.
D: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new
information.
• ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the
date of this notice, means that you accept the approved JD in its entirety, and waive all rights to appeal the approved JD.
• APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers
Administrative Appeal Process by completing Section II of this form and sending the form to the district engineer. This form
must be received by the division engineer within 60 days of the date of this notice.
E: PRELIMINARY JURISDICTIONAL DETERMINATION: You do not need to respond to the Corps regarding the
preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved JD (which may be appealed),
by contacting the Corps district for further instruction. Also you may provide new information for further consideration by the
Corps to reevaluate the JD.
SAW-2012-01414
SECTION 1I - REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT
REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your objections to an initial
proffered permit in clear concise statements. You may attach additional information to this form to clarify where your reasons or
objections are addressed in the administrative record.)
ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps memorandum for the
record of the appeal conference or meeting, and any supplemental information that the review officer has determined is needed to
clarify the administrative record. Neither the appellant nor the Corps may add new information or analyses to the record.
However, you may provide additional information to clarify the location of information that is already in the administrative
record.
POINT OF CONTACT FOR QUESTIONS OR INFORMATION:
If you have questions regarding this decision and/or the
If you only have questions regarding the appeal process you may
appeal process you may contact:
also contact:
District Engineer, Wilmington Regulatory Division,
Mr. Jason Steele, Administrative Appeal Review Officer
Attn: Eric Alsmeyer
CESAD-PDO
Raleigh Regulatory Field Office
U.S. Army Corps of Engineers, South Atlantic Division
3331 Heritage Trade Drive, Suite 105
60 Forsyth Street, Room 1OM15
Wake Forest, NC 27587
Atlanta, Georgia 30303-8801
Phone: (404) 562-5137
RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government
consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15 day
notice of any site investigation, and will have the opportunity to participate in all site investigations.
Date:
Telephone number:
Signature of appellant or agent.