HomeMy WebLinkAboutEmail RE Construction Stormwater NOI Not Accepted - 13900 Morman, Alaina
From: laserfiche@ncdenr.gov
Sent: Wednesday, July 24, 2019 3:55 PM
To: Thomas.WilliamsJr@duke-energy.com
Cc: McCoy, Suzanne; Gail.Tyner@duke-energy.com
Subject: Construction Stormwater NOI Not Accepted
This email is to notify you that your application for Morehead Wildwood-Harlowe 115kV Line Loop into
Harlowe Substation was not accepted for the following reason:
Part A14 must be converted to acres.
Part A15B Waterbody index no. is 21-22
Please submit a new application.
Please contact The Stormwater Program Administrative Assistant for more information at (919) 707-
3640. Please reference NOI application no. 13900 and Project ID NCC-CARTE-2019-Morehead Wildwood-
Harlowe 115kV Line Loop into Harlowe Substation.
This email was automatically generated by Laserfzche. Please do not respond to this email address, as
responses are not monitored.