HomeMy WebLinkAbout20090900 Ver 1_401 Application_20090809-r--MULKEY
ENGINEERS & C O N S U LTA N T S
August 31, 2009
Mr. Andrew Williams
Regulatory Project Manager
U.S. Army Corps of Engineers
Wilmington District, Raleigh Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
SUBJECT: Nationwide Permit Application for Burning Tree Drive Drainage
Improvements Project, Town of Chapel Hill, Orange County
Dear Mr. Williams,
The Town of Chapel Hill (Town) proposes to construct drainage improvements to address
stormwater control problems in The Oaks subdivision at Chapel Hill Country Club in
Orange County. The project site is within USGS hydrologic unit 03030002 and is part of the
Little Creek drainage in the Cape Fear River Basin. An unnamed tributary (UT) to Little
Creek occurs in the project area and is identified by NC Division of Water Quality Index
Number 16-41-1-15-(0.5). The location of the project is shown on the attached Figures 1
through 3.
The overall project as proposed will install new stormwater collection system components
which will include new yard basins, catch basins, junction boxes, and concrete pipes along
Burning Tree Drive and Pinehurst Drive. Construction will primarily occur in upland areas;
however, the project includes placement of fill in the UT to Little Creek where it occurs at
Burning Tree Drive and in a manmade stormwater pond that is hydrologically connected to
Little Creek. The Town is requesting these impacts be authorized under the Nationwide
Permit program. It is anticipated that several different permits will apply to the different
types of fill created by this proposed project, as described below.
0 Installation of a rip-rap energy dissipater pad on the UT to Little Creek will create
impacts below an existing 42-inch diameter pipe outlet at Burning Tree Drive. The
stream banks at the pipe outlet have been severely eroded from stormwater scour
such that the pipe is perched above the channel. Approval for dissipater pad impacts
is requested under NWPs 13 and 39 as this work is being completed to prevent
further erosion of the channel which is being used as part of the Town's overall
storm water management facilities in the community.
Channel stabilization would also include installation of a rock cross vane structure
immediately downstream from the dissipater pad. It is requested this work be
authorized by NWP 27 as the rock vane will enhance stream stability and aquatic
habitats by directing flow into the middle of the channel and away from the banks.
Geotextile fabric will be used in the channel under the energy dissipater pad and rock
August 31, 2009
Page 2
cross vane. Inspection (monitoring) of the rock vane for five years from date of
construction is proposed to ensure it functions as designed.
Existing dual 24-inch pipes on the UT to Little Creek will be replaced with a new 6-
foot by 3-foot precast concrete box culvert. The current pipes provide a golf cart
path crossing of the stream at the 17`h hole golf course fairway and are undersized
for current stormwater volumes. The Town requests approval under NWP 3 for
maintenance activities to replace the pipes with a box culvert with wing walls and rip-
rap for stabilization at the inlet and outlet side of the culvert.
Stormwater collected in upland areas will be directed through new pipes installed
along Pinehurst Drive and discharged into a man-made pond located adjacent to
Pinehurst Drive; the pond is hydrologically connected through a series of
downstream ponds to Little Creek. The pond is currently used by the golf course for
stormwater retention and turfgrass irrigation. Impacts will be created by
construction of the dual 36-inch pipes with headwall structure to sit below the
normal water surface elevation. The pipe outlet will be submerged as a safety
measure to prevent pedestrians and domestic pets from entering the pipes. Approval
for this work is requested under NWP 12 for utility line activities.
Work completed in the UT to Little Creek and the stormwater pond will be
completed in dry conditions. To accomplish this, approval is requested under NWP
33 for use of a temporary dewatering system using check dams, sand bags, and
diversion pipes.
Temporary impacts will occur to the UT to Little Creek from installation of coir
fiber matting at two floodplain drainways that will be created downstream of the
rock vane. The low berm located along the right top of bank on the UT to Little
Creek will be breached in two places to reconnect adjacent residential yards to the
stream channel and allow overbank flood waters and stormwater detention to drain
back into the UT channel. Coir fiber matting will be installed in the drainways and at
the top of bank on the UT to stabilize disturbed areas and will be anchored with live
stake vegetation.
Please find attached a permit application package which includes a Pre-Construction
Notification form, list of property owners, figures, photographs, permit drawings, half-sized
plan sheets, and a CD with electronic copies of the permit documents. The USACE
Rapanos determination forms were previously submitted for review; however, an electronic
copy of the forms is included on the CD. We anticipate that corresponding Section 401
General Water Quality Certifications will be authorized by the North Carolina Division of
Water Quality through the Express Review program. The Town of Chapel Hill and its
contractors will comply with all conditions of the 404/401 permits.
August 31, 2009
Page 3
If you have any questions or comments concerning the project or this application package,
please contact me at (919) 858-1871 or by email to ccarr&mulkeyinc.com. You may also
contact Chris Jensen, Town of Chapel Hill, at (919) 969-7233.
Thank you for your assistance.
Sincerely,
Cindy Simpson Carr
Senior Scientist
Mulkey Engineers & Consultants, Inc.
CC w/Attachments
Lia Gilleski, DWQ 401 Express Permit Unit
Chris Jensen, Town of Chapel Hill
Version 1.4
January 9, 2009
401 Oversight/Express Permitting PCN Submittal Checklist
Ef The application fee (Checks may be made out to "N.C. Division of Water Quality"
- $240.00 for 401 Water Quality Certification with minor impacts
- $570.00 for 401 Water Quality Certification with major impacts
- Express Review Fee (Amount requested on Acceptance Letter)
[ Five (5) complete and collated copies of the PCN Application and supporting
documentation (instead of providing 5 copies of the full size plans you may provide two
copies of full size plans along with three copies of 11 X 17 plans)
•? Stormwater Management Plan (if applicable - see PCN Form Help File Section E)
1) Please provide three (3) copies of the stormwater management plans along with all
supporting information pertaining to this project including the following:
a. Entire site development/layout plans delineating all drainage areas;
b. Design calculation sheets for all proposed BMPs) sized for both on-site and
off-site drainage;
c. BMP supplements for each proposed BMP and Required Items Check List
(http://h2o.enr.state.nc.us/su/bmp forms.htm) along with all required
items;
d. A Notarized Operation & Maintenance Agreement for each stormwater
management facility;
e. Detailed construction drawing sheets shall include
(i) Erosion and sediment control plans;
(ii) Installation and planting schedules for the proposed BMPs;
(iii) Appropriately scaled plan views and cross sectional details of all
BMPs and associated components - inlet and outlet structures,
forebay, respective zones and pertinent elevations.
If your project is located within a State implemented Riparian Buffer Rule Area, submit the
following along with site plans and PCN form:
1) Three (3) copies of the details for on-site diffuse flow provisions, (refer to
http://h2o.enr.state.nc.us/su/bmp_jorms.htm).
DWQ Stream Determination Forms for streams on property and DWQ determination
letter for wetlands or streams (if applicable).
The following is the most critical of all the information that you must provide. The quality and
detail of the information will often determine the expeditiousness of the review. The following is
a checklist of the types of pertinent information required at a minimum:
Maps and Plans:
The most recent version of the 1:24,000 USGS Topographic Map - Please cleanly draw or
delineate the site boundaries on the topographic map.
r
The most recent version of the bound and published County NRCS Soil Survey Map -
(required for projects within the Neuse River Basin, Tar-Pamlico River Basin, Randleman
Lake Watershed and the Catawba River Basin, also recommended for all projects) -
Please clearly delineate the site boundaries, etc. on the map. If the delineation obscures
any of the features, it is recommended that a clean copy be provided. Copies of the
Version 1.4
January 9, 2009
current soil survey and/or soil survey map sheets can be obtained from the local NRCS
County Office (http://www.nc.nres.usda.gov/). GIS soil layers are not acceptable.
Vicinity map - Please clearly mark the location and approximate boundaries of the property
and project on the map. Please indicate north arrow and scale. Please include applicable
road names or State Road numbers.
`0 The Site Plan - The most critical map to be provided is the site plan. You must provide full
sized plans. The following is the minimum list of plans that are typically needed.
Q Pre-construction/Pre-existing conditions - This sheet (or sheets) must include:
• All jurisdictional and non-jurisdictional wetland, stream, water features, State regulated
buffers (delineated into Zones 1 and 2)
• Topographic contours with elevations
• Any existing structures and impervious areas
• Existing utility lines and easements
• Existing roads, culverts, and other pertinent features
• North arrow and the scale (1":50' scale is recommended).
0 Proposed conditions - This sheet (or sheets) must include:
• All jurisdictional and non-jurisdictional wetland, stream, water features, State regulated
buffers (delineated into Zones 1 and 2)
• Lot layout (if a subdivision or commercial development is proposed) - lots must be
developable without further impacts to jurisdictional and. non-jurisdictional wetlands,
streams, water features, and State regulated buffers. Building envelopes must be
provided when streams, wetlands, riparian buffers, or water features exist on a lot
• All built-out structures and impervious cover
• Final grading contours with elevations
• All utilities and easements (including septic fields on all lots within 100 feet of stream,
wetland, or water features - if applicable)
• Impacted areas - these should correspond with the Impact numbers listed on your PCN
form.
, Drainage Plans - Final drainage plans must include the following:
• Locations and pertinent elevations and sizes of the stormwater collection system and
drainage ways
• All inlets and outlets must also be shown with pertinent elevations (All outlets to
wetlands must be at a non-erosive velocity, generally less than 2 ft/sec during the peak
flow from the 10-yr storm)
• Scaled stormwater BMPs must also be indicated as required by DWQ rules and policies
• In certain cases (see Section E of PCN form), final stormwater management plans must
also be provided (see Stormwater Management Plan Checklist)
[] Proposed Impacts - All impacts to jurisdictional and non-jurisdictional wetland, stream,
water features, and State regulated buffers must be shown and labeled on the site plans at
a scale no smaller than 1" = 50'. All excavation, fill, flooding, stabilization, and other impacts
that will be conducted in or near jurisdictional and non-jurisdictional wetland, stream, water
features, and State regulated buffers must be indicated. Please provide cross sectional
details showing the provisions for aquatic life passage (burial of culvert 20% for culverts <_ 48
inches, and 1-foot for culverts > 48 inches).
Version 1.4
January 9, 2009
Wetland Impacts:
Precise grading and final elevation contours must be provided. Existing
vegetation and any clearing must be specified.
fi All subsurface utility lines must indicate the location of anti-seep collars.
Construction detail for anti-seep collars must be provided.
?I
Roadway or other crossings of riparian wetlands may require floodway culverts to
maintain existing hydrological conditions.
Plans should show that the hydrology of remaining wetlands on the site will be
maintained.
Stream Impacts:
Q Stream impacts must be clearly shown on the plans. The centerline as well as
the banks of the stream must be surveyed or located by GPS for the portion of
the stream to be impacted.
The inlet and the outlet of all culverts should be aligned with the stream as
much as possible. Inlet and outlet elevations and streambed elevations should
be indicated. Any inlet or outlet protection must be shown and enumerated on
the impact map(s).
For bottomless culverts or other spans, a vertical cross section should be
provided that shows the minimum distance from each span to each stream bank,
the stream cross section, the height of the span above the stream and the
minimum distance from the edge of each footer to each stream bank.
Additionally, please provide a signed and sealed geotechnical report of
subsurface soils at the proposed bottomless culvert location. The report must
comply with the Division of Highways - Guidelines for Drainage Studies and
Hydraulic Design, prepared by A.L. Hankins, Jr., State Hydraulics Engineer -
1999.
Multiple culverts or sectioned box culverts typically require the use of sills, off-
setting or other means to match the cross section of the existing stream (in order
to maintain stream stability and provide aquatic life passage). A vertical cross
section of the culverts should be shown overlain with the up and downstream
stream cross section including the stream flood-prone area.
+?® Impacts associated with dam construction must indicate and enumerate all fill
associated with the dam footprint, spillway and any bank stream bank
stabilization. The length of stream impounded must also be indicated and
enumerated.
O?Of w A T??p?
li
? Y
Office Use Only:
Corps action ID no.
DWQ project no.
Form Version 1.3 Dec 10 2008
Pre-Construction Notification (PCN) Form
A. Applicant Information
1. Processing
1 a. Type(s) of approval sought from the
Corps:
®Section 404 Permit E] Section 10 Permit
1b. Specify Nationwide Permit (NWP) number: 3, 12, 13, 27, 33, 39 or General Permit (GP) number:
1c. Has the NWP or GP number been verified by the Corps? ? Yes ® No
1 d. Type(s) of approval sought from the DWQ (check all that apply):
E 401 Water Quality Certification - Regular ? Non-404 Jurisdictional General Permit
? 401 Water Quality Certification - Express Riparian Buffer Authorization
1 e. Is this notification solely for the record
because written approval is not required? For the record only for DWQ 401
Certification:
? Yes ® No For the record only for Corps Permit:
? Yes ® No
1f. Is payment into a mitigation bank or in-lieu fee program proposed for mitigation
of impacts? If so, attach the acceptance letter from mitigation bank or in-lieu
fee program. ? Yes ® No
1 g. 1s the project located in any of NC's twenty coastal counties. If yes, answer 1 h
below. ? Yes ® No
1h. Is the project located within a NC DCM Area of Environmental Concern (AEC)? ? Yes ® No
2. Project Information
2a. Name of project: Burning Tree Drive Stormwater Improvements
2b. County: Orange
2c. Nearest municipality/ town: Chapel Hill
2d. Subdivision name: Chapel Hill Country Club Subdivision
2e. NCDOT only, T.I.P. or state
project no: n/a
3. Owner Information
3a. Name(s) on Recorded Deed: See attached Table 1 for list of names
3b. Deed Book and Page No. Municipal Project
3c. Responsible Party (for LLC if
applicable): Chris Jensen, Town of Chapel Hill, Stormwater Management Division
3d. Street address: 405 Martin Luther King Jr. Blvd.
3e. City, state, zip: Chapel Hill, NC 27514-5705
3f. Telephone no.: (919) 969-7233
3g. Fax no.: (919) 969-7276
3h. Email address: cjensen@townofchapelhill.org
Page 1 of 12
PCN Form - Version 1.3 December 10, 2008 Version
4. Applicant Information (if different from owner)
4a. Applicant is: ? Agent ? Other. specify:
4b. Name: Chris Jensen. Town of Chapel Hill, Stormwater Management Division
4c. Business name
(if applicable):
4d. Street address: 405 Martin Luther King Jr. Blvd.
4e. City. state. zip: Chapel Hill, NC 27514-5705
4f. Telephone no.: (919) 969-7233
4g. Fax no.: (919) 969-7276
4h. Email address: cjensen@townofchapelhill.org
5. AgenVConsultant Information (if applicable)
5a. Name: Cindy Carr
5b. Business name
(if applicable): Mulkey Engineers & Consultants. Inc.
5c. Street address: P.O. Box 33127
5d. City. state, zip: Raleigh, NC 27636-3127
5e. Telephone no.: (919) 858-1871
5f. Fax no.: (919) 851-1918
5g. Email address: ccarr@mulkeyinc.com
Page 2 of 12
PCN Form - Version 1.3 December 10, 2008 Version
B. Project Information and Prior Project History
1. Property Identification
1a.
Property identification no. (tax PIN or parce# ID): Municipal Project
(see Table 1 list of private property owners)
1b.
&te coordinates (in decimal degrees): Latitude: 35.9161843
Longitude: - 79.0140264
(DD.DDDDDD) (-DD.DDDDDD)
1c. Property size: nla acres
2. Surface Waters
2a. Name of nearest body of water (stream, river, etc.) to
proposed project: Little Creek
2b. Water Duality Classification of nearest receiving water: WS-IV NSW
2c. River basin: Cape Fear
Page 3 of 12
PCN Form - Version 1.3 December 10, 2008 Version
3. Project Description
3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this
application:
The proposed project is located in Orange County, within the Chapel Hill Oaks Subdivision and Chapel Hill Country
Club (see Figures 1 and 2).
Land within the subdivision is developed for large lot single family residences (0.5 to i acre) and an 18-hole golf
course with country club facilities. The topography is relatively flat to moderately sloped within the subdivision.
Residential yards are manicured lawns surrounded by a mature overstory of mixed pine and hardwoods and understory
of horticulture plantings. In naturalized areas the understory is relatively clear due to landscape maintenance activities,
deer browse, and shading effects. The subdivision has an existing underground stormwater collection system, comprised
of curb inlets. catch basins, junction boxes. and concrete pipes, which is maintained by the Town of Chapel Hill. The golf
course has several large, constructed ponds located on the east side of Pinehurst Drive that are used for storm water
storage and to irrigate the golf course turfgrass.
Approximately 1,775 linear feet of an intermittent/perennial stream, an unnamed tributary (LIT) to Little Creek, flows
northeastward through the subdivision and crosses two golf course fairways. The stream flows through small diameter
corrugated plastic pipes on the golf fairways and through a 42-inch diameter reinforced concrete pipe at Burning Tree
Drive. The high stream bank at the Burning Tree Drive pipe outlet shows evidence of severe erosion and scouring at the
pipe outlet has resulted in the pipe perching above the channel. Scour has also occurred where the UT flows through
dual 24-inch corrugated plastic pipes at the 17th fairway golf cart path. A low spoil cast pile exists at the top of banks
downstream of Burning Tree Drive and this low berm prevents stormwater from receding into the creek.
Attached photo log shows existing conditions of these areas. Figure 2 identifies the location where proposed work will
create impacts to the UT to Little Creek and to a stormwater pond located near the Pinehurst Drive and Burning Tree
Drive intersection.
3b. List the total estimated acreage of all existing wetlands on the property:
There are no wetlands within the areas proposed for construction of stormwater control measures.
3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property:
Over 7.000 linear feet of intermittent and perennial streams are located within the subdivision and golf course.
Approximately 850 linear feet of the intermittent LIT to Little Creek is located between Burning Tree Drive and its
confluence with Little Creek.
3d. Explain the purpose of the proposed project:
The overall project as proposed will
install new stormwater collection yard basins. catch basins. junction boxes, and concrete pipes in upland areas along
Burning Treet Drive and Pinehurst Drive;
redirect stormwater collected from existing components to the new catch basins, junction boxes, and concrete pipes;
install dual 36-inch diameter stormwater pipe outlets to carry stormwater collected by new upland yard inlets into an
existing man-made stormwater pond adjacent to Pinehurst Drive near the Burning Tree Driver intersection.
install a rip-rap energy dissipater pad below the Burning Tree Drive pipe outlet;
install a rock cross vane below the new rip-rap energy dissipater pad;
breach the low berm on the right bank of LIT to Little Creek in two locations to reconnect and improve floodwater
drainage downstream from Burning Tree Drive (breach will be above the ordinary high water mark); and
replace undersized dual 24-inch diameter corrugated plastic pipes at the 17th hole fairway golf cart path with a precast
concrete 6-foot by 3-foot box culvert.
Page 4 of 12
PCN Form - Version 1.3 December 10. 2008 Version
3e. Describe the overall project in detail, including the type of equipment to be used:
Proposed impacts covered by this permit application include the installation of a rip-rap energy dissipator pad on UT to
Little Creek below the Burning Tree Drive pipe outlet; installation of a rock cross vane structure immediately downstream
from the dissipator pad; installation of coir fiber matting at two floodplain drainways created by breaching low berm on UT
to Little Creek; replacing the dual 24-inch plastic pipes at the 17th hole fairway golf cart path; and installing stormwater
pipe outlets in a stormwater retention pond adjacent to Pinehurst Drive. Other stormwater system improvements and
required underground utility relocation work will occur in uplands and will not impact jurisdictional resources.
The rip-rap energy dissipator pad and rock cross vane witl be installed to reduce bank erosion below the perched
Burning Tree Drive pipe outlet. The energy dissipator pad will be approximately 1.7 feet deep.. with the shape conforming
to the natural channel geomorphology to provide a smooth transition from end of apron to natural channel width. A rock
cross vane will be constructed at the end of the dissipator pad to provide stability and to direct water flows into the center
of the channel and away from the banks. Geotextile fabric will be used in the channel under the energy dissipater pad
and rock cross vane. A temporary coffer dam and diversion pipe will be used to divert water flow so work can be
performed in dry conditions. Vegetation will be planted along the disturbed banks to provide stabilization and to anchor
the geotextile fabric.
The low berm located along the right top of bank on the UT to Little Creek, between Burning Tree Drive and the 17th
hole fairway, will be breached in two places downstream from the rock cross vane. The breaches will be made above the
ordinary high water mark and in areas where tree removal will not be required. Two shallow floodplain drainways will be
built in upland areas to reconnect adjacent residential yards to the stream channel and allow overbank flood waters and
stormwater detention to drain back into the UT channel, thereby alleviating stormwater retention in adjacent residential
yards. Coir fiber matting will be installed in the drainways and at the top of bank on the UT to stabilize disturbed areas
and will be anchored with live stake vegetation.
The dual 24-inch diameter corrugated plastic pipes located under the 17th hole fairway paved golf cart path will be
removed and replaced with a precast 6-foot by 3-foot concrete box culvert with head wall and wing walls. The new box
culvert will provide increased capacity to carry storm water flows in the UT to Little Creels channel, thereby alleviating
backwater bank and channel scouring and flooding into residential yards. Temporary cofferdams and diversion pipe will
be used to divert water flow so work can be performed in dry conditions.
Dual 36-inch diameter reinforced concrete pipe outlets with a concrete headwall will be installed to carry stormwater
into the golf course stormwater management pond (P1) located on the east side of Pinehurst Drive. The pipes will be
constructed to sit below the normal open water surface elevation. Temporary sand bags and a water diversion pipe will
be used during construction so work can be performed in dry conditions.
Construction equipment will include a track hoe and front loader, dump trucks for material delivery, hand tools, and
other common construction equipment used in underground utility construction as needed.
4. Jurisdictional Determinations
4a. Have jurisdictional wetland or stream determinations by the
Corps or State been requested or obtained for this property /
®Yes ? No ? Unknown
project (including all prior phases) in the past?
Comments.
4b. If the Corps made the jurisdictional determination, what type ® Preliminary ? Final
of determination was made?
4c. If yes, who delineated the jurisdictional areas? Agency"Consultant Company: Mulkey Engineers &
Consultants. Inc.
Name (if known): Cindy Carr Other:
4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation.
Field JD review completed with USACE on October 3, 2007 and Rapanos forms submitted on October 8, 2007.
5. Project History
5a. Have permits or certifications been requested or obtained for ? Yes ? No ® Unknown
this project (including all prior phases) in the past?
5b. If yes, explain in detail according to "help file" instructions.
6. Future Project Plans
6a. Is this a phased project? ? Yes ® No
6b. If yes. explain.
Page 5 of 12
PCN Form - Version 1.3 December 10, 2008 Version
U. rrupuseU unpacks invenwry
1. Impacts Summary
1a. Which sections were completed below for your project (check all that apply):
? Wetlands ® Streams - tributaries Buffers
® Open Waters ? Pond Construction
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
2a. 2b. 2c. 2d. 2e. 2f.
Wetland impact Type of jurisdiction
number - Type of impact Type of wetland Forested (Corps - 404, 10 Area of impact
Permanent (P) or (if known) DWQ - non-404, other) (acres)
Temporary T
W 1 ? P ? T ? Yes
?No ? Corps
?DWQ
W2 ?P?T ? Yes ? Corps
?No ?DWQ
W3 ? P ? T ? Yes ? Corps
? No ? DWO
W4 ? P ? T ? Yes ? Corps
?No ?DWQ
W5 ? P ? T ? Yes ? Corps
? No ? DWQ
W6 ? P ? T ? Yes ? Corps
? No ? DW Q
2g. Total wetland impacts
2h. Comments: There are no wetland impacts.
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted.
3a. 3b. 3c. 3d. 3e. 3f. 3g.
Stream impact Type of impact Stream name Perennial Type of jurisdiction Average Impact
number - (PER) or (Corps - 404, 10 stream length
Permanent (P) or intermittent DWQ - non-404, width (linear
Temporary (T) (INT)? other) (feet) feet)
Fill
S1 ®P ? T (rip-rap energy
dissipater pad, rock UT Little Creek ® PER
? INT Z Corps
? DWQ 5 50
cross vane)
I Fill
R Z Corps
S2 [K PEI T (culvert wing wall, UT Little Creek NT ? DWQ 5 33
rip-rap)
S3 ? P ? T ? PER ? Corps
? INT ? DWQ
S4 ? PEI T ? PER ? Corps
? INT ? DWQ
S5 ? P ? T ? PER ? Corps
? INT ? DWQ
S6 ? P ? T ? PER ? Corps
? INT ? DWQ
311. Total stream and tributary impacts 83
3i. Comments Total Permanent impacts = 83 linear feet. Total Temporary impacts = 136 linear feet.
S1 (Site 1) and S2 (Site 2) impact areas are shown on permit drawing Sheet 11 of 12.
Page 6 of 12
PCN Form - Version 1.3 December 10, 2008 Version
S1 permanent impacts of 50 LF (resulting in 540 square feet or 0.012 acre) are for installation of a rip-rap energy dissipator
pad and rock cross vane.
S1 Temporary impacts of 100 LF (resulting in 653 square feet or 0.015 acre) will occur from use of check dams for
dewatering. installation of two berm breaches above the ordinary high water mark, and installation of coir fiber matting at berm
breaches.
S2 permanent impacts of 33 LF (resulting in 71 square feet or 0.002 acre) are for installation of wing walls and rip-rap at new
precast concrete box culvert. The box culvert will replace existing pipes.
S2 temporary impacts of 36 LF (resulting in 291 square feet or 0.007 acre) are from use of check dams for dewatering and
construction of culvert components.
4. Open Water Impacts
If there are proposed impacts to lakes, ponds. estuaries. tributaries, sounds.. the Atlantic Ocean, or any other open water of
the U.S. then individually list all open water impacts below.
4a. 4b. 4c. 4d. 4e.
Open water Name of waterbody
impact number - (if applicable) Type of impact Waterbody type Area of impact (acres)
Permanent (P)
or Temporary
T
01 ® P ? T nia Fill Man-Made 0.003 acre
(concrete pipes and headwall) Stormwater Pond (127 sq.feet)
02 ?P?T
03 ?P?T
04 ?P?T
4f. Total open slater impacts
4g. Comments:
01 impacts are shown as Site 3 on permit drawing Sheet 10 of 12.
01 permanent impacts of 0.003 acre (127 square feet) are for installation of dual storm water {wipes with a head wall situated
below the water surface.
01 temporary impacts of 0.024 acre (1,047 square feet) are from use of sand bags and dewatering during construction.
5. Pond or Lake Construction
If and or lake construction proposed. then complete the chart below.
5a. 5b. 5c. 5d. 5e.
Wetland Impacts (acres) Stream Impacts (feet) Upland
Pond ID Proposed use or purpose of (acres)
number pond
Flooded
Filled
Excavated
Flooded
Filled
Excavated
Flooded
P1
P2
5f. Total
5g. Comments:
5h. Is a dam high hazard permit required?
? Yes ? No If yes, permit ID no:
5i. Expected pond surface area (acres):
5j. Size of pond watershed (acres):
5k. Method of construction:
Page 7 of 12
PCN Form - Version 1.3 December 10, 2008 Version
6. Buffer Impacts (for DWQ)
If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts
below. If an impacts require mitigation, then you MUST fill out Section D of this form.
6a. ? Neuse ? Tar-Pamlico ® Other: Jordan
Project is in which protected basin? Reservoir Watershed
? Catawba ? Randleman
6b, 6c. 6d. 6e. 6f. 6g.
Buffer impact
number - Reason Buffer Zone 1 impact Zone 2 impact
Permanent (P) for impact Stream name mitigation (square feet) (square feet)
or Temporary required?
T
Protection
of
Existing ? Yes
B1 ? P E T Structures UT to Little Creek ® No 11,680 1,039
and
Stream
Banks
B2 []P?T ?Yes
? No
B3 ?P?T ?Yes
? No
6h. Total buffer impacts 11,680 1,039
6i. Comments: Per 15A NCAC 028.0267(9), riparian buffer impacts are allowable. Buffer impacts are for construction of rip-
rap energy dissipater pad and rock cross vane at Burning Tree Drive pipe and are temporary because disturbed areas will be
replanted as shown on Permit Drawing Sheets 11 and 12.
D. Impact Justification and Mitigation
1. Avoidance and Minimization
la. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project.
Avoidance measures include retaining the existing Burning Tree Drive 42-inch diameter concrete pipe, retaining existing
channel geomorphology instead of creating a new channel, and not placing existing channel into stormwater pipes.
Minimization measures include breaching the low berm at the top of bank above the ordinary high water mark and installing
drainway in areas where vegetation will not need to be removed.
1b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques.
Where possible.. work will be completed using hand tools. This will avoid damage to the mature vegetation along the stream
banks and will limit the number of trees that must be removed for construction.
2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a. Does the project require Compensatory Mitigation for ? Yes ® No
impacts to Waters of the U.S. or Waters of the State?
2b. If 7es. mitigation is required by (check all that apply): ? DWO ? Corps
? Mitigation bank
2c. If yes. which mitigation option will be used for this project? ? Payment to in-lieu fee program
? Permittee Responsible Mitigation
Page S of 12
PCN Form - Version 1.3 December 10, 2008 Version
3. Complete if Using a Mitigation Bank
3a. Name of Mitigation Bank:
3b. Credits Purchased (attach receipt and letter) Type Quantity
3c. Comments:
4. Complete if Making a Payment to In-lieu Fee Program
4a. Approval letter from in-lieu fee program is attached. ? Yes
4b. Stream mitigation requested: linear feet
4c. If using stream mitigation, stream temperature: ? warm ? cool ?cold
4d. Buffer mitigation requested (DWQ only): square feet
4e. Riparian wetland mitigation requested: acres
4f. Non-riparian wetland mitigation requested: acres
4g. Coastal (tidal) wetland mitigation requested: I acres
4h. Comments:
5. Complete if Using a Permittee Responsible Mitigation Plan
5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan.
6. Buffer Mitigation (State Regulated Riparian Buffer Rules) - required by DWQ
6a. Will the project result in an impact within a protected riparian buffer that requires
buffer mitigation? ® Yes ? No
6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the
amount of mitigation required.
Zone 6c.
Reason for impact 6d.
Total impact
(square feet)
Multiplier 6e.
Required mitigation
(square feet)
Zone 1 3 (2 for Catawba)
Zone 2 1.5
6f. Total buffer mitigation required:
6g. If buffer mitigation is required. discuss what type of mitigation is proposed (e.g., payment to private mitigation bank.
permittee responsible riparian buffer restoration, payment into an approved in-lieu fee fund).
Buffer mitigation is not required.
6h. Comments: Per 15A NCAC 028.0267(9), buffer impacts are allowable without mitigation. Buffer impacts are temporary
because disturbed areas well be replanted.
Page 9 of 12
PCN Form - Version 1.3 December 10, 2008 Version
E. Stormwater Management and Diffuse Flow Plan (required by DWQ)
1. Diffuse Fiow Plan
1a. Does the project include or is it adjacent to protected riparian buffers identified ® Yes ? No
within one of the NC Riparian Buffer Protection Rules?
1 b. If yes, then is a diffuse flow plan included? If no, explain why.
Comments: No stormwater management plan is required because the project is ? Yes ® No
for maintenance of existing stormwater systems and does not create any
impervious surface.
2. Stormwater Management Plan
2a. What' is the overall percent imperviousness of this project? %
2b. Does this project require a Stormwater Management Plan? ? Yes ® No
2c. If this project DOES NOT require a Stormwater Management Plan, explain why: Work is part of a storm water
improvement project that will address flooding in residential yards. The project does not change existing impervious
surface area and is a low density project. It was confirmed that a SMP is not required during a preapplication meeting with
DWQ staff on August 6, 2009 and Express Review staff on August 26, 2009.
2d. If this project DOES require a Stormwater Management Plan. then provide a brief, narrative description of the plan:
? Certified Local Government
2e. Who will be responsible for the review of the Stormwater Management Plan? ? DWQ Stormwater Program
? DWO 401 Unit
3. Certified Local Government Stormwater Review
3a. In which local government's jurisdiction is this project? Town of Chapel Hill
? Phase II
? NSW
3b. Which of the following locally-implemented stormwater management programs ? USMP
apply (check all that apply): ? Water Supply Watershed
? Other:
3c. Has the approved Stormwater Management Plan with proof of approval been ? Yes ? No
attached?
4. DWQ Stormwater Program Review
? Coastal counties
? HOW
4a. Which of the following state-implemented stormwater management programs apply ? ORW
(check all that apply): ? Sesslon Law 2006-246
? Other:
4b. Has the approved Stormwater Management Plan with proof of approval been
? Yes ? No
attached?
5. DWQ 401 Unit Stormwater Review
5a. Does the Stormwater Management Plan meet the appropriate requirements? ? Yes ? No
Page 1.0 of 12
PCN Form - Version 1.3 December 10, 2008 Version
5b. Have all of the 401 Unit submittal requirements been met? ? Yes ? No
F. Supplementary Information
t. Environmental Documentation (DWQ Requirement)
1a. Does the project involve an expenditure of public (federal/state/local) funds or the E Yes ? No
use of public (federal/state) land?
1 b. If you answered "yes" to the above.. does the project require preparation of an
environmental document pursuant to the requirements of the National or State ? Yes ® No
(North Carolina) Environmental Policy Act (NEPAiSEPA)?
1 c. If you answered "yes" to the above, has the document review been finalized by the
State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval
? Yes ? No
letter.)
Comments:
2. Violations (DWQ Requirement)
2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500). Isolated
Wetland Rules (15A NCAC 2H .1300). DWQ Surface Water or Wetland Standards, ? Yes ® No
or Riparian Buffer Rules (15A NCAC 2B .0200)?
2b. Is this an after-the-fact permit application? ? Yes ® No
2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s);
3. Cumulative Impacts (DWQ Requirement)
3a. Will this project (based on past and reasonably anticipated future impacts) result in ? Yes ® No
additional development, which could impact nearby downstream water quality?
3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the
most recent DWQ policy. If you answered "no," provide a short narrative description.
4. Sewage Disposal (DWQ Requirement)
4a, Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from
the proposed project, or available capacity of the subject facility.
The project does not include sewage disposal.
Page 11 of 12
PCN Form - Version 1.3 December 10, 2008 Version
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this project occur in or near an area with federally protected species or ? Yes 0 No
habitat?
5b. Have you checked with the USFWS concerning Endangered Species Act ? Yes ® No
impacts?
E:1 Raleigh
5c. If yes, indicate the USFWS Field Office you have contacted. ? Asheville
5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical
Habitat?
NC Natural Heritage Program Virtual Workroom maps, GIS shapefile data layers, and field investigation conducted by a
qualified biologist to determine presence of protected species or their habitats.
6. Essential Fish Habitat (Corps Requirement)
6a. Will this project occur in or near an area designated as essential fish habitat? ? Yes O No
6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat?
Project is located in Piedmont physigraphic region
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
7a. Will this project occur in or near an area that the state, federal or tribal
governments have designated as having historic or cultural preservation ? Yes No
status (e.g., National Historic Trust designation or properties significant in
North Carolina history and archaeology)?
7b. What data sources did you use to determine whether your site would impact historic or archeological resources?
Project is located within established subdivision and country club golf course and excavation will not impact any
previously undisturbed areas.
B. Flood Zone Designation (Corps Requirement)
Sa. Will this project occur in a FEMA-designated 100-year floodplain? 9 Yes ? No
8b. If yes, explain how project meets FEMA requirements: The project will not create an impact to the FEMA floodplain
because there will be no fill or excavation to change the floodplain.
8c. What source(s) did you use to make the floodplain determination? North Carolina Floodplain Mapping Information System
(GIS based website available through FEMA) and hydraulic engineering design.
Applicant/Agent's Printed Name Ap icant/Agent's Signature Date
(Agent's signature is valid only if an aulhorization letter from the applicant
is provided.)
Page 12 of 12
PCN Form - Version 1.3 December 10, 2008 Version
Table 1. Section 404/401 Impact Area Property Owners
PIN OWNER ADDRESS DEED BOOK/PAGE DATE RECORDED
9798471629 Chapel Hill P.O. Box 2165 3391/96 4/5/2004
Country Club Chapel Hill, NC
27514
9798689751 Chapel Hill P.O. Box 2165 2263/447 5/16/2001
Country Club Chapel Hill, NC
27514
9798680227 Sterling H. Kenan 1011 Pinehurst 02-E-414 9/2/2002
Drive
Chapel Hill, NC
27517-5656
9798588479 Frances Miriam 1010 Pinehurst 1635/297 9/24/1997
Kovens Drive
Chapel Hill, NC
27514-5654
9798586570 Walter Ray & 1014 Burning Tree 838/399 2/19/1990
Mary L. Parmer Drive
Chapel Hill, NC
27515-5606
North Carolina Division of Water Quality -Stream Identification Form; Version 3.1
I Date: Aug. 22, 2007 Project: Burning Tree Drive Latitude: 35°54'58.251"N
Evaluator: Cindy Carr, Mulkey I Site: Stream S1, Reach 1
Longitude: 79°0' 60.488"W
Total Points:
Stream is at least intermittent F I 25 County: Orange Other: Chapel Hill
If >19 or perennial if >30
A. Geomor holo (Subtotal = 14.5 ) A bsent Weak Moderate Strong
1a. Continuous bed and bank ? 0 ? 1 ? 2 0 3
2. Sinuosity ? 0 ® 1 ? 2 ? 3
3. In-Channel structure: riffle-pool sequence N o ? 1 ? 2 ? 3
4. Soil texture or stream substrate sorting N o ? 1 ? 2 ? 3
5. Active/relic flood lain ? 0 ? 1 ? 2 ® 3
6. Depositional bars or benches N o ? 1 ? 2 ? 3
7. Braided channel N o ? 1 ? 2 ? 3
8. Recent alluvial deposits ? 0 ? 1 ® 2 ? 3
9a. Natural levees N o ? 1 ? 2 ? 3
10. Headcuts ? 0 ? 1 ® 2 ? 3
11. Grade controls N o ? 0.5 ? 1 ? 1.5
12. Natural valley or draina ewa ? 0 ® 0.5 ? 1 ? 1.5
13. Second or greater order channel on existing
USGS or NRCS map or other documented
evidence.
?No = 0
®Yes = 3
" Man-made ditches are not rated; see discussions in manual.
B Hydrology (Subtotal = 6 ) Absent Weak Moderate Strong
14. Groundwater flow/discharge ?0 ?1 ®2 ?3
15. Water in channel and > 48 hrs. since rain, or
Water in channel - dry or growing season ?0 Ni ?2 ?3
16. Leaflitter ?1.5 ®1 ?m ?0
17. Sediment on plants or debris No ?m ?1 ?1.5
18. Organic debris lines or piles (Wrack lines) ?0 ®0.5 ?1 ?1.5
19. Hydric soils (redoximorphic features) present? ?No = 0 ®Yes = 1.5
C. Biology (Subtotal = 4.5 ) A bsent Weak Moderate Strong
20". Fibrous roots in channel ? 3 ? 2 ? 1 N o
21 . Rooted plants in channel ® 3 ? 2 ? 1 ? 0
22. Crayfish ? 0 ? m ® 1 ? 1.5
23. Bivalves N o ? 1 ? 2 ? 3
24. Fish ® 0 ? 0.5 ? 1 ? 1.5
25. Amphibians ? 0 ® 0.5 ? 1 ? 1.5
26. Macrobenthos (note diversity and abundance) N o ? m ? 1 ? 1.5
27. Filamentous algae; periphyton N o ? 1 ? 2 ? 3
28. Iron Oxidizing bacteria/fungus N o ? m ? 1 ? 1.5
29". Wetland plants in streambed ?FAC=0.5; ?FACW=0.75; ?OBL=1.5;
?SAV=2.0; ?Other=0
".Items 20 and 21 Locus on the presence of upland plants, Item 29 tocuses on the presence of aquatic or wetland
plants.
Notes: (Use back side of this form for additional notes.) Sketch:
• Stream appears to have been channelized at time of residential and golf course construction.
• Several culverts on stream.
• Several small drainage pipes from yards or homes have outfalls to creek.
North Carolina Division of Water Quality -Stream Identification Form; Version 3.1
I Date: Aug. 22, 2007 Project: Burning Tree Drive Latitude: 35°54'58.251"N
Evaluator: Cindy Carr, Mulkey I Site: Stream S1, Reach 2
Longitude: 79°0' 60.488"W
Total Points:
Stream is at least intermittent F I 31 County: Orange Other: Chapel Hill
If >19 or perennial if >30
A. Geomor holo (Subtotal = 19.5 ) A bsent Weak Moderate Strong
1a. Continuous bed and bank ? 0 ? 1 ? 2 0 3
2. Sinuosity ? 0 ® 1 ? 2 ? 3
3. In-Channel structure: riffle-pool sequence ? 0 N i ? 2 ? 3
4. Soil texture or stream substrate sorting ? 0 ? 1 ? 2 ® 3
5. Active/relic flood lain ? 0 ? 1 ® 2 ? 3
6. Depositional bars or benches ? 0 ? 1 ? 2 ® 3
7. Braided channel N o ? 1 ? 2 ? 3
8. Recent alluvial deposits ? 0 ? 1 ® 2 ? 3
9a. Natural levees N o ? 1 ? 2 ? 3
10. Headcuts ? 0 ® 1 ? 2 ? 3
11. Grade controls N o ? 0.5 ? 1 ? 1.5
12. Natural valley or draina ewa ? 0 ® 0.5 ? 1 ? 1.5
13. Second or greater order channel on existing
USGS or NRCS map or other documented
evidence.
?No = 0
®Yes = 3
" Man-made ditches are not rated; see discussions in manual.
B Hydrology (Subtotal = 7 ) Absent Weak Moderate Strong
14. Groundwater flow/discharge ?0 ?1 ?2 03
15. Water in channel and > 48 hrs. since rain, or
Water in channel - dry or growing season ?0 ?1 ?2 ®3
16. Leaflitter ?1.5 ?1 ®0.5 ?0
17. Sediment on plants or debris No ?m ?1 ?1.5
18. Organic debris lines or piles (Wrack lines) ?0 ®0.5 ?1 ?1.5
19. Hydric soils (redoximorphic features) present? ®No = 0 ?Yes = 1.5
C. Biology (Subtotal = 4.5 ) A bsent Weak Moderate Strong
20". Fibrous roots in channel ? 3 ? 2 N i ? 0
21". Rooted plants in channel 0 3 ? 2 ? 1 ? 0
22. Crayfish N o ? m ? 1 ? 1.5
23. Bivalves N o ? 1 ? 2 ? 3
24. Fish N o ? 0.5 ? 1 ? 1.5
25. Amphibians ? 0 ® 0.5 ? 1 ? 1.5
26. Macrobenthos (note diversity and abundance) N o ? m ? 1 ? 1.5
27. Filamentous algae; periphyton N o ? 1 ? 2 ? 3
28. Iron Oxidizing bacteria/fungus N o ? m ? 1 ? 1.5
29". Wetland plants in streambed ?FAC=0.5; ?FACW=0.75; ?OBL=1.5;
?SAV=2.0; ?Other=0
".Items 20 and 21 Locus on the presence of upland plants, Item 29 tocuses on the presence of aquatic or wetland
plants.
Notes: (Use back side of this form for additional notes.) Sketch:
• Stream appears to have been channelized at time of residential and golf course construction.
• Several culverts on stream.
• Several small drainage pipes from yards or homes have outfalls to creek.
North Carolina Division of Water Quality -Stream Identification Form; Version 3.1
I Date: Aug. 22, 2007 Project: Burning Tree Drive Latitude: 35°54'58.251"N
Evaluator: Cindy Carr, Mulkey
Site: Stream S3
Longitude: 79°0' 60.488"W
Total Points:
Stream is at least intermittent F I 9.5 County: Orange Other: Chapel Hill
If >19 or perennial if >30
A. Geomor holo (Subtotal = 5.5 ) A bsent Weak Moderate Strong
1a. Continuous bed and bank ? 0 0 1 ? 2 ? 3
2. Sinuosity ? 0 N i ? 2 ? 3
3. In-Channel structure: riffle-pool sequence N o ? 1 ? 2 ? 3
4. Soil texture or stream substrate sorting N o ? 1 ? 2 ? 3
5. Active/relic flood lain ? 0 ? 1 ? 2 ® 3
6. Depositional bars or benches N o ? 1 ? 2 ? 3
7. Braided channel N o ? 1 ? 2 ? 3
8. Recent alluvial deposits N o ? 1 ? 2 ? 3
9a. Natural levees N o ? 1 ? 2 ? 3
10. Headcuts N o ? 1 ? 2 ? 3
11. Grade controls N o ? 0.5 ? 1 ? 1.5
12. Natural valley or draina ewa ? 0 ® 0.5 ? 1 ? 1.5
13. Second or greater order channel on existing
USGS or NRCS map or other documented
evidence.
®No = 0
?Yes = 3
" Man-made ditches are not rated; see discussions in manual.
B Hydrology (Subtotal = 0.5 ) Absent Weak Moderate Strong
14. Groundwater flow/discharge No ?1 ?2 ?3
15. Water in channel and > 48 hrs. since rain, or
Water in channel - dry or growing season No ?1 ?2 ?3
16. Leaflitter ?1.5 ?1 ?m ®0
17. Sediment on plants or debris No ?m ?1 ?1.5
18. Organic debris lines or piles (Wrack lines) ?0 ®0.5 ?1 ?1.5
19. Hydric soils (redoximorphic features) present? ®No = 0 ?Yes = 1.5
C. Biology (Subtotal = 3.5 ) A bsent Weak Moderate Strong
20". Fibrous roots in channel ? 3 ? 2 N i ? 0
21". Rooted plants in channel ? 3 ® 2 ? 1 ? 0
22. Crayfish N o ? m ? 1 ? 1.5
23. Bivalves N o ? 1 ? 2 ? 3
24. Fish N o ? 0.5 ? 1 ? 1.5
25. Amphibians N o ? m ? 1 ? 1.5
26. Macrobenthos (note diversity and abundance) N o ? m ? 1 ? 1.5
27. Filamentous algae; periphyton N o ? 1 ? 2 ? 3
28. Iron Oxidizing bacteria/fungus N o ? m ? 1 ? 1.5
29". Wetland plants in streambed ®FAC=0.5; ?FACW=0.75; ?OBL=1.5;
?SAV=2.0; ?Other=0
".Items 20 and 21 Locus on the presence of upland plants, Item 29 tocuses on the presence of aquatic or wetland
plants.
Notes: (Use back side of this form for additional notes.) Sketch:
0 Appears to have been channelized, drains in Wetland WA near WA5 point.
15
Radon dnwars l
C Lln f/' `374} • ^+w +
: 1t i 7 ` r \ J i l
,?
?-
'
` •? -
'? ? ?
r
.
? ?,
. , -tom -
„r ? ? c`? ` l
'J
\?
4444 - •.. ?? r ? T n? *w ja ? ? . ?Sch? ?, ? ? + ??? ? l I'
} !
r-i
r _
• •?
«
?? .T
B areliff ?
Gorr
Ir I ) .?
.
./ , ? ?
' ?
`- I Course rf ??
I n y : l I ? ° f r Y 1. 1 r
.
f + ) 'k. yam.
Fnloner ?? S - \ )'
? t - 1 I.? ??C'f :z .,
+ f
V N I
L HIV
Project Area
.-.,! ? - 4 -. - \
. ?: ?
S}7 Y ClF','1Y
RTVAfWLJNA ' IR ~? 4 a?.l ? I YI I fI ? :? ?,? J 1+? ?y V. tl / . ? ?? e•.
It II .? + u y ?. ?U •.Tl?
pl
.` rr ??a r - : ?y i Lk'i P.? 4`M1 t. ?
-'
"
?i
w
„ n i r s r _ ??,?? `
Couro j + r - cq
? 2av ? , f 1 ??
\
8# Ther»y
Hnre.a
M r + 9rhti Sch ? \_ fi r
/+ ?q•4 l; _?F
'
f
r `?a1 r,,
ti
` .
+ ? ? Mir', .
? •;
k L . ?
f `I? ?.. +u
• Golf tS
Course r ?• f ti
! J F 1yJ ?r
f ?t1 Lb?' !i .;, ?. l 1906 -- i `? ? ? ? ^ t ) C ?. = hs .
_ 1 5,ew ,?, ?• ? I. ?
• 1
i 1 ? t a• II l.?l ?. i
-
D
Y
J 1
r } t
Legend
mo,
Proposed Impacts
• PROJECT LOCATION
Town of Chapel Hill Figure
Burning Tree Drive Drainage Improvements
Orange County, North Carolin a
M U L K E Y 0 0.25 0.5 1 Miles
1:24,000
USGS 7.5-Minute Quadrangle: Chapel Hill (1978; photorevised 1981)
Contour Interval: 10 Feet. Adjacent Map: SW Durham
w
W
W
. ,.
:
AT
C K? 3 Ali.
9 J
?1 I10? YtIb'H$IlQ
U ?i
Q N .
z. m LL
+
N r Qlei• y N N
J +NU+ m
w D
2?
?
Q
c z
1 3 CJ
"
U
=LL1
..CJv - m S ?. ?? cV
ui Q1,
u'l
O r_
N
rn U
U
u .F.
Ok
S'
3
o
/ WtC2 ?
F-
r.
. ?
.
m
sB \ m a ?'
d U
L)
3 \
w Ydt?2 Q v m 3 >
O = Z
U y
eo)j
Boo O
0$
tt U e
+
w+
C
4 bG is p
U) O a °
°
3; t
L) o
L J L,
3-
y jY uj N ?
10
,
_
"`
U
?
'? d ? i .
c
ice r ,
;; ?
`,o• J *
- ? t E :
O
?.
W
h N
I' ? m
y??.•
.
?
r
E
r
4r
LJ?
A
?
t
?`
,• k
t
,ry"a +q!'sn j'i ? t'1+-; ?I ,,,.'" •,r a
O a. .. ti * t .? l t 1
G. '? ??' `. t
' 1j £ ?.? ?? •? ? ???
'? ?'
nom'
*
.
d
Z: '7
'
•
Q ? t y/'
i2 45`!1 ? ?'t' ? ?.,.,,, ? ? y11..
' L
? -¢ r
i ? T
W F
-
V
3
?
I ?
( y y
a
?a
1 *4
1 > 41
". ? .T ? ?; s 'r- ? ./' `I •=ra
x. b :.P J?? 1x - ?7f.7- £ ?g.K?5t y •. t ?,1-',y.?'
. j. ?. 'T•
'`?• iR s >g'
d?'+
?li? ? ??'?a?
? ?,x'Mr`?ra - ?
' 3'
?
?
?fr
W
4
?d
v,
y t r,;r j ,
1?
r f ` rs ', lr?y l,e ! F '-, ?_i w 1y ^y'D r^° ?tX //
" .+?r ?,.r w r ? .' TY,7r??+-•?'? ?? •'W
r ?F Y•
?F
`
, ,
!CXs1
?'
s T+ it + W " `
,. ?.??k - ?.?p '??, a•y? •y^a,s A )?!??,,yy4_:? 1. ,?ti :- ?Ay,, ,re 7„? tw ? ?,??'- •? ? ¢ e? !?/?M
?'J?r?r'?',?'"'f'J"'7T •1? 'a? ,. w?ly.,n' y ,y??j.., ).
77?? /G T
(/
?
Y
1.. i
r
4 / .?
J _
?t
,
'
?
i
?
y
?
? ?'
"
' ?
"
"
'!? g•
f c
Y.
,?
a?j
ei
1
? f •-w?l
,i.
,?/
^
-r _ e
40
?,, ^ ? •?.: ?? ? f~. ?N y.' '+v•? •r' .a sssss
1-, `?? 3 :• .q. `y! ' ' 'r ? 1'"
fir` ?t?'+ .• ?
y y
d* 5.
.r •A • `r '..?Y, - .* ?'M' . ?J yr• ?,F;.,;a¢,??. ?y
Alf
66
`
IV
4
-
0
Legend
4a ?+r a a d `?' O Proposed Impact Areas
r;''? USACE Jurisdictional Determinations
' ?
rti ° •,.t r l ?p,? ,? Y??
' 'fi
w?
'
Perennial
Im
ortant (404)
'
Y
, ` ,`
? t?
,
p
/ #ti_P? ? f
r, w?
>,
Ay Perennial
Unimportant 404
??
,
, IF
" P _ Intermittent Unimportant (404)
-
?
,
Stormwater Ponds
• PROJECT VICINITY DELINEATIONS Figure
Burning Tree Drive Project
Chapel Hill Country Club
Orange County, North Carolina
3
MULKEY 0 125 250 500 Feet 1:3,000
Delineation Surveys Completed August 22, 2007
M U L K E Y PHOTOGRAPHIC LOG
Client Name: Project Name: Project No.
Town of Chapel Hill Burning Tree Drive Stormwater Improvements 2007038.00
Photo No. Date:
-
16
'
1 9/15/07
F
Direction Photo -
Taken: $ , Mme' '
s
_t ..
Southwest
t
-%-? yp
..? a 'v _ yY9 19 a? „? ri.aal+' k iLy. t *',,v, 1
%
R?'?
r_
(upstream)
r#
_jk
Description:
Burning Tree Drive, 42-
inch diameter concrete
pipe outlet on UT to
Little Creek. Water flows .-: ; . T
northward toward
confluence with Little ;
Creek.
Note high bank with 41
erosion from scour.
Proposed impacts are moot
for new rip-rap
dissipater pad and rock
cross vane. ` .°
Photo No. Date:
2 9/14/07
Direction Photo
Taken:
Southwest
(upstream)
Description:
Burning Tree Drive pipe
outlet with normal
rainfall storm water
flow.
y°
M U L K E Y PHOTOGRAPHIC LOG
Client Name: Project Name: Project No.
Town of Chapel Hill Burning Tree Drive Stormwater Improvements 2007038.00
Photo No. Date:
3 5/28/0 .?? - ; `,- .?
Direction Photo
Taken:
Southwest
(upstream)
Description:
UT to Little Creek
approx. 50 feet.
downstream from <a, fi.?
Burning Tree Drive pipe • m?; + r , `
shown in Photos 1 and
.06
b3?N yam'
2.
Note sediment bar.,. # F
deposition.
Photo No. Date:
4 2/21/07
Direction Photo
Taken:
South
(upstream)
Description:
UT to Little Creek,
approx. 100 feet
downstream from
Burning Tree Drive
pipe.
Note low berm along
top of stream banks.
Elevation of residential
yards adjacent to stream
are below the berm and
storm water is
impounded onto yards.
s ,
?F
d CC?LL
M U L K E Y PHOTOGRAPHIC LOG
Client Name: Project Name: Project No.
Town of Chapel Hill Burning Tree Drive Stormwater Improvements 2007038.00
Photo No. Date: =
5 9/14/07 Nz
;
Direction Photo
?
Taken: n ?' _ # Aq?'d`' a
South
(upstream)
;
k
, .
rc u' - ilk,
Description:
z;
,
UT to Little Creek, i
J
i
,
looking upstream from
:
if
gocart path at channel
i
f
- x r
-: ?? . - ?•:
carry
ng waters
rom normal rainfall.
s
P>!? i d
Existing dual 24-inch
diameter plastic pipes • ' ,},
-"'
create backwater scour _
1;?
,, .F y 5 _
•, fr ?
'4..jT_' .
„
?
and flooding onto , ??
y
`y x
adjacent residential
yards. - _
Photo No. Date:
6 5/28
Direction Photo
Taken:
Southeast
(upstream)
Description:
Inlets of existing dual
24-inch diameter plastic
pipes are visible at edge
of golf cart path.
Proposed impacts
include replacing these
pipes with a 6-foot by 3-
foot preformed concrete
box culvert and placing
rip-rap in the channel at
the inlet and outlet.
„? 9+" +4 s y, w f ty,
-AW
y?.
I
MULKEY
Client Name:
Town of Chapel Hill
Photo No. Date:
7 5/28/09
Direction Photo
Taken:
South
(upstream)
PHOTOGRAPHIC LOG
Project Name: Project No.
Burning Tree Drive Stormwater Improvements 2007038.00
Photo No. Date:
8 5/28/09
Direction Photo
Taken:
Northeast
(upstream)
Description:
From outlet end plastic
pipes under golf cart
path, stream flows
northward into beaver
dam wetland and
eventually to confluence
with Little Creek.
arc
p,
M PHOTOGRAPHIC LOG
Client Name:
Town of Chapel Hill
Photo No. Date:
9 9/14/07
Direction Photo
Taken:
Southwest
Project Name:
Burning Tree Drive Stormwater Improvements
Awl
Description:
Man-made storm water
retention pond adjacent - -?__
to Pinehurst Drive and -
used by Chapel Hill CC
to irrigate golf course
turf.
Proposed impacts include
installation of new dual M
36-inch diameter concrete
pipes to outlet storm
water from new
collection system along
Pinehurst Drive
Photo No.
KEY Date:
Direction Photo $;- 5 & 6 %- j
Taken: , ?a %,I 9
Plan View of Project s & a
Area ..
1 & 2 .
Description:
Numbers in yellow boxes
?°
ti
correspond to Photo No.
of
hoto
ra
hs 1 to 11 *
x <r?, yf a ?'' j
p
.
g
p
x? w
Yellow arrow mdicateS / / • rj y k "4 r? ""r
4.
general direction of photo d ! ?' •? ,? ? '§%
view and location photo
was taken from.
Areas enclosed by red
?
rectangle are locations of
proposed impacts
t<<
requiring Section
404/401 permits.
Project No.
2007038.00
WETLAND/STREAM PERMIT IMPACT SUMMARY
WETLAND IMPACTS SURFACE WATER IMPACTS
Site
No.
Station
(From/To)
Structure
Size / Type
Fill In
Wetlands
(ac) Temp.
Fill in
Wetlands
(ac)
Excavation
In Wetlands
(ac) Mechanized
Clearing
(Method III)
(ac) Permanent
SW
Impacts
(ac) Temporary
SW
Impacts
(ac) Permanent
Channel
Impacts
(LF) Temporary
Channel
Impacts
(LF) Permanent
Pond
Impacts
(ac) Temporary
Pond
Impacts
(ac)
1 rip-rap energy dissipator 0.00 0.00 0.00 0.00 0.01 0.02 50 100
and rock cross vane
see Sheet 11 of 12
2 6 x 3 RCBC, wing walls, and 0.00 0.00 0.00 0.00 <0.01 0.01 33 36
rip-rap
see Sheet 11 of 12
3 20+00 -L- RT dual 36-inch diameter 0.00 0.00 0.00 0.00 <0.01 0.02
concrete pipes, headwall
see Sheet 10 of 12
TOTALS: 0.00 0.00 0.00 0.00 0.02 0.03 83.00 136.00 <0.01 0.02
'3'd q -Pr ;'aaul u3 PG Old 60OZ Al(1r bZ 7d'N3SN3( Sll 133NIEM 103(Oad
((d
' iDNO1d EEZZ-696(616)
""Z 7N 911H 13dVH? O
.?
, Y W 0'ONIA3JI1f1W'MMM
0 31Y0 :A9
NMO S1N3W3AObdWl 3J`dNl`dad 4A19'Nf'ONq a3Hj NLLaWV S06
)`
/l
?y;?y3Nl9,v .?y •."
J '
P? y''•.d =
1
'l (x
B lfi L-LSB l6)
l-L 5 B(fi (61 6)
6l ('j(
b11'
3AR14 33111 JNINilf18 jN3W1atld30 JNIa33N19
111H 13dtMJ JO
NMOl
`•V
Z =
•
cY
? 9E9LZ 'a'N
:A9 OAHJ
?A9'S34
.
- a;ln z: GZ L EE XOG oe Od
Od
(?
SJNIMb'da %C
•
' 61
NV11nBN
cio v BM33NIE N3 (7d011k13N 37Ij0lld J7 0
'?
' d
'?
'rd `
1
.
; O,y
...... / \ / ¦ OOI OS 0 OS
nvlvozlaoNl 37l?oadi6ro7d l 0 O
o, 2139Wf1N 1J3f021d w ti
SNOISIA3N d :A9 43NVd3Nd SNNId 06 OZ 0 03
and a3add3aa
_
o a
Q a °en.
J// D
pez
o <Z
z
Da / Gu g
I , OW od
a All/ ? zM ??? po ao
g
OF
lI 2 1 111 I?
OI? l /
?Il
/
N
O I I
I l ?? I? Is R
_ -- 2-36
I I I
R
P ?
I
I
C
?
L I
I
L /
I I
VIII ?° III ? \ I I ? o 1
W i
I
\
I
I CI I ? ? ?.
\ ?
I
I
I
I I
I
I
III
I ?w
03
°
III
L I
I
I
k ?
o?
C
?c?a omQ u
mmm?Q? I
J I
II I
III
.0 °2 o?
oe'?N
v w
w w J ¢
II
I I F
? a F
I Y' rZO? J 'Z" ?U 1 I
W
I II V e? m v r O `a`
?m On,
II I
III ?
I ? ?? f3 FZ
O I
II ?N -W-
I
I 0Q Um mW Vf?
WU W I
I
I
?
O
I
I ? =N FQ? HV
z?z Za I
II
I Wo-
NSN
?
LQ
}?
a
?
m
- I N
BiiW
?' 2g/
I I
I
? t
p
IIII I
II 9
f p•! p 3
~ r 1 I II
s
(n j IIII I i
I
I II
I ?I I
I Gg
? GW
? i
ti
? I
III
I
I
I
I I
I ?
ZO ?
ZO ?
I i
I I ?
I I I I ?? ?? ? i
I
I I I '
I
II
I
I I I I
II
o Q o I I
I
I
>?
?
I I
II I
O
?N6tl?0
1 i
I I
w?w I I I I I '?
II
I
I
I
/ r?N?"14?ct
??v
cvzz mrn(n ?
I I
i
I
I I .,,
I
t5
I
II 1n II II II II II
i
I I I {, ?
I ?<C J I
III 1 ?I ?? ? I
I I 30.00- <
I c7 ?
??
h
;
I?
o
R I
'
I 1
I z _
J
w ???wz
??? I I 1 I?1
1
I I Ol7p
?
z Z Ln DO
II II
cn II II I
?
w
' 1
??
II z
9
9 zrn
Yo Ow
?? II
6:
H
?
?
? ?
? I
? ?
?? ??
?? ??
?
?
H
z n
o II
1 1
e>4 x e<
p3 <Q
QO I?x
u
o-
I I I
a N Z-
1\ I
G?
fd
o
I I ?m p
f
t
i ( 91 :6 F T
Um i \ -_ I DRf/EN?Y N
R? 1 1? 1 1 1 C? C I I
j
?
O?E
\
IA
?F
? I I
I I
I /
1 I
`1 I
B" pC ID PTURI W m ? I I /
sl\ \\\4"STL_- 1.;I IxI ru zZ I
02
?
1 1 1
V 1?/ ? I II II ? I
\
\ ?\I - 1\I L J
3tPM `
i?
\U
\
1
\
1
I
; 1
}dO
1\\M
1
a
\
`
/
X11\ 1
?mm
1
?mm
W
F- I I
,11 6 1??N Q
3
m ? i m i m m ? H H I?H H? H ih
?$ z
r? W
? CL
.
p C4
N
N
N
N
N LO ? M
N N N N N
53333 33WI13 S3ivo$