HomeMy WebLinkAbout20190802 Ver 1_More Info Requested_20190717Strickland, Bev
From: Homewood, Sue
Sent: Wednesday, July 17, 2019 1:10 PM
To: Derek Goddard
Cc: Fuemmeler, Amanda J CIV (US); Leslie, Andrea J
Subject: RE: [External] Propsed Liddle Project in Ashe county- Drone footage
Derek,
I have a few items for you to address before I can issue the 401 for this project:
You indicate that the wetland impacts are temporary, however it appears that you will be constructing an 8' channel and
sloped banks through the wetland area. I believe that would be considered permanent impacts converting a portion of
the wetland to stream. Although this would not require mitigation I think it should be accurately accounted. Amanda,
please confirm or correct me.
I haven't been to the site and this might be obvious if I had, but please provide an analysis of whether you believe the
hydrology of the remaining wetland will be modified/reduced by the relocation of the stream. If the slope is such that
the lowest portion of the existing wetland would be downslope of the stream then it could be that the location of the
stream would intercept the hydrology to a portion of the wetland in the future.
In order for DWR to provide an exemption from Condition 11.9 in GC#4134 you must request to work in the wet and
provide a detailed justification with supporting documentation such as calculations or construction sequences,
explaining why it is not feasible to work in the dry. While it may be not be practical to provide full time pump around,
you must explain why it is not feasible to temporarily pump around while equipment is in the channel/structures are
being installed, and divert water back into the channel when equipment is not actively within the channel. You must also
provide an explanation of how you intend to meet downstream water quality standards, such as turbidity standards,
while working in the wet.
Thanks,
Sue Homewood
Division of Water Resources, Winston Salem Regional Office
Department of Environmental Quality
336 776 9693 office
336 813 1863 mobile
Sue. Homewood@ncdenr.gov
450 W. Hanes Mill Rd, Suite 300
Winston Salem NC 27105
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Derek Goddard <derek@brec.biz>
Sent: Tuesday, July 9, 2019 3:48 PM
To: Leslie, Andrea J <andrea.leslie@ncwildlife.org>
Cc: Homewood, Sue <sue.homewood@ncdenr.gov>; Fuemmeler, Amanda J CIV (US) <Amanda.Jones@usace.army.mil>
Subject: Re: [External] Propsed Liddle Project in Ashe county- Drone footage
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Hey Andrea,
Hopefully we can get drone footage as we go forward on most submittals. I have answered your questions below.
On Tue, Jul 9, 2019 at 1:56 PM Leslie, Andrea J <andrea.leslie@ncwildlife.org> wrote:
Hi Derek,
I'm reviewing the Liddle project now. The drone footage is helpful, thank you. A few questions for you:
1. How wide will the planted woody buffer be?
10-25 feet . It will be excluded from livestock
1.
2. Are you intending on working in the wet?
Yes, The CFS is pretty significant and I think it would do more damage to divert the flow.
1.
2. Can you protect the woody vegetation on the right bank on the downstream third of the project?
Yes, We do not plan to take any of that vegetation out, just trim it.
1
Andrea
Andrea Leslie
Mountain Habitat Conservation Coordinator
NC Wildlife Resources Commission
N
645 Fish Hatchery Rd., Building B
Marion, NC 28752
828-803-6054 (office)
828-400-4223 (cell)
www.ncwildlife.org
Get NC Wildlife Update delivered to your inbox from the N.C. Wildlife Resources Commission.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
From: Derek Goddard <derek@brec.biz>
Sent: Tuesday, June 25, 2019 5:16 PM
To: Homewood, Sue <sue.homewood@ncdenr.gov>; Fuemmeler, Amanda J CIV (US)
<Amanda.Jones@usace.army.mil>; Leslie, Andrea J <andrea.leslie@ncwildlife.org>
Subject: [External] Propsed Liddle Project in Ashe county- Drone footage
External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
report.spam@nc.gov
Fyi
Thanks
Derek
---------- Forwarded message ---------
From: Andrew C (via Google Drive) <ac1657@gmail.com>
Date: Tue, Jun 25, 2019, 2:43 PM
Subject: Video of Liddle.MP4
To: <derek@brec.biz>
ac1657@gmail.com has shared the following video:
191,
0000=01i1111C•:MOLVAI0J
Open
ac1657@gmail.com is outside your organization.
Google Drive: Have all your files within reach from any device.
Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA
Derek Goddard, PLS, GISP
BREC, P.A.
126 Executive Drive, Suite 220
Wilkesboro, NC 28697
828.265.4425
336.844.4088
828.964.9349 Cell
www.brec.biz
derek@brec.biz
Confidentiality Notice:
D
This E -Mail transmission (and/or the documents accompanying it (Attached or uploaded to the BREC, P.A. server) may
contain information belonging to the sender and/or intended recipient which is confidential, privileged and/or exempt
from disclosure under applicable law. The information is intended only for the use of the individual(s) or entity named
above. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution or the
taking of any action in reliance on the contents of this information is strictly prohibited. If you have received this E -Mail
transmission in error, please immediately notify us by return E-Mail or telephone to arrange for return of its contents
including any documents.