HomeMy WebLinkAbout20160981 Ver 1_Year 0 As-Built Review_20190709Site Information
Site Information
Date
Prepared By:*
Meeting Type:*
USACE AID:
7/9/2019
Erin Davis
Year 0 As -Built Review
NCDWR ID: 20160981
NCDWR Version 1
Weather:
Coordinates:
Attendees
Project Name:* Uale
Type of Site:* Bank Stream Site
Sponsor/Provider: * Bank Stream Site
County:* Johnston
HUC and Basin:* Neuse - 03020201
Degrees North Degrees West
RES - Jamie Mceachran, Brian, Ryan
Medric, Brad Breslow, Ben Carol, David
DWR - Katie Merritt, Mac Haupt, Erin Davis
USACE - Todd Tugwell, Kim Browning, Sam
Dailey,
Project Review Checklist
(provide additional detail in notes section on next page)
General Site Issues/Concerns
Stream Issues/Concerns
Wetland Issues/Concerns
17 Vegetation Composition or
Density
Ir Planted Stem Vigor (due to soil,
browsing)
17 Invasive/Exotic Species
Ir Beaver/Feral Hogs
(management plan)
17 Soil (manipulation, compaction,
fertility)
Ir Livestock Present/Evidence of
Livestock Access
F- Crossings or Utility Lines
F- BMPs or Alternate Approaches
,F- Fencing Issues or Fencing
Needed
Ir Ponds Within Project Area
17 Incised/Entrenched
'7 Headcuts Present/Forming
17 Stream Structures
Failing/Piping
F- Excess Sediment/Aggradation
17 CrosslSections
Missing/Indicate Problems
Ir Bank Instability/Failure
17 Bench Rills/Erosion
(constructed bench or P2 valley)
Ir Excess Sinuosity (lack of flow)
r Braided/Anabranch Channel
IF- Evidence of Excessive
Hydrology
F- Evidence of Insufficient
Hydrology
r Hydric Soil Indicators/Soil
Series
IF- Surface Roughness or Bedding
Ir Channel Relocation/Riparian
Connectivity
17 Hydroperiod Length or
Start/Stop Date
17 Inappropriate Credit Ratio
Proposed
Ir JD Needed to Confirm
Approach
17 Continuity/Fragmentation
Ir Easement Issues (existing farm,
CE, NRCS funding)
17 Easement Encroachments
(livestock, clearing)
Ir Easement Marking/Signage
17 Insufficient Project Size
Ir Adjacent Property Owner
17 T&E Species
Ir Section 106 (historic
listing/tribal issues)
17 Insufficient Stream Drainage
Area
Ir Insufficient Hydrology (if raising
channel bed)
17 Vegetation in Channel (stream
vs wetland)
17 Flow Obstructions (undersized
pipes, fords)
17 Substrate Concerns
(embeddedness, particle size)
Ir Live Stakes Absent/Failing
17 Evidence of Water Quality
Issues
Ir Inlstream Habitat Weak/Missing
17 Stream Buffer Width Inadequate
Ir Missing Gauge Data
(preconstruction or monitoring)
17 Gauge Location/Placement
Ir Gauge Maintenance
17 Drainage Ditches/Swales
Present
Ir Field Tiles/Subsurface
Drainage
17 Continued Ag Use Adjacent to
Wetland
Page 2 --
Notes and Sketches, etc
Cattle have been in the project site until recently- went through temporary
fencing; permenant fencing just installed; Planting completed by May 31;
discussion on site construction complete (what & when); MYO timeline;
coordinated with DOT on future culvert work & designed accordingly;
fencing will be added to the utility easement border for future grazing,
fence should also be added along ford;
IRT discussion- table plot density vs site density;
Credit Release/Site Closeout Information
(For rronitoring or closeout review only)
..........................................................................................................
Stream Credits
Warm Cool Cold
Requested
Approved*
Wetland Credits
Riparian Riverine Riparian Non-Riverine Non -Riparian Coastal
Requested
Approved*
*The updated credit ledger for the project, which includes this release, rrust be approved by the Roject fVlanager.
Result of Monitoring Report or Closeout
Signature *
Date 7/9/2019