HomeMy WebLinkAbout710009_Plan of Action_20181001)6-1-lt
2�41� GI7C��
7/, �
PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 71 9
Facility Name: A&G Smith Farms
Certified Operator Name;
Archie Smith -
County: Pender
Operator Number:
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon Name/ID:
Spillway(Y or N):
Level(inches):
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
1 2
N N
10 10
2. Check all applicable items
XXX Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
XXX Liquid level is within the 25 year 24 hour storm elevations for one or more structures: A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates for depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste:
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Archie Smith
Phone:
Facility Owner/Manager (print)
"� JS ith- Date: 9/25/2018
Facility Owner/Manager (signature)
r
ti
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: Lagoon#1
line m =
212.9 lb PAN
2.
Structure ID: Lagoon #2
line m =
212.9 lb PAN
3.
Structure ID:
line m =
lb PAN
4.
Structure ID:
line m =
lb PAN
5.
Structure ID:
line m =
lb PAN
6.
Structure ID.
line m =
lb PAN
n.lines 1+2+3+4+5+6= 425.8lbPAN
Ill. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR
2 PAN balance
(lb/acre)
t TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u. application window'
7058
A
Cereal Rye/OS
3.86
75.00
289.5
Sept -April
7058
B
Cereal Rye/OS
3.91
75.00
293.3
10/1-3/31
7058
C
Cereal Rye/OS
2.68
75.00
201.0
10/1-3/31
7058
D
Cereal Rye/OS
3.43
75.00
257.3
10/1-3/31
7058
E
Cereal Rye/OS
1.41
75.00
105.8
10/1-3/31
7058
F
Cereal Rye/OS
2.95
75.00
221.3
10/1-3/31
7058
G
Cereal Rye/OS
1.29
75.00
96.8
10/1-3/31
10/1-3/31
t
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 1464.8 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 425.8 lb. PAN
x. Crop's remaining PAN balance (line v from section III) = 1464.8 lb. PAN
y. Overall PAN balance (w - x) = -1039 lb. PAN
PoA (30 Day) 2/21/00
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Mr Smith contacted me on 09/17/2018 to report his lagoons were in the red. This POA was completed by Sam
Edwards Environmental Specalist with NCDA/Soil and Water on 9/25/2018. The 5 day POA was waved by
DWR because of Hurricane Floernce. It dumped an excessive amount of rain. Will pump as field conditions
allow
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): Lagoon #1
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker J 10.0 inches
b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 9.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 22500 fe
e line c/12 x lined x 7.48 gallons/ft3 126225 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 19048 ft3
h. current herd # 2600 certified herd # 2600
actual waste produced = current herd # x line g = 19048 ft3
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i +j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 1 8/8/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown, below)
0 ft3
13125 ft3
40109 gallons
1.28 Ibs/1000 gal.
212.9 Ibs. PAN
PoA (30 Day) 2/21 /00
a
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): Lagoon #2
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 10.0 inches
b. designed 25' yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 9.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 22500 ft2
e. line c/12 x line d x 7.48 gallons/ft3 126225 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
r
g. volume of waste produced according to structural design 19048 ft3
h. current herd # 2600 certified herd # 2600
actual waste produced = current herd # x line g = 19048 ft'
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x ' 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 1 8/6/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0 ft3
13125 ft3
40109 gallons
1.28 Ibs/1000 gal.
212.9 Ibs. PAN
PoA (30 Day) 2/21/00