Loading...
HomeMy WebLinkAbout310271_Plan of Action_20181001r Ico—l—�C6 31 --Z7 PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 31-271 Facility Name: CJK Farms Certified Operator Name: Don LaCoe County: Duplin Operator Number: 16377 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon Name/ID: Spillway(Y or N): Level(inches): Lagoon Lagoon Lagoon 3 Lagoon Lagoon 1 2 N N 15 16 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another -permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3_ Earliest possible date to begin land application of waste: as conditions permit I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Don LaCoe Phone: 910-293-5572 Facility Owner/ na er (print) Date: 9/16/2018 Facility Owner/Manager (signature) e II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL -FREEBOARD AND/OR 25 YRJ24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Lagoon 1 line m = 277.7 lb PAN 2 Structure ID: Lagoon 2 line m = 308.2 lb PAN 3 Structure ID- line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6 Structure ID: line m = lb PAN n.lines I+2+3+4+5+6= 585.81bPAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIFI f]S TO WHIT W aenl remtinr RC ADoi IMn n1 Ir3me- TL,1C1 �^ r.,,,.. o. tract # p. field # q. crop r. acres s remaining IRR 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (Ibs,) column r x s u application window' 2238 1 Bermuda 3.20 100.00 320.0 March - October 2238 2 Bermuda 3.90 100.00 390.0 March - October 2238 3 Bermuda 3.20 100.00 320.0 March - October 2238 4 Bermuda 2.10 100.00 210.0 March - October -I-,- — I — 1 -1 -t, � �..a Opp %,cmui I Vp0C U1 I lCxL coup appucauon Deglnnmg Cate for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 1240.0 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) = 585.8 lb. PAN PoA (30 Day) 2/21 /00 i' It x. Crop's remaining PAN balance (line v from section III) = 1240.0 lb. PAN y. Overall PAN balance (w - x) _ -654 Ib. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Waste transfer forms on this farm show water was being transferred to the biggest lagoon however it kept raining. PoA (30 Day) 2/21/00 It PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): La oon 1 2. Current liquid volume in 25 yr./24 hr storm storage & structural freeboard a. current liquid level according to marker 15.0 inches b. designed 25 yr./24 hr. storm & structural freeboard 19.5 inches c. line b - line a (inches in red zone) = 4.5 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 32015 ftz e. line c/12 x line d x 7.48 gallons/ft3 89802 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 90 days g. volume of waste produced according to structural design 32309 ft3. h. current herd # 1960 certified herd #1 1960 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 9/26/2018 m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21 /00 32309 ft° 1 ft3 18675 ft3 127120 gallons 1.28 Ibs/1000 gal. 277.7 Ibs. PAN PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE I. Structure Name/Identifier (ID): La oon 2 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker 16.0 inches b. designed 25 yr./24 hr storm & structural freeboard 19.5 inches c. line b - line a (inches in red zone) = 3.5 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 64900 ft2 e. "line c/_12 x line d x 7.48 gallons/ft3 141590 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural'design 180 days g. volume of waste produced according to structural design 87035 ft3 h. current herd # 2640 certified herd # 2640 actual waste produced = current herd # x line g = 87035 -ft3 certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 9/26/2018 m. ((lines e + k)/1000) x line I - REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21/00 I�ft3 �39375 ft3 157591 gallons 1.03 lbs/1000 gal. 308.2 lbs. PAN