Loading...
HomeMy WebLinkAbout310464_Plan of Action_20190926PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES I - Facility Number: AWS310464 County: Duplin Facility Name: Herring Pork Producers Certified Operator Name: Chad Herring I Operator Number: 989911 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoins with spillways. Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon Name/ID: 1 2 13 Spillway(Y or N): N - N 'N Level(inches): 12 12 '12 2. Check all applicable items Liquid level is within the designed strucitural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates,fro depopulation "if animals are to be moved to anothe l permitted facility, provide facility number, lagoon freeboard levels and herd population fIor the receiving facility 3. Earliest possible date to begin land applicatio ' of waste: as conditions permit I hereby certify that I have reviewed the information listed above and Included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Prentice Herring Facility Owner/Manager (print) 'Facility Owner/Manager (signature) Phone: 919-222-8157 Date: 9/26/2018 s PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 1 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker 12.0 inches b, designed 25 yr./24 hr. storm & structural freeboard 26.41 inches c. line b - line a (inches in red zone) = 14.4 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 63700 ft2 e_ line c/12 x line d x 7.48 gallons/ft3 571771 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 54719 ft3 h. current herd #F--7-46-91 certified herd # 7469 i actual waste produced = current herd # x line g = 54719 ft' certified herd # i. volume of wash water according to structural design 6 ft3 j. excess rainfall over evaporation according to design 37158 ft3 k. (lines h + i + j) x 7.48 x 30 days/line f= 114540 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 8/17/2018 m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2121100 1.03 Ibs/1000 gal. 706.9 Ibs. PAN 9 r PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 2 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard c. line b - line a (inches in red zone) _ d. top of dike surface area according to design (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft3 3. Projected volume of waste liquid produced during draw down period 12.0 inches 19.8 inches 7.8 inches 46420 ft2 225694 gallons f. temporary storage period according to structural design 880 days g. volume of waste produced according to structural design 43320 ft3 h. current herd # 5913 certified herd # 5913 actual waste produced = current herd # x line g = 43320 ft3 certified herd # i. volume of wash water according to structural design Oft3 j. excess rainfall over evaporation according to design 27078 ft3 k. (lines h + i + j) x 7.48 x 30 days/line f= 87763 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 8/17/2018 m: ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on -the next Structure tab shown below) PoA (30 Day) 2/21/00 1.03 Ibs/1000 gal_ 322.9 Ibs. PAN t PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD 1. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 3 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a_ current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard c. line b - line a (inches in red zone) _ d. top of dike surface area according to design (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft3 3. Projected volume of waste liquid produced during draw down period 12.0 inches 20.0 inches 8.0 inches 19550 ftz 97977 gallons f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 15956 ft3 h. current herd # 2178 certified herd # 2178 actual waste produced = current herd # x line g = 15956 fts certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4 Total PAN to be land applied during draw down period I_ current waste analysis dated 8/17/20 , m. ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21/00 1ft3 11404 1ft3 34109 gallons 1.03 Ibs/1000 gal. 136.0 Ibs. PAN 1 :t II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: 1 line m = 706.9 lb PAN 2. Structure ID: 2 line m = 322.9 lb PAN 3. Structure ID: 3 l line m = 136.0 lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structu"re ID: line m = lb PAN n. lines 1+2+3+4+5+6= 1165.8 lb PAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. a. tract # p. field # q. crop r_ acres s. remaining 1RR 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (Ibs.) column r x s u. application window Zone 1 Bermuda 2.01 248.37 499.2 Mar -Sept Zone 213 Bermuda 4.46 186.91 - 833.6 Mar -Sept Zone 3 Bermuda 5.12 217.49 1113.5 Mar -Sept Zone 4 Bermuda 5.56 184.63 1026.5 Mar -Sept Zone 7A Bermuda 2.15 145.08 311.9 Mar -Sept Zone 7131 Bermuda 1.57 127.49 200.2 Mar -Sept Zone 8 Bermuda 4.52 125.12 565.5 Mar -Sept - J 'State current crop ending application date or next crop application beginning date for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 4550.6 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section 11) = 1165.8 lb. PAN PoA (30 Day) 2/21/00 x. Crop's remaining PAN balance (line v from section III) = 4550.6 lb. PAN y. Overall PAN balance (w - x) _ .3385 lb. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information_ If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is available for pumping if needed. PoA (30 Day) 2/21/00