Loading...
HomeMy WebLinkAbout710073_Plan of Action_20181004PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 71-073 Facility Name: Hairr 2 Certified Operator Name: County: Pender Wesley Hairr Operator Number 19957 1. Current liquid levels) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon Name/ID: Hairr 2 Spillway(Y or N): no Level(inches): 7 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. XXXX Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Phan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: 9/25/2018 1 hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Wesley Hairr � Phone: Facility Owner/Manager (print) Wa7 llevt� Date: 9/25/2018 Facility Owner/Manager (signature) PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES - 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): I Hairr 2 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard - c. line b - line a (inches in red zone) _ d. top of dike surface area according to design (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft3 3. Projected volume of waste liquid produced during draw down period 7.0 inches 19.0 inches 12.0 inches 331056 ftz 2476299 gallons f. temporary storage period according to structural design 180 days g. volume of waste,produced according to structural design 417300 ft3 h. current herd #F---36-0-01 certified herd # 3600 actual waste produced = current herd # x line g = 417300 ft3 certified herd # i. volume of wash water according to structural design Oft3 j. excess rainfall over evaporation according to design 201751 ft3 k. (lines h + i +j) x 7.48 x 30 days/line f= 771750 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 7/13/2018 1.66 Ibs/1000 gal. m. ((lines e + k)/1000) x line 1= 5391.8 lbs. PAN REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21 /00 til II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Hairr 2 line m = 5391.8 lb PAN 2. Structure ID: line m = lb PAN 3. Structure ID: line m = lb PAN 4. Structure'ID: line m = lb PAN 5. Structure ID: line-m = lb PAN 6. Structure ID: line m = lb PAN n.lines 1+2+3+4+5+6= 5391.8lbPAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PFRInD_ ❑n NOT LIST FIELDS Tn WHICH PAN CANNOT RF APPI_IFD Dl1RIN(. THIS 3n DAY PFRIOD o. tract # p. field # q. crop- r. acres s remaining IRR 2 PAN balance (Ib/acre) t TOTAL PAN BALANCE FOR FIELD (lbs.) column rxs u. application window' 3 Crabgrass 33 100.00 3300.0 Mar - Sep 4-5 Bermuda 37 150.00 5550.0 Mar -Sep I 'State current crop ending application date or next crop application beginning date for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 8850.0 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) = 5391.8 lb. PAN x. Crop's remaiging PAN balance (line v from section III) = 8850.0 lb. PAN y. Overall PAN balance (w - x) _ -3458 lb. PAN ine y must show as a deficit. If line y, does not show as a deficit, list course of action here including pump and aul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN ased on new information. If new fields are to be included as an option for lowering lagoon level, add these elds to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to nother permitted facility, provide information regarding the herd population and lagoon freeboard levels at the 3ceiving facility. NARRATIVE: Irrigation onto existing spray fields will continue as weather and field conditions permit. 11 PoA (30 Day) 2/21/00