PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
I
Facility Number:
-Facility Name:
31-95
P-2333(1-3,10-13)
Certified Operator Name: Randall N. Barefoot
County: Duplin
Operator Number: 17796
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lagoon Name/ID: (1-3) . (10-13)
Spillway(Y or N): N N
Level(inches): 13 14
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 9/24/18 Weather permitting.
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and'to the best of my knowledge and ability, the information is
accurate and correct.
Prestage Farms Inc. Phone: 910-592-5771
Facility Owner/Manager (print) -
law Date: 10/25/2018
Facility Owner/Manage(signature)
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/identifier(ID): 1-3)
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 13.0 inches
b. designed 25 yr./24 hr, storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 6.0 inches
top of dike surface area according to design
d. (area at below structural freeboard elevation) 48814 fe
e. line c/12 x line d x 7.48 gallons/ft3 182564 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 61320 ft3
h. current herd # 1860 certified herd # 1860
actual waste produced = current herd # x line g = 61320 ft3
certified herd #
i. volume of wash water according to structural design Oft3
j. excess rainfall over evaporation according to design 28475 ft3
k. (lines h + i +j) x 7.48 x 30 days/line f= 111944 gallons
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 9/24/2018 0.53 ibs/1000 gal.
m., ((lines e + k)/1000) x line 1 = 156 lbs. PAN
REPEAT SECTION 1 FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0
r
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): (10-13)
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/ft3
3. Projected volume of waste liquid produced during draw down period
14.0 inches
19.0 inches
5.0 inches
53941 ft2
168116 gallons
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 35430 ft3
h. current herd # 2480 certified herd # 2480
actual waste produced = current herd # x line g =
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 9/24/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21 /00
35430 f t'
�0 ft3
31466 ft3
83397 gallons
0.55 Ibs/1000 gal.
138.3 Ibs. PAN
1w
Il. TOTAL POUNDS OF PAN, STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YRJ24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE
STRUCTURES FOR FACILITY
1. Structure ID: (1-3)
line m = 156.1 lb PAN
2. Structure ID: (10-13)
line m = 138.3 lb PAN
3. Structure ID:
line m = lb PAN
4. Structure ID:
line m = lb PAN
5. Structure ID:
line m = lb PAN
6. Structure ID:
line m = lb PAN
n. lines +2+3+4+5+6= 294.4lbPAN
111. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNfIT RR ADDI IFn nl IDIAIr TWIQ an nnv Doninn
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR
2 PAN balance
(lb/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u. application window'
4202
1A
Bermuda
3.91
177.00
692.1
Mar -Oct
v. Total PAN
available for all fields (sum
of r_nl imn
tl -
Foo 1
ih Deu
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section 11) = 294.4 lb. PAN
x. Crop's remaining PAN balance (line v from section 111) = 692.1 lb. PAN
y. Overall PAN balance (w - x) _ -397.6 lb. PAN
Line y must show as a deficit. if line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information_ If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Called in to DWR on 9/19118.