HomeMy WebLinkAbout20170537 Ver 1_ As-Built Monitoring Report_20190626Strickland, Bev
From: Dailey, Samantha J CIV USARMY CESAW (USA) <Samantha.J.Dailey@usace.army.mil>
Sent: Wednesday, June 26, 2019 2:54 PM
To: Tugwell, Todd J CIV USARMY CESAW (US); Kim Browning; Haupt, Mac; Davis, Erin B;
Bowers, Todd; Wilson, Travis W.
Subject: [External] SAW -2015-01799 EBX-EM, LLC / Neu -Con UMBI / Hannah Bridge As -Built
Monitoring Report
Follow Up Flag:
Flag Status:
Follow up
Flagged
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.spam@nc.gov<maiIto: report.spam@nc.gov>
Good afternoon,
The below referenced FINAL As -Built Monitoring Report review has been requested by EBX-EM, LLC. Per Section
332.8(0)(9) of the 2008 Mitigation Rule, this review follows the streamlined review process, which requires an IRT
review period of 15 calendar days from this email notification. Please provide any comments by 5 PM on the 15 -day
comment deadline shown below. When providing comments please indicate if your concerns are great enough that you
intend to request an ADDITIONAL site visit prior to the initial credit release (please note the IRT visited the Hannah
Bridge Stream and Wetland Mitigation Site on May 28th, 2019). Comments provided after the 15 -day comment
deadline (shown below) may not be considered.
At the conclusion of this comment period, a copy of all comments will be provided to EBX-EM, LLC and the NCIRT along
with District Engineer's intent to approve or disapprove this Final As -Built and as -built implementation credit release.
Sponsor: EBX-EM, LLC
Name:
Neu -Con UMBI / Hannah Bridge Stream and Wetland Mitigation Site
USACE ID:
SAW -2015-01799
River Basin:
Neuse
H UC:
03020201
County:
Johnston
The As -Built Implementation Credit Release for the Hannah Bridge Mitigation site would entail 15 -percent of the total
stream and wetland restoration and enhancement credits: 846.9 stream mitigation units and 2.23 wetland mitigation
units.
15 -Day Comment Start Date: June 26, 2019 15 -Day Comment Deadline: July 11, 2019 45 -Day Credit Release Approval
Deadline: July 11, 2019
*NOTE: If a site visit is request by the IRT, comments are due 15 days after the site visit is complete.
Mitigation Plan lengths may vary from the As-Builts.
Link to Hannah Bridge As -Built drawings are on RIBITs, under the Hannah Bridge As -Built Report:
https://rib its. usace. a rmy. m i I/ri bits_a pex/f? p=107:278:13795309506457:: N O: R P, 278: P278_BAN K_I D:4413
Please select the arrow beside Hannah Bridge As -Built Report and select Final Hannah Bridge Baseline Monitoring
Report.
Thank you,
Sam
Samantha Dailey
Regulatory Project Manager
U.S. Army Corps of Engineers
Regulatory Division
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
(919) 554-4884, Ext. 22
Samantha.j.dailey@usace.army.mil