HomeMy WebLinkAbout310765_Plan of Action_20190118PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number: 31-765 County: Duplin
Facility Name: Flagship Farms 1, 2 U
Certified Operator Name: Joe Szaloky Operator Number:
AWA999328
1 • Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon Name/ID
Spillway(Y or N):
Level(inches).
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
Lag 1 Lag 2 Lag 3
N N N
19 14 14
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWO prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates fro depopulation
*if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: as conditions permit
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Advantage Farms, LLC Phone: 910-293-5248
Facility Owner/Manager (print)
Date: 1/18/2019
Facility Owner/Manager (signat e)
t
ll. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YRJ24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: 4110
line m = lb PAN
2.
Structure ID. 4111
line m = 574.2 lb PAN
3.
Structure ID: 4112
line m = 514.4 lb PAN
4.
Structure ID:
line m = lb PAN
5.
Structure ID,
line m = lb PAN
6.
Structure ID:
line m = lb PAN
n.lines 1+2+3+4+5+6= 1088.7:ibPAN
111. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT RF APPI IFn nI IRIMr. THI. to nev PF=Pion
o. tract #
p. field # '
q. crop
r. acres
s remaining IRR
2 PAN balance
(lb/acre)
it. TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column rx s
u. application window'
T72141
1
Wheat
3.55
82.90
294.3
Sept -April
2
Wheat
3.05
79.61
242.8
Sept -April
3
Wheat
3.71
79.61
295.4
Sept -April
4
Wheat
2.93
79.61
233.3
Sept -April
5
Wheat
0.90
106.15
95.5
Sept -April
9
Wheat
1.52
106.15
161.3
Sept -April
10
Wheat
3.82
106.15
405.5
Sept -April
11
Wheat
1.37
106.15
145.4
Sept -April
12
Wheat
1.85
106.15
196.4
Sept -April
13
Wheat
1.04
106.15
110.4
Sept -April
14
Wheat
2.71
106.15
287.7
Sept -April
15
Wheat
0.69
106.15
73.2
Sept -April
16
Wheat
1.30
110.55
143.7
Sept -April
17
Wheat
3.12
110.55
344.9
Sept -April
18
Wheat
3.23
110.55
357.1
Sept -April
19
Wheat
6.27
106.15
665.6
Sept -April
State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 4052.5 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 1088.7 lb. PAN
PoA (30 Day) 2/21/00
x. Crop's remaining PAN balance (line v from section 111) = 4052.5 lb. PAN
y. Overall PAN balance (w - x) _ -2964 lb. PAN
Line y must show as a deficit. If line y-does not show as a deficit, list course of action here including pump and
haul, depopulation, .herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Irrigation onto existing spray fields will continue as weather' and field conditions permit. Additional land is
available for pumping if needed. Remaining PAN is an estimate as grower did not supply me with available
PAN.
PoA (30 Day) 2/21/00
.
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): 14110
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker Dinches
b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 19.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 108900 ftZ
e. line c/12 x line d x 7.48 gallons/ft' 1289739 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 121352 ft3
h. current herd # 3672 certified herd #1 3672
actual waste produced = current herd # x line g = 121352 ft'
certified herd #
i. volume of wash water according to structural design Oft3
j. excess rainfall over evaporation according to design 86213 ft3
k. (lines h + i +j) x 7.48 x 30 days/line f= 258764 gallons
4. Total PAN to be land applied during draw down period
I. current waste analysis dated Q Ibs/1000 gal.
m. ((lines e + k)/1000) x line 1 = 0 lbs. PAN
r
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): 14111
2. Current liquid volume in 25 yr./24-hr. storm storage & structural freeboard
a. current liquid level according to marker 14.0 inches
b designed 25 yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 5.0 inches
d. top of dike surface area according'to design
(area at below structural freeboard elevation)
108900 ft2
e, line c/12 x line d x 7.48 gallons/ft3
339405 gallons
3 Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
180 days
g. volume of waste produced according to structural design
121352 ft3
h. current herd # 1 36721 certified herd # 3672
actual waste produced = current herd # x line g =
121352 ft'
certified herd #
i. volume of wash water according to structural design ft3
J. excess rainfall over evaporation according to design 86213 ft3
k. (lines h + i +j) x 7.48 x 30 days/line f= 258764 gallons
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 10/25/2018 0.96 1 Ibs/1000 gal.
m. ((lines e + k)/1000) x line 1 = 574.2 Ibs, PAN
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21/00
.`
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): 4 112
2. Current liquid volume in 25 yr /24 hr. storm storage & structural freeboard
a. current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) _
d. top of dike surface area according to design
(area at below structural freeboard elevation)
14.0 inches
19.0 inches
5.0 inches
1089001 ftz
e. line c/12 x line d x 7.48 gallons/ft3 339405 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 1213521 ft3
h. current herd # 3672 certified herd # 3672
actual waste produced = current herd # x line g = 121352 ft°
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 10/25/2018
m. ((lines e + k)/1000) x line I
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0
PoA (30 Day) 2/21 /00
Oft3
8621-31 ft3
258764 gallons
0.86 Ibs/1000 gal.
514.4 Ibs. PAN