PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
11/19/2018
1. Structure Name/Identifier (ID): E&B Farms Inc. 3 FN: 31-122
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard -
a. current liquid level according to marker
17.0 inches
` b. designed 25 yr./24 hr. storm & structural freeboard
19.0 inches
c. line b - line a (inches in red zone) =
2.0 inches
d. top of dike surface area according to design
(area at below structural freeboard- elevation)
109512 ft2
e. line c/12 x line d x 7.48 gallons/ft3
136525 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
180 days
g. volume of waste produced according to structural design
121058.2 ft3
h. current herd # 3672 certified herd # 3672
actual waste produced = current herd # x line g =
121058 ft'j
certified herd #
i. volume of wash water according to structural design
Oft3
j. excess rainfall over evaporation according to design
66220 ft3
k. (lines h + i +j) x 7.48 x 30 days/line f=
233473 gallons
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 7/24/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
1.19 Ibs/1000 gal.
440.3 Ibs. PAN
PoA (30 Day) 2/21/00 11/19/2018
r
-y
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: E&B Farms Inc.(1)
line m =
lb PAN
2.
Structure ID. E&B Farms Inc. (2)
line m =
lb PAN
3.
Structure ID: E&B Farms Inc. (3)
line m = 440.3 lb PAN
4.
Structure ID:
line m =
lb PAN
5.
Structure ID:
line m =
lb PAN
6.
Structure ID:
line m =
lb PAN
n.lines 1+2+3+4+5+6= 440.3lbPAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s remaining IRR
2 PAN balance
(lb/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u. application wndow'
2900
P1
Small Grain
3.04
50.00
152.0
Oct -March
P2
Small Grain
4.30
50.00
215.0
Oct -March
P3
Small Grain
6.72
50.00
336.0
Oct -March
P5
Small Grain
5.05
50.00
252.5
Oct -March
P6
Small Grain
2.49
50.00
124.5
Oct -March
P7
Small Grain
4.34
50.00
217.0
Oct -March
P9
Small Grain
2.43
5000
121.5
Oct -March
P11
Small Grain
4.30
50.00
215.0
Oct -March
P16
Small Grain
4.02
50.00
201.0
Oct -March
P17
Small Grain
3.97
50.00
198.5
Oct -March
P18
Small Grain
4.00
50.00
200.0
Oct -March
P19
Small Grain
2.95
50.00
147.5
Oct -March
P20
Small Grain
3.15
50.00
157.5
Oct -March
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 2538.0 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 440.3 lb. PAN
x. Crop's remaining PAN balance (line v from section III) = 2538.0 lb. PAN
y. Overall PAN balance (w - x) = -2098 lb. PAN
PoA (30 Day) 2/21 /00 11 /19/2018
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Lagoon 3 still in red from hurricane Florance. Waste will be applied agronomically and hydraulically as
weather permits.