HomeMy WebLinkAbout710014_Plan of Action_20181219t 2, - 4. -1 �
�D/9600z1-0
PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number
71-14
County:
Ponder
Facility Name: Locklin Farms
Certified Operator Name; " Ottls Cavanaugh Operator Number.
71*
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon NameAD:
Spillway(Y or N):
Level(inches):
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
1
N
17
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
XXX Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste
to be pumped and hauled is reflected in section Ill tables. Included within this plan is a list
of the proposed sites with related facifity numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP. "
_ Operation will be partially or fully depopulated.
'Attach a complete schedule with corresponding animal units and dates for depopulation
T animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and hens population for the receiving facility
3. Earliest possible date to begin land application of waste:
1 hereby certify that 1 have reviewed the Information listed above and Included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate.and correct
_ Ottis Cavenaugh Phone: 910-284-2416
a ' ity Ow�rr�r/Manager (print)
Date: 12/14/2018
Facility Owner/Manager (' ature)
In
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
1. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): Lagoon #1
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 17.0 inches
b. designed 25 yr./24 hr. storm & structural freeboard 20.0 inches
c. line b - line a (inches in red zone) = 3.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 95250 ftZ
e. line c/12 x line d x 7.48 gallonsflt' 178118 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 46888 ft3
h. current herd # 3500 certified herd # - 3672
actual waste produced = current herd # x line g = 44692 fe
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 8/16/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I. FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21 /00
Offs
62040 ft3
133059 gallons
0.99 Ibs/1000 gal.
308.1 Ibs. PAN
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1. Structure ID: Lagoon#1
line m =
308.1 lb PAN
2. Structure ID:
line m =
-lb PAN
3. Structure ID:
line m =
lb PAN
4. Structure ID:
line m =
lb PAN-
5. Structure ID:
line m =
lb PAN
6. Structure ID:
line m =
lb PAN
n. lines 1 + 2 + 3 + 4 + 5 + 6 = 308.1 lb PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIFI nS TO WWIrH PANT rANMr1T RI= Aom mn nl IDIAI!_ -ruic qn r►wv ncmjr,n
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR
2 PAN balance
(lb/acre)
L TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u, application window'
7046
Al
Small Grain Overseed
4.07
50.00
203.5
10/1-3/31
A5&6
Small Grain Overseed
5.71
50.00
285.5
10/1-3/31
Acenter
Small Grain Overseed
12.18
50.00
609.0
10/1-3/31
131-4
Small Grain Overseed
15.73
50.00
786.5
10/1-3/31
C1-4
Small Grain Overseed
18.34
50.00
917.0
10/1-3/31
D14
Small Grain Overseed
10.79
50.00
539.5
10/1-3/31
Mate current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 3341.0 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied -(line n from section II) = 308.1 lb. PAN
x. Crop's remaining PAN balance (line v from section III) = 3341.0 Ib. PAN
y. Overall PAN balance (w - x) _ .3033 lb. PAN
PoA (30 Day) 2/21/00
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Irrigation onto existing spray fields will continue as weather and field conditions permit. Information for POA was
supplied by producer on 12/14/18. This POA was completed by Jason Turner Pender SWCD on 12/14/18..
PoA (30 Day) 2/21/00