Loading...
HomeMy WebLinkAbout310870_Plan of Action_20181218PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 31-870 County: Duplin Facility Name: Kenan Hog Farm Certified Operator Name: Reginald Kenan Operator Number: AWA 22043 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon Name/ID: -Spillway(Y or N): Level(inches): Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Kenan N 15 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ prior to transfer of waste to a site not covered, in the facility's CAWMP. - Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number,.lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: as conditions permit I hereby certify that 1 have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is -accurate and correct. Reginald Kenan Phone: 910-289-2144 Facility Owner/Manager (print) Date: 9%16/2018 Facil ner anager (signature) II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: Kenan Lagoon line m = 2067.5 lb PAN 2. Structure ID: line m = lb PAN 3. Structure ID. line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID. line m = lb PAN n.lines I+2+3+4+5+g= 2067.51bPAN 111. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD_ DO NOT I IRT PIFI nC Tn VVWlr u DAKI rAkikinr or Anni irn mi ins- - o tract # p. field # q. crop r. acres s. remaining IRR 2 PAN balance (lb/acre) I. TOTAL PAN BALANCE FOR FIELD (lbs.) column r x s u. application window' T865 F2 RTI 5 Small Grain 4.13 100.00 413.0 Sept - April T865 T865 T865 T865 F2 RTI 6 F2 RT 8 F3 RT 9 F3 RT 10 Small Grain Small Grain Small Grain Small Grain 3.31 1 34 2.20 2.36 100.00 100.00 100.00 100.00 331.0 134.0 220.0 236.0 Sept - April Sept - April Sept - April Sept - April T865 T865 T865 T865 F3 RT 11 F4 RT 14 F3 RT 15 F3 RT 16 Small Grain Small Grain Small Grain Small Grain 2.98 3.90 2.48 2.89 100.00 100.00 100.00 100.00 298.0 390.0 248.0 289.0 Sept -April Sept - April Sept - April Sept.- April appncauvn sate or next crop application beginning date for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 2559.0 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section 11) = 2067.5 lb. PAN PoA (30 Day) 2/21/00 x. Crop's remaining PAN balance (line v irom section'lll) = 2559.0 lb. PAN y. Overall PAN balance (w - x) _ 491 lb. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is available for pumping if needed. PoA (30 Day) 2/21 /00 r- PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID). JKenan Lagoon 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker I15.0 inches b. designed 25 yr./24 hr. storm & structural freeboard E7-1-9.01 inches c. line b - fine a (inches in red zone) = 4.0 inches d. top of dike surface area according to design (area at below structural freeboard elevation) 185400 ft2 e. line c/12 x line d x 7.48 gallons/W 462264 gallons 3. Projected volume of waste liquid produced during draw down period - f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 242116.4 ft3 h. current herd # 7344 certified herd # 7344 actual waste produced = current herd # x line g = 242116 fts certified herd # i. volume of wash water according to structural design r-ft3 j. excess rainfall over evaporation according to design 108150 ft3 k. (lines h + i + j) x 7.48 x 30 days/line f= 436665 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 8/6/2018 2.30 Ibs/1000 gal, m. ((lines e + k)/1000) x line I = 2067.5 Ibs PAN REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21/00