HomeMy WebLinkAbout240015_Plan of Action_2018101720 Iq 00,16-1 244 /0-0 -10 PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number. 24-15 Facility Name: Owen Farm Certified Operator Name: Sidney W. Taylor County: Columbus Operator Number: - 18446 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon Name/ID: 1 Spillway(Y or N): - N Level(inches): 12 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances'are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWQ priorto transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. 'Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: 9/24/18 Weather Permitting. hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct. Prestage Farms Inc. Phone: Facility Owner/Manager (print) jeW'd� Date: Facility Owner/ an er (signature) 910-592-5771 10/17/2018 i 30 DAY DRAW DOWN PERIOD I. TOTAL_ PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 10wen Farm 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard a. current liquid level according to marker 12.0 inches b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches c. line b - line a (inches in red zone) = 7.0 inches top of dike surface area according to design d. (area at below structural freeboard elevation) 130680 ft2 e, line c/12 x line d x 7.48 gallons/ft3 570200 gallons 3. Projected volume of waste liquid produced during draw down period f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 96926 ft 3 h. current herd # F---2-9-40-1 certified herd # 2940 actual waste produced = current herd # x line g certified herd # ' i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7.48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated 1 9/24/2018 m_ ((lines e + k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) 96926 ft3 ICI ft3 76230 ft3 215868 gallons 0.50 393 lbs. PAN . oil II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YRJ24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: 1 line m =' 393.0 lb PAN 2. Structure ID: line m = lb PAN 3. Structure ID: line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID: line m = lb PAN n.lines 1+2+3+4+5+6= 393.0lbPAN 111. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED MIRING THIS an nay PFRInn o. tract # p. field # q. crop r. acres s. remaining IRR 2 PAN balance (Ib/acre) L TOTAL PAN BALANCE FOR FIELD (lbs.) column r x s u. application window' 7669 R1 Rye Overseed 3.50 50.00 175.0 Sep -Mar 7669 R2 Rye Overseed 1.90 50.00 95.0 Sep -Mar 7669 R3 R e Overseed 4.10 50.00 205.0 Sep -Mar I V. I ouu rruv avauaulu wr an nelus tsum of column iJ o IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) x. Crop's remaining PAN balance (line v from section 111) y. Overall PAN balance (w - x) = 4/0.0 ID. PAN 393.0 lb. PAN 475.0 lb. PAN -82 lb. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information., If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Called in to,DWR on 9/19/1 S.