Loading...
HomeMy WebLinkAbout240015_Plan of Action_20190116i �20 / � 40162 PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: 24-15 Facility Name: Owen Farm Certified Operator Name: Sidney W. Taylor County: Columbus Operator Number: 18446 1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways; and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways. Lagoon Name/ID: Spillway(Y or N): Level(inches): Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 1 N 17 2. Check all applicable items Liquid level is within the designed structural freeboard elevations of one or more structures. Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day Plan of Action is attached. Agronomic balance is within acceptable range. Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related facility numbers, number of acres and receiving crop information. Contact and secure approval from the DWO prior to transfer of waste to a site not covered in the facility's CAWMP. Operation will be partially or fully depopulated. *Attach a complete schedule with corresponding animal units and dates fro depopulation *if animals are to be moved to another permitted facility, provide facility number, lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste: 1/18/19 Weather Permitting. I hereby certify that I have reviewed the information listed above and included within the attached Plan of Action, and to the best of my knowledge and ability, the information is accurate and correct Prestage Farms Inc. Phone: Facility Owner/Mans er (p int) Z, Date: Facility Owner/Manager (signature) 910-592-5771 1 /16/2019 t 111 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Name/Identifier (ID): 1 Owen Farm 2. Current liquid volume in 25 yr.124 hr. storm storage &,structural freeboard a. current liquid level according to marker b. designed 25 yr./24 hr. storm & structural freeboard c. line b - line a (inches in red zone) _ top of dike surface area according to design d. (area at below structural freeboard elevation) e. line c/12 x line d x 7.48 gallons/ft3 3. Projected volume of waste liquid produced during draw down period 17.0 inches 19.0 inches 2.0 inches 130680fh 162914 gallons f. temporary storage period according to structural design 180 days g. volume of waste produced according to structural design 96926 ft3 h. current herd # 2940 certified herd # 2940 actual waste produced = current herd # x line g = 96926 ft3 certified herd # i. volume of wash water according to structural design �ft3 j. excess rainfall over evaporation according to design 76230 ft3 k. (lines h + i + j) x 7.48 x 30 days/line f= 215868 gallons 4. Total PAN to be land applied during draw down period I. current waste analysis dated 9/24/2018 0.50 m. ((lines e + k)/1000) x line I = 189 lbs. PAN REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID: 1 line m = 189.4 lb PAN 2. Structure ID: line m = lb PAN 3. Structure ID: line m = lb PAN 4. Structure ID: line m = lb PAN 5. Structure ID: line m = lb PAN 6. Structure ID: line m = lb PAN n.lines1+2+3+4+5+6= 189.4lbPAN -------------- III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD. o. tract # p. field # q. crop r. acres s. remaining IRR 2 PAN balance (lb/acre) t. TOTAL PAN BALANCE FOR FIELD (Ibs.) column r x s u. application window' 7669 R1 Rye Overseed 3.50 40.00 140.0 Sep -Mar 7669 R2 Rye Overseed 1.90 50.00 95.0 Sep -Mar 7669. R3 Rye Overseed 4.10 36.00 143.5 Sep -Mar V. 1 Uldl rP11V dVdlldUle for dil Ilews tsum Oi cowrnn i) _ IV. FACILITY'S PDA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section 11) _ x. Crop's remaining PAN balance (line v from section 111) _ y. Overall PAN balance (w - x) = �J/t3.O to. VAN 189.4 lb: PAN 378.5 lb. PAN -189 lb. PAN i` 1% Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd -reduction options, recalculate new PAN based on new information. If new fields are to be included as an option for lowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility.