PLAN OF ACTION(Poa)' FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number.
Facility Name:
Certified Operator Nar
31-109
Jimmy Britt
County: Duplin
Tempan Jimmy Britt Operator Number.
1. Current liquid level(s) in inches as measured from the current liquid level -in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
i%ithe lagoon to the bottom of the spillway for lagoons with -spillways.
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5-
Lagoon Name/ID: JB1 Jb3
Spillway(Y or N): N N
Level(inches): 18 18
2. Check all applicable items
Liquid level is within the designed, structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Bolume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of -acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP.
Operation will be partially or fully depopulated.
*Attach a complete schedule with corresponding animal units and dates,fro depopulation
*if animals are to'be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 11/4/2018
I hereby certify that I. have reviewed the information listed above. and included within the
attached, Plan of Action, and" to the best of my knowledge and ability, the information- is
accurate and. correct.
Jimmy Britt Phone:
Facility Owner/Manager (print)
Date: 11 /4/2018
Facility Owner/Manager (signature)
II'. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR' 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: J131
line m =
163.6 lb PAN
2.
Structure ID: J133
line m =
161.9 lb PAN
3.
Structure ID:
line m =
lb PAN
4.
Structure ID:
line m =
lb PAN,
5.
Structure ID:
line m =
lb PAN
6.
Structure ID:
line m =
lb PAN
n. lines 1 +2+3+4+5+6= 325.5 lb PAN
III. TOTAL PAN BALANCE REMAINING FOR -AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR-
2 PAN balance
(Ib/acre)
t TOTAL PAN
BALANCE FOR
FIELD (Ibs.)
column r x s
u. application window'
8402
p13
wheat
8.32
111.00
923.5
9/1-4/30
8402
p14
wheat
7.38
111.00
819.2
9/1-4/30
8402
P15
small grain
4.20
50.00
210.0
11/1-3/31
8402
P1
rye
2.38
96.00
228.5
8/15-5/15
8402
P4
rye
4.36
96.00
418.6
8/15-5/15
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 2599.7 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied' (line n from section 11) = 325.5 lb. PAN
PoA (30 Day) 2/21/00
x. Crop's remaining, PAN balance (line v from section III) = 2599.7 lb. PAN
y. Overall PAN balance (w - x) _ -2274 lb. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon, level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is
available for pumping if needed.
PoA (30 Day) 2/21 /00
i
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD' AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): JB1
- 2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 18.0 inches
b. designed 25 yr./24 hr. storm & structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 1.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 40896 1ft2
e. line c/12 x line d x 7.48 gallons/ft3 25492 gallons
3. Projected volume of waste liquid produced during draw down period-
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 48581 ft3
h. current herd # 1470 certified herd # 1470
actual waste produced = current herd# x line g = 48581 ft3
certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 10/11/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION 1 FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
0 ft3
25375 ft3 r
92198 gallons
1.39 Ibs/1000 gal.
163.6 lbs. PAN
PoA (30 Day) 2/21/00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN, PERIOD
1. TOTAL PAN TO ;BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): JB3
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker
�b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according -to design
(area at below structural freeboard elevation)
e. line c/12 x line d x 7.48 gallons/W
3. Projected volume of waste liquid produced during draw down period
18.0 inches
19.0 inches
1.0 inches
11444 ftZ
7133 gallons
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 46188 ft3
h. current herd #F___2_4_0__01 certified herd #1 1400
actual waste produced = current herd-# x line g =
certified herd #
i. volume of wash water according to structural design
J. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated - 10/11/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I- FOR EACH WASTE -STRUCTURE ON SITE.
(Click on the next Strupture tab shown'bellow)
79179 ft'
Offs
21554 ft3
125581 gallons
1.22 Ibs/1000 gal.
161.9 lbs. PAN
t_
PoA (30 Day) 2/21/00
11. TOTAL VOLUME OF WASTE STORED WITHIN STRUCTURAL FREEBOARD ELEVATIONS
FOR ALL WASTE STRUCTURES FOR FACILITY
1. structure ID: JB1
line I =
117334 gallons
2. structure ID: JB2
line I =
131580 gallons
3. structure ID: J133
line I =
42609 gallons
4. structure ID:
line I =
gallons
5. structure ID:
line I =
gallons
6. structure ID:
line I =
gallons
n. lines 1 + 2 + 3 + 4 + 5 + 6 =
291523 gallons
o. line n / 27154 =
10.74 acre -inches
III. TOTAL ACRES AVAILABLE TO RECEIVE WASTE DURING 5 DAY DRAW DOWN PERIOD''2
'While this section deals with hydraulic loading capacities, applications cannot exceed
agronomic rate for receiving crop according to its certified waste plan.
2Fields with no remaining PAN balance, no receiving crop, and/or completely saturated are
not considered available to receive waste.
p._tract #
q. field #
r. soil type
s. crop
t. acres
u. remaining
IRR-2 PAN
balance
(lb/acre)
v. ma)amum
application rate
(in/hr)
w. ma)amum
application
amount (inches)
8402
p13
torh nta
wheat
8.32
111
1-
0.96
8402
p0B
torh nta
wheat
7.38
111
1
0.96
8402
p15
torh nta
bermuda rass
4.20
.86.44
1
0.96
8402
pl
norfolk
rye
2.38
96
1
0.96
8402
p4
norfolk
rye
4.36
96
1
0.96
x. total acres available during 5 day draw down (sum of column t) = 26.64 acres
IV. FACILITY'S PoA OVERALL HYDRAULIC LOAD TO BE LAND APPLIED PER ACRE
PoA (5 Day) 2/21/00
Y. line o = 0.40 inches per acre to be applied within 5 days
line x
If unable to land apply hydraulic load listed in line y, list course of action here including pump
and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options,
recaicuiate new n arauuc ioaa nasea on new
to land app
1. Describe moisture conditions of fields? (e.g. Is there water standing in field; does irrigation
equipment mar down in tield; "tratticability" across soils; will soils absorb application without runott, etc.
Heavy RainFall from Hurrican Florance.
All fields in good conditions.
2. Date and amount of last rainfall event?
DATE: 09/16/18
AMOUNT: 13.00 inches
4. Given optimum soil and weather conditions, is irrigation equipment capable of applying the volume in
line "n" at appropriate seasonal i.e. winter application rates within 5 days?
Yes
5. Irrigation schedule for next 5 days - Include daily schedule; proposed application rates and amounts
per irrigation event; changes made in gun sizes, nozzles, "o" rings, operating time, travel speed, etc. to
meet proposed cnanges in application rates and amounts; and any otl
All pulls will be made in a manner so as not to allow runoff or ponding.
i
PoA (5 Day) 2/21/00