HomeMy WebLinkAbout20190104 Ver 2_Utilities Modification Table- B-4916_20190614WETLAND PERMIT IMPACT SUMMARY WETLAND IMPACTS SURFACE WATER IMPACTS Site No. Station (From/To) Structure Size / Type Permanent Fill In Wetlands (ac) Temp. Fill In Wetlands (ac) Excavation in Wetlands (ac) Mechanized Clearing in Wetlands (ac) Hand Clearing in Wetlands (ac) Permanent SW impacts (ac) Temp. SW impacts (ac) Existing Channel Impacts Permanent (ft) Existing Channel Impacts Temp. (ft) Natural Stream Design (ft) 1 -L- 10+88 RT WATER LINE IMPACTS + 0.005 < 0.01 TO 10+98 RT 2 -L- 11+90 RT TEMPORARY POWERLINE RELOCATION < 0.01 < 0.01 0.27 TO 16+82 RT + 0.034 TOTALS`: < 0.01 0.005 < 0.01 --0-28— 0 1 0 0 "Rounded totals are sum of actual impacts NOTES: 2014 0.314