HomeMy WebLinkAbout20181161 Ver 1_Table 3 - Stream Impacts_Updated_201905093. Stream Impacts: If there are perennial or intermittent
stream impacts (including temporary impacts) proposed on the site, then complete this question for all stream sites impacted.
3a. Stream
Impact Number,
Permanent or
Temporary
3b. Type of Impact
3c. Stream Name
3d. Determination
3e. Type of
Jurisdiction
3f. Average Stream
Width (ft.)
3g.
Impact
Length
(if.)
S1-P
Culvert
Gashes Creek (Sol)
Perennial
Corps
6
42
S2 - P
Culvert
Gashes Creek (S01)
Perennial
Corps
6
42
S3 - P
Culvert
UT1 > Gashes Creek (S02)
Perennial
Corps
2
50
S4 - P
Culvert extension
Gashes Creek (S01)
Perennial
Corps
6
9
S5 - T
Coffer dam construction
Gashes Creek (S01)
Perennial
Corps
6
10
S6 - T
Coffer dam construction
Gashes Creek (S01)
Perennial
Corps
6
10
S7 - T
Coffer dam construction
UT1 > Gashes Creek (S02)
Perennial
Corps
2
10
S8 - T I
Cofferdam construction
I Gashes Creek (S01)
Perennial
iCorps
6
10
S9 - T ICutvert
removal & bank stabilization
I UT2> Gashes Creek (S03)
I Perennial
lCorps
2
20
(Sum All Impacts)
(Temporary)
Net Permanent Impacts
203
60
143