HomeMy WebLinkAbout20190565 Ver 1_Additional Info Received Corps_20190503Mitchell, Robert K
From: tealleneng@comporium.net
Sent: Friday, May 3, 2019 11:39 AM
To: 'Brown, David W CIV USARMY CESAW (US)'
Cc: Mitchell, Robert K; Leslie, Andrea J
Subject: [External] RE: Request for Additional Information - McCarter Residence New Boathouse
Attachments: PCN Form - McCarter, NWP 3 - Rev 2.doc
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to report.spam@nc.gov<mai Ito: report.spam@nc.gov>
Hello Mr. Brown:
I confirmed the existing site conditions at the McCarter Residence. The new Boathouse will be located in approximately
the same footprint as the existing Boathouse. The existing Boathouse has not be demolished yet. The original fill
associated with the existing Boathouse is about 35 CY. The fill associated with the new Boathouse is approximately 40
Cy.
I am proposing a change to the PCN Form to NWP 3 authorization. I have attached a copy of the revised PCN Form
changing to a NWP 3.
Please let me know if this is acceptable.
Please call or email if you have any questions.
Thank you.
Terry Allen, PE, MSE
T.E. ALLEN ENGNIEERING, PC
P.O. Box 103
Rosman, NC 28772
828-553-3004 Mobile
828-877-4883 Office
-----Original Message -----
From: Brown, David W CIV USARMY CESAW (US) [mailto:David.W.Brown@usace.army.mil]
Sent: Friday, May 03, 2019 8:01 AM
To: tealleneng@comporium.net
Cc: Mitchell, Robert K; Leslie, Andrea J
Subject: Request for Additional Information - McCarter Residence New Boathouse
T.E. Allen Engineering, P.C.
Rosman, NC 28772
Terry Allen,
The Corps has received (April 26) and reviewed the submitted Pre -Construction Notification (PCN) application and
supporting documents for the new boathouse foundation at the McCarter residence, 282 Windward Point, Lake
Toxaway, Transylvania County, NC. The PCN request utilization of Nationwide Permit (NWP) 18 for 0.08 acres of
temporary open water impacts and 0.02 acres of permanent open water impacts to Lake Toxaway for construction the
new boathouse foundation.
NWP 18 authorizes minor discharges of dredged or fill material into all waters of the U.S. (WoUS). Under this NWP the
quantity of discharged material cannot exceed 25 cubic yards below the plane of the ordinary high water mark (OHWM).
After review of the submitted PCN and supporting documents the Corps has the following comments and request for
additional information.
1) Review of the submitted documents indicate 38-40 cubic yards of fill are to be placed below the OHWM. This amount
exceeds the allowable fill volume under NWP 18. Please confirm the amount of fill to be placed in WoUS for this project.
2) Is the new foundation replacing an existing foundation at the same location on the property? If so, what is the
amount of fill in WoUS of the existing foundation?
3) As proposed the project does not meet the conditions of NWP 18. You may need to redesign the project to meet the
conditions of NWP 18 or withdraw this request and resubmit the project under another NWP or resubmit the project
under an individual permit.
Please copy Kevin Mitchell with NC Department of Environment Quality, Division of Water Resources and Andrea Leslie
with NC Wildlife Resources Commission (NCWRC) on your response to this request. At this time, the request to utilize
NWP 18 for authorization of impacts to WoUS for this project is on hold until the above noted information is submitted.
Once the Corps receives the information listed above and comments from NCWRC we will be able to continue to process
your application. If you have any questions please contact me.
Sincerely,
David Brown, PG
Regulatory Specialist/Geologist
USACE Wilmington District -Asheville Regulatory Field Office
151 Patton Avenue, Room 208
Asheville, NC 28801-5006
828-271-7980, ext. 4232
david.w.brown@usace.army.mil
This email has been checked for viruses by AVG.
https://www.avg.com