HomeMy WebLinkAbout310391_30 day Plan of Action_20181203,1 ,. 3A- 3 a I
ZMU3s6 Z
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
�j
Facility Number: "11 N - County: ar4l
Facility
S' ,C ve- sm 1 ,
Certified Operator Name: 56V,4 .5?4,,A Operator # 11VY
Current liquid level(s) in inches as measured from the current liquid_ level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways
Structure 1 Structure 2 Structure 3 Structure 4 Structure 5 Structure 6
Lagoon Name/Identifier (ID): SS�
Spillway (Yes or No): I V�
Level (inches):
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures. Five
and 30 day Plans of Action are attached. Hydraulic and agronomic balances are within
acceptable ranges.
Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A 30 day
Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste to
pumped and hauled is reflected in section III tables. Included within this plan is a list of the
proposed sites with related facility number(s), number acres and receiving crop information.
Contact and secure approval from the Division of Water Resources prior to transfer of
waste to a site not covered In the facility's certified animal waste management plan.
Operation will be partially or fully depopulated.
- attach a complete schedule with corresponding animal units and dates for depopulation
- if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population fog the receiving facility
3. Earliest possible date to begin land application of waste:
I hereby certify that I have reviewed the information listed above and included within the attached Plan
of Action, and to the best of my knowledge and ability, the Information is accurate and correct.
S+iphvn Crglg * Sm,M
Facility Owner/Manager (print)
WAIN WN
Owner/Manager (signature)
PoA Cover Page 2121100
Phone: ara- SSO-0/77
Date: 12 •3 - zo/('
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PANTO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID). I Steve Smith Farm 99132
2 Current liquid volume in 25 yr.124 hr. storm storage & structural freeboard
a current liquid level according to marker
b. designed 25 yr./24 hr. storm & structural freeboard
c. line b - line a (inches in red zone) =
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e• line c/12 x line d x 7.48 gallons/fO
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design
18.Oinches
19.5inches
. 1.5inches
70000 ft2
65450 gallons
180 days
g. volume of waste produced according to structural design 71211 fe
h. current herd # 2100 certified herd # 2160
actual waste produced = current herd # x line g =
certified herd #
I. volume of wash water according to structural design
j excess rainfall over evaporation according to design
k (lines h + i +j) x 7,48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 8/16/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21/00
69233 tt'
0 to
40833.3 fe
137216 gallons
0.83 Ibs/1000 gal.
168.2 lbs. PAN
"I
1 structure ID: 551
2. structure ID-
3. structure ID:
4. structure ID:
5. structure ID:
6. structure ID:
n. lines 1+2+3+4+5+6 =
line m =
Ib PAN
line m =
lb PAN
line m =
lb PAN
line m =
lb PAN
line m =
lb PAN
line m =
lb PAN
1 6 9• of
lb PAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAYDRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CAN NOT BE APPLIES DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining
IRR-2 PAN
balance
(lb/acre)
t. TOTAL PAN
BALANCE
FOR FIELD
(lbs.)
column r x s
u.
application
window'
o
p
c�,s
S
a
N
Coa
v
a07
1630
3
Coas?W
a.31
Sv
s.s
36
Co1
O
1�6
'State current crop ending application date or next crop application beginning date for available receiving
crops during 30 day drawn down period
v. Total PAN available for all fields (sum of column t) _ lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
PoA (30 Day) 2121100 2
w. Total PAN to be land applied (line n from section II) _ �G 8 a lb. PAN
ic. Crop's remaining PAN balance (line v from section III) 2019lb. PAN
y. Overall PAN balance (w -x) = - 3 9.43 lb. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here
including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd
reduction options, recalculate new PAN based on new information. If new fields are to be
included as an option for lowering lagoon level, add these fields to the PAN balance table and
recalculate the overall PAN balance. If animal waste is to be hauled to another permitted
facility provide information regarding the herd population and lagoon freeboard levels at the
receiving facility.
NARRATIVE:
PoA (30 Day) 2/21/00 3