HomeMy WebLinkAbout310368_30 day POA_20181010BARWICK AG SERVICES, LLC
103 COUNTRY CLUB CIRCLE
CLINTON, NC 28328
October 9 2018
North Carolina Division of Aquifer Protection
Attn: Mrs. Kristin Miguez
127 Cardinal Drive Extension
Wilmington, NC 28405-2845
Dear Kristin,
Please find enclosed Plans of Action for the following farms. All were pumped down prior to
Hurricane Florence but due to 25-30" of rain; all lagoons got in the red- Pre -and post -storm
levels were as follow:
31-92 OR Blizzard Farm: 36" pre, 7" post
31-368 Boyd Barfield Farm. #1, 35' pre, 12" post, #2; 34" pre, 12" post
31-656 Lynn & Annette Smith Farm: 38" pre, 12" post
71-12 Crooked Run: 30" pre: 4" post
We have had an extremely wet 2018 and lagoons have been more difficult to manage than
usual.
Thank you for your attention to this matter.
Sincerely,
Curtis Barwick
av�g o as��
PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number:
31-368
County: Du
Facility Name: Boyd Barfield Farm
Certified Operator Name: Thomas Barfield Operator Number
999323
1. Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways, and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways.
Lagoon Name/ID
Spillway(Y or N):
Level(inches).
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
1 2
N N
12 12
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures. A
30 day Plan of Action is attached. Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations. Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables. Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP
Operation will be partially or fully depopulated.
'Attach a complete schedule with corresponding animal units and dates fro depopulation
'if animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3. Earliest possible date to begin land application of waste: 912212018
I hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Thomas Barfield / Manager Phone: 919-222-9921
Facility Owner/Manager (print)
Date: 10/9/2018
Facility Owner/Manager (signature)
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID).- 11
2. Current liquid volume in 25 yr./24 hr. storm storage & structural freeboard
a. current liquid level according to marker 12.0 inches
b. designed 25 yr./24 hr. storm & structural freeboard19.0 inches
c. line b - line a (inches in red zone) = 7.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 54289 ft2
e. line c/12 x line d x 7.48 gallons/ft3 236881 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 40617 ft3
h. current herd # 1232 certified herd # 1232
actual waste produced = current herd # x line g = 40617 ft3
certified herd #
i. volume of wash water according to structural design Oft3
j. excess rainfall over evaporation according to design 33042 ft3
k. (lines h + i + j) x 7.48 x 30 days/line f= 91828 gallons
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 9/26/2018 0.85 Ibs/1000 gal.
m. ((lines e + k)/1000) x line 1 = 279.4 Ibs. PAN
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
PoA (30 Day) 2/21 /00
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/Identifier (ID): 12
2. Current liquid volume in 25 yr./24 hr.'storm storage & structural freeboard
a. current liquid level according to marker 12.0 inches
b. designed 25 yr./24 hr. storm &structural freeboard 19.0 inches
c. line b - line a (inches in red zone) = 7.0 inches
d. top of dike surface area according to design
(area at below structural freeboard elevation) 45796 ft2
e. line c/12 x line d x 7.48 gallons/ft3 199823 gallons
3. Projected volume of waste liquid produced during draw down period
f. temporary storage period according to structural design 180 days
g. volume of waste produced according to structural design 40617 ft3
h. current herd #F---1-2-3-21 certified herd # 1232
actual waste produced = current herd # x line g =
.certified herd #
i. volume of wash water according to structural design
j. excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4. Total PAN to be land applied during draw down period
I. current waste analysis dated 1 9/26/2018
m. ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
40617 ft3
Oft3
27977 ft3
85514 gallons
0.83 Ibs/1000 gal.
236.8 Ibs. PAN
PoA (30 Day) 2/21 /00
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR./24
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1.
Structure ID: 1
line m =
279.4 lb PAN
2.
Structure ID: 2
line m =
236.8 lb PAN
3.
Structure ID:
line m =
lb PAN
4.
Structure ID:
line m =
lb PAN
5.
Structure ID:
line m =
lb PAN
6.
Structure ID:
line m =
lb PAN
n. lines 1 + 2 + 3 + 4 + 5 + 6 = 516.2lbPAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PFRInn Inn NnT I IRT F'IFI ns TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD.
o. tract #
p. field #
q. crop
r. acres
s. remaining IRR
2 PAN balance
(lb/acre)
t. TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u. application window'
3068
1
rye overseed
3.27
100.00
327.0
OCT-FEB
3068
2
rye overseed
3.22
100.00
322.0
OCT-FEB
3068
3
rye overseed
3.51
100.00
351.0
OCT-FEB
3068
4
rye overseed
2.76
100.00
276.0
OCT-FEB
3068
5
rye overseed
1.25
100.00
125.0
OCT-FEB
3068
6
rye overseed
3.30
100.00
330.0
OCT-FEB
3068
7
rye overseed
1.82
100.00
182.0
OCT-FEB
3068
8
rye overseed
2.69
100.00
269.0
OCT-FEB
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 2182.0 lb. PAN
IV. FACILITY'S PoA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = - 516.2 lb. PAN
PoA (30 Day) 2/21/00
x. Crop's remaining PAN balance (line v from section III) = 2182.0 Ib. PAN
y. Overall PAN balance (w - x) _ -1666 Ib. PAN
Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc For pump & haul and herd reduction options, recalculate new PAN
based on new information. If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility
Irrigation onto existing spray fields will begin as weather and field conditions permit.
PoA (30 Day) 2/21/00