Please find enclosed Plans of Action for the Hunter farms All were pumped down prior to
Hurricane Florence but due to 25-30" of rain, all lagoons got in the red. Pre -and post -storm
levels were as follow:
31-131 Michael Hunter#1 (Hazel Farm): 44" pre; 17" post
31-792 Michael Hunter #2 (Hallsville Farm)- 46" pre; inundated post
Both lagoons are now in compliance.
We have had an extremely wet 2018 and lagoons have been more difficult to manage than
usual.
Thank you for your attention to this matter.
Sincerely,
Curtis Barwick
Ugb [96
PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
Facility Number
31-131
Facility Name Michael Hunter #1 (Hazel)
Certified Operator Name Scott Hunter
County Duplin
Operator Number 18075
1 Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the
lowest point on the top of the dam for lagoons without spillways; and from the current liquid level
in the lagoon to the bottom of the spillway for lagoons with spillways
Lagoon Name/ID
Spillway(Y or N):
Level(inches):
Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5
17
2. Check all applicable items
Liquid level is within the designed structural freeboard elevations of one or more structures.
Five and 30 day Plans of Action are attached. Hydraulic and agronomic balances are
within acceptable ranges.
X Liquid level is within the 25 year 24 hour storm elevations for one or more structures A
30 day Plan of Action is attached Agronomic balance is within acceptable range.
Waste is to be pumped and hauled to off site locations Volume and PAN content of waste
to be pumped and hauled is reflected in section III tables Included within this plan is a list
of the proposed sites with related facility numbers, number of acres and receiving crop
information. Contact and secure approval from the DWQ prior to transfer of waste to a site
not covered in the facility's CAWMP
Operation will be partially or fully depopulated.
'Attach a complete schedule with corresponding animal units and dates fro depopulation
cif animals are to be moved to another permitted facility, provide facility number, lagoon
freeboard levels and herd population for the receiving facility
3 Earliest possible date to begin land application of waste 9/21/2018
1 hereby certify that I have reviewed the information listed above and included within the
attached Plan of Action, and to the best of my knowledge and ability, the information is
accurate and correct.
Michael Hunter
Facility Owner/Manager (print)
Phone 910 298-8364
Date, 10/9/2018
Facility Owner/Manager (signature)
II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124
HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY
1
Structure ID. 1
line m = 161
2 lb PAN
2
Structure ID:
line m =
lb PAN
3
Structure ID
line m =
lb PAN
4.
Structure ID
line m =
lb PAN
5.
Structure ID
line m =
lb PAN
6.
Structure ID
line m =
lb PAN
n. lines 1 + 2 + 3 + 4 + 5 + 6 = 1612lbPAN
III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN
PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DURING THIS 30 DAY PERIOD_
a tract #
p. field #
q. crop
r acres
s remaining IRR
2 PAN balance
(lb/acre)
L TOTAL PAN
BALANCE FOR
FIELD (lbs.)
column r x s
u application window'
1671
10
small grain
5.05
5000
2525
Oct -Mar
1671
11
small grain
5.05
50.00
2525
Oct -Mar
1671
12
small grain
541
5000
2705
Oct -Mar
1671
9
small grain
531
5000,
265.5
Oct -Mar
'State current crop ending application date or next crop application beginning date for available
receiving crops during 30 day draw down period.
v. Total PAN available for all fields (sum of column t) = 1041 0 lb. PAN
IV. FACILITY'S PDA OVERALL PAN BALANCE
w. Total PAN to be land applied (line n from section II) = 161 2 lb. PAN
PDA (30 Day) 2/21/00
x. Crop's remaining PAN balance (line v from section III) = 1041 0 lb. PAN
y. Overall PAN balance (w - x) _ -880 lb. PAN
Line y must show as a deficit If line y does not show as a deficit, list course of action here including pump and
haul, depopulation, herd reduction, etc For pump & haul and herd reduction options, recalculate new PAN
based on new information If new fields are to be included as an option for lowering lagoon level, add these
fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to
another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the
receiving facility
Irrigation onto existing spray fields will continue as weather and field conditions permit Other land is available
application.
PoA (30 Day) 2121100
PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES
30 DAY DRAW DOWN PERIOD
I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE
1. Structure Name/ldentifier (ID). 1
2 Current liquid volume in 25 yr /24 hr storm storage & structural freeboard
a current liquid level according to marker
b designed 25 yr./24 hr storm & structural freeboard
c line b - line a (inches in red zone) _
d. top of dike surface area according to design
(area at below structural freeboard elevation)
e. line c112 x line d x 7.48 gallonslft'
3. Projected volume of waste liquid produced during draw down period
f temporary storage period according to structural design
17.0 inches
19.5 inches
25 inches
60475 ftz
94240 gallons
180 days
g volume of waste produced according to structural design 80706 ft3
h current herd # 2448 certified herd # 2448
actual waste produced = current herd # x line g =
certified herd #
i volume of wash water according to structural design
j excess rainfall over evaporation according to design
k. (lines h + i + j) x 7.48 x 30 days/line f=
4 Total PAN to be land applied during draw down period
I current waste analysis dated 9/26/2018
m ((lines e + k)/1000) x line I =
REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE.
(Click on the next Structure tab shown below)
80706 ft'
0 ft3
36750 ft3
146428 gallons
0.67 Ibs/1000 gal.
161.2 Ibs. PAN