HomeMy WebLinkAbout20140762 Ver 4_April 17 Sediment inspection_20190422Wetland Inspection Report
Project Num: 20140762
Project Name: NCDOT- US 221 (R-2915B)
County: Watauga
Location: NCDOT- US 221 (R-2915B)
Latitude: +35' 16' 05"
SW Plan Location
Site Owner Name NC DOT PDEA
Inspection Date: 4/17/2019
Reason for Inspection Routine
Inspection Type: Site Inspection (DOT)
Inspection Contact Person:
On -Site Representative(s):
Version: 4 Status: Issued
Project Type: Road/Highway Widening
Region: Central
Title:
Primary Inspector: Dave Wanucha
Secondary Inspector(s):
Facility Compliance Status: ❑ Compliant 0 Not Compliant
Program Areas: Standards/Sediment
Question Areas:
Unpermittable Activities
Inspection Summary:
A follow up inspection will occur in May.
Longitude: -81 ° 30' 10"
Phone:
Phone: 336-776-9703
page: 1
Site Number: 20140762 Owner: Thorpe, Gregory
Inspection Date: 4/17/2019 Inspection Type: Site Inspection (DOT) Reason for Visit: Routine
Unpermittable Activities
Yes No NA NE
# Note: This section should be completed only if the impact is unpermittable (eg. Sediment, draining
wetlands, etc.).
Is stream(s) free of unpermittable impacts?
❑
0
❑
❑
Is wetland(s) free of unpermittable impacts?
❑
0
❑
❑
Is open water(s) free of unpermittable impacts?
❑
❑
0
❑
Are other standards being met (turbidity, pH, etc.) in all surface waters onsite?
❑
❑
0
❑
Are surface waters on the site free of illegal discharges?
❑
❑
0
❑
Comment: Site 6 was ok but removed sediment needed to be taken to upland site. Site 13A needed additional
sediment and 57 stone removed. SDO near Site 8 needed sediment removed and fencing repaired. Sites
2A and B needed a boulder removed and sediment removed from SDOs. Site 13A needs to be checked
for sediment around inlet of temporary culvert. Bridge drains discharge directly to wetlands on B-Section.