660034_Plan of Action_20190107
6 1ms .1P PLAN OF ACTION(Poa) FOR HIGH FREEBOARD AT ANIMAL FACILITIES Facility Number: Facility Name Certified Operator Name AWS660034 County- Smithfield-Carroll's Farm 11 (8511) William Bain Jr Northampton Operator Number 991343 1 Current liquid level(s) in inches as measured from the current liquid level in the lagoon to the lowest point on the top of the dam for lagoons without spillways: and from the current liquid level in the lagoon to the bottom of the spillway for lagoons with spillways Lagoon 1 Lagoon 2 Lagoon 3 Lagoon 4 Lagoon 5 Lagoon NamellD 11P 11S Spillway(Y or N) N N Level(inches): 16 19 2. Check all applicable items Liquid level is within the designed structural Freeboard elevat ons of one or more structures Five and 30 day Plans of Act on are attached Hydraulic and agronomic balances are within acceptable ranges. X Liquid level is within the 25 year 24 hour storm elevations for one or more structures A 30 day Plan of Action is attached. Agronomic balance is within acceptable range X Waste is to be pumped and hauled to off site locations Volume and PAN content of waste to be pumped and hauled is reflected in section III tables. Included within this plan is a list of the proposed sites with related fac Idy numbers, number of acres and receiving crop information. Contact and secure approval from the DWO prior to transfer of waste to a site not covered In the facility's CAWMP. Operation will be partially or fully depopulated *Attach a complete schedule with corresponding animal units and dates fro depopulation 'if animals are to be moved to another perm;tted facility, provide facility number. lagoon freeboard levels and herd population for the receiving facility 3. Earliest possible date to begin land application of waste- as conditions perm't I hereby certify that I have reviewed the Information listed above and Included within the attached Plan of Action, and to the best of my knowledge and abllity, the information is accurate and correct. R.O_ Britt Phone 1-804-834-2109 Fa ' y ZneNMana (print Date. 1/7/2019 n r( a PLAN OF ACTION (PoA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1, Structure Namefidentifier (ID): 11 P 2. Current liquid volume in 25 yr.124 hr. storm storage & structural freeboard a, current liquid level according to marker 16.0 inches b. designed 25 yr./24 hr. storm & structural freeboard i9.0 inches c line b - line a (inches in red zone) = 3.0 inches d top of dike surface area according to design (area at below structural freeboard elevation) 111582 ft2 e. line c/12 x line d x 7.48 gallons/ft' 208658 gallons 3 Projected volume of waste liquid produced during draw down period f_ temporary storage period according to structural design 125 days g volume of waste produced according to structural design 240268 W h, current herd # 3272 certified herd # 3272 actual waste produced = current herd # x 'ine g = certified herd # i. volume of wash water according to structural design j. excess rainfall over evaporation according to design k. (lines h + i + j) x 7 48 x 30 days/line f= 4. Total PAN to be land applied during draw down period I. current waste analysis dated I 11/1/2018 m. ((lines e + k)/1000) x line I = REPEAT SECTION 1 FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2/21/00 240268 ft' �0 UW 431329 gallons 2 i6 Ibs11000 gal 1382A lbs. PAN PLAN OF ACTION (POA) FOR HIGH FREEBOARD AT ANIMAL FACILITIES 30 DAY DRAW DOWN PERIOD I. TOTAL PAN TO BE LAND APPLIED PER WASTE STRUCTURE 1. Structure Namelidentifier (ID): Ills 2. Current liquid volume in 25 yr.124 hr storm storage & structural freeboard a. current liquid level according to marker 19 0 :nches b. designed 25 yr,124 h,-. storm & structural freeboard 19 0 inches c. line b - line a (inches in red zone) = inches d. top of dike surface area according to design (area at below structural freeboard elevation) 76881 ftz e. line c/12 x line d x 7.48 gallonslft' gallons 3 Projected volume of waste !iquid produced during draw down period f temporary storage period according to structural design 125 days g. volume of waste produced according to structural design fe h current herd # 3272 certified herd # 3272 actual waste produced = current herd # x line g = certified herd # i. volume of wash water according to structural des gn i. excess rainfal: over evaporation according to des gn k. (lines h + i + f) x 7.48 x 30 days/line f= 4 Total PAN to be land applied during draw down period I. current waste analysis dated 11/1/2018 m. ((lines e+ k)/1000) x line I = REPEAT SECTION I FOR EACH WASTE STRUCTURE ON SITE. (Click on the next Structure tab shown below) PoA (30 Day) 2121100 fts © ft3 109937 ft3 197359 gallons 1,49 Ibs11000 gal. 294.1 Ibs, PAN II. TOTAL POUNDS OF PAN STORED WITHIN STRUCTURAL FREEBOARD AND/OR 25 YR.124 HR. STORM STORAGE ELEVATIONS IN ALL WASTE STRUCTURES FOR FACILITY 1. Structure ID- lip line m = 1382.4 lb PAN 2. Structure ID: 11 S line m = 294.1 lb PAN 3. Structure ID* line m = lb PAN 4_ Structure ID- line m = lb PAN 5. Structure ID' line m = lb PAN 6 Structure ID, line m = lb PAN n. lines 1 + 2 + 3 + 4 + 5 + 6 = 16764lbPAN III. TOTAL PAN BALANCE REMAINING FOR AVAILABLE CROPS DURING 30 DAY DRAW DOWN PERIOD. DO NOT LIST FIELDS TO WHICH PAN CANNOT BE APPLIED DARING THIS 30 DAY PERIOD. o. tract # p. field # q. crop r acres s remaining 1RR 2 PAN balance (Ibfacre) L TOTAL PAN BALANCE FOR FIELD (lbs.) column r x s u. application window C Cover Crop 5.03 16.94 85.2 Sept -Apr LP1 Cover Crop 33.65 22.29 750.1 Sept -Apr LP2 Cover Crop 21.53 29.79 641.4 Sept -Apr zone 1 Overseed 410 3.82 15.7 Sept -Apr zone 2 Overseed 367 15.55 57.1 Sept -Apr zone 3 Overseed 349 25.68 89.6 Sept -Apr zone 4 Overseed 355 3669 130.2 Sept -Apr 'State current crop ending application date or next crop application beg nning date for available receiving crops during 30 day draw down period. v. Total PAN available for all fields (sum of column t) = 1769.2 lb. PAN IV. FACILITY'S PoA OVERALL PAN BALANCE w. Total PAN to be land applied (line n from section II) = 1676 4 Ib. PAN PoA (30 Day) 2/21100 x. Crop's remaining PAN balance (line v from section III) = 1769.2 lb. PAN y. Overall PAN balance (w - x) = -93 lb. PAN Line y must show as a deficit. If line y does not show as a deficit, list course of action here including pump and haul, depopulation, herd reduction, etc. For pump & haul and herd reduction options, recalculate new PAN based on new information. If new fields are to be included as an option foCowering lagoon level, add these fields to the PAN balance table and recalculate the overall PAN balance. If animal waste is to be hauled to another permitted facility, provide information regarding the herd population and lagoon freeboard levels at the receiving facility. Irrigation onto existing spray fields will continue as weather and field conditions permit. Additional land is available for pumping if needed. Pump and haul to Farm 8529, AWS660030 as needed. PoA (30 Day) 2/21/00 Towel[, Buster From: Weston, Kevin <kweston@smithfield.com> Sent: Monday, January 07, 2019 2:39 PM To: Towell, Buster Cc: Britt, RO; Queen, Earl Subject: [External] Farm 8511 POA Attachments: 8511 30 Day POA 010719.pdf EA roil emaii, DoY.,not click links or open attachments unless your veri€ied. Send a!i suspiao '01:e' enailas aq attaehment to FRE Man & — _ _.. —.dwmmamank- Buster, Attached is a copy of the 30 Day PoA for Farm 8511, AWS660034 in Northampton County. Smithfield. Kevin Weston Environmental Resource Specialist p: (910) 293-5363 x55363 c: (910) 290-3300 e; kweston@smithfield.com 2822 Hwy 24 W Warsaw, North Carolina 28398 smithfieldfoods.com