HomeMy WebLinkAbout20180765 Ver 2_Stream enhancement memo 030519_20190306Headwaters Engineering, PC NCBELS Lic. No. C-4500 MEMORANDUM TO: David Brown, US Army Corps of Engineers Kevin Mitchell, NC Division of Water Resources FROM: Andrew Bick, PE DATE: March 5, 2019 RE: Stability Assessment and Stream Enhancements UTs to Fowler Creek High Hampton Resort, Cashiers, Jackson County, NC Approximately 880 linear feet (LF) of culvert was removed from an unnamed tributary to Fowler Creek (referred to in the attached plans as UT1) at the High Hampton Resort golf course, which is currently undergoing a renovation. The banks of the daylighted channel were sloped and large stone was placed in the bed and on the banks. A subsequent sediment removal effort was completed at the request of DWR. UT2 is located about 1,700 LF east of UTI in the #2 fairway. The Corps and DWR expressed concern with the height of the drop at the beginning of the UT2 channel at a headwall where two culverts discharge, specifically with regard to stability and aquatic organism passage. The purpose of this memo is to document as -built surveys completed by C1earWater Environmental Consultants (CEC), to summarize our analysis of channel stability based on this survey and our observations of the site, and to present proposed stream enhancements. As -Built Survevs In February 2019, CEC staff completed total station surveys of the daylighted UT 1 channel and UT2 near the headwall. The surveys were based on a local datum. The UT 1 survey included points along the top of both banks, the thalweg and water surface, four cross sections and several ground points. The UT2 survey collected points along the thalweg of the channel and at a transect immediately downstream of the headwall. The attached plans show the results of the surveys superimposed on 2015 aerial imagery, which was collected prior to the stream daylighting. The plan view of UT 1 indicates a relatively straight alignment through roughly the low point of the valley between a culvert under a cart path at the upstream end and a sediment trap at the downstream end. The profile data indicate a slope of approximately 6 percent; the relatively straight alignment would be expected for a slope in this range. The slope over the downstream 200 LF is noticeably flatter than the upstream 500 LF, apparently in response to the effects of the sediment trap, which is currently a 3 -foot tall riprap check dam. (In late January 2019, Headwaters Engineering completed a laser level reference reach survey of UTI downstream of the sediment trap in order to support a design to remove the trap and create a stable transition to a bedrock slide immediately downstream of the trap.) Cross section surveys through the daylighted reach of UTI indicate a relatively narrow and deep channel, with width -depth ratios of 10 or less. Bank heights range from 2.4 to 3.2 feet and top widths range from 11 to 20 feet. Cross section plots with dimension parameters are attached. As shown on the attached photos, the bed and banks contain abundant riprap, generally ranging in median size from 8 inches to more than 24 inches. The UT2 survey indicates a drop of 1.8 feet from the invert of the north culvert to the thalweg and a relatively flat slope of 1.8 percent from this point downstream. The cross-section survey shows a relatively large channel with 3.4:1 side slopes and a maximum depth of 3.7 feet. UT 1 Stabili . Analysis We used the USGS web -based hydrology tool StreamStats to estimate the drainage area above the subject reach of UTI and found it to be 22 acres. A digitized watershed boundary using the Jackson County contours indicated a slightly smaller drainage area. Land use in the watershed includes forest, the golf course and low density residential. The North Carolina Mountain regional curve predicts a bankfull discharge of about 8 cubic feet per second (cfs) for a 22 -acre watershed. Previous experience indicates that regional curve predictions at the extreme low end of the drainage area range such as this are not as reliable as those in the middle of the range (between 2 and 30 square miles). Analysis of the surveyed riffle cross sections indicates the discharge corresponding to the low bank stage is on the order of 140 to 200 cfs. The reference cross section survey by Headwaters in the relatively undisturbed reference reach indicates a bankfull discharge of about 60 cfs. Based primarily on a comparison to the reference reach cross section, it appears that the daylighted channel was constructed deeper and wider than would have been designed based on a natural channel design approach. Analyses of the as -built cross sections indicate shear stresses in the riffles on the order of 5 to 6 pounds per square foot (psf). With reference to Shield's equation, the predicted grain size for threshold of motion ranges from 240 to 300 mm, or 9 to 12 inches. Analysis of the reference cross section flowing full at a discharge of about 150 cfs indicates a shear stress and threshold grain size similar to those of the constructed channel (4.8 psf and 230 mm, respectively). We are aware of the daylighted channel being subjected to multiple flood events since it was constructed and there does not appear to be bank erosion or bed scour. In our experience, constructed streams are typically weakest immediately after construction and become more resilient with time. The large stone in the channel and on the banks does not appear to have been mobilized during any of these recent storms, and calculations indicate that even when flowing full (well above the predicted "bankfull" discharge), the majority of the bed and bank materials would not be mobilized. The proposed boulder steps at the downstream end of UTI will provide additional grade control. A visual monitoring program over the next two to three years will likely provide the data necessary to evaluate long term stream stability. UT2 Perched Conditions The concern expressed for UT2 is the high drop from the culverts to the receiving channel. The proposed boulder step downstream of the headwall will reduce the drop height to about 9 inches, and the proposed pool between the step and the headwall will help dissipate energy and promote better aquatic organism habitat. As with UTI, the UT2 channel has been subjected to multiple large floods and we have not observed stability issues even without the energy dissipation effects of the proposed pool and step. A visual monitoring program seems appropriate for UT2 as well. Closure Based on our review of the data and our calculations, we do not recommend any repairs or modifications to UTI at this time beyond the sediment trap removal and boulder steps at the downstream end. For UT2, the proposed boulder step and pool should address energy dissipation and aquatic organism passage concerns. If you have any questions. please call me at 828.606.0306. Attachments: Stream Enhancement Plans Cross Section Plots and Shear Stress Calculations Photos Zvi �� r ai 1'•' STREAM ENHANCEMENTS TRIBUTARIES TO FOWLER CREEK HIGH HAMPTON RESORT CASHIERS, NORTH CAROLINA SHEET INDEX 1. TITLE 2. UT1 AS -BUILT PLAN & PROFILE (DAYLIGHTED REACH) 3. UT1 ENHANCEMENT PLAN & PROFILE 4. UT2 ENHANCEMENT PLAN & PROFILE (PERCHED CULVERTS) 5. DETAILS VICINITY MAP NOT TO SCALE M �v PROJECT SITE n Q w Q cn o z 0 o cn a> a_W U W 0 U)a M,o Wc �o°OoU Q E z o z W U 0 WZ O J > cn W Y Q) LLJJ LU rn Q U Z U) zW � W WLR wUW ry z U � Z W ZU) J �Ow zOa= ui Q O -<r U UJ -r CD U>>= DATE: MARCH 2019 SCALE: AS SHOWN TITLE SHEET 1 OF 5 uw) 9)0 ; "'rP� .... , ` 0 U)a M,o Wc �o°OoU Q E z o z W U 0 WZ O J > cn W Y Q) LLJJ LU rn Q U Z U) zW � W WLR wUW ry z U � Z W ZU) J �Ow zOa= ui Q O -<r U UJ -r CD U>>= DATE: MARCH 2019 SCALE: AS SHOWN TITLE SHEET 1 OF 5 t XS3 — 8.0'-1 1.0' - - L 3.0' RIFFLE 10.5' 1.5' 3.0' IaeTelI 1 TYPICAL SECTIONS 1 1" = 10' CONSTRUCTION NOTES: 1. WORK SHALL BE STAGED SUCH THAT NO MORE CREEK BANK/BED IS DISTURBED THAN CAN BE STABILIZED AT THE END OF THAT WORK DAY. 2. A PUMP -AROUND SHALL BE USED TO DIVERT FLOW AROUND THE WORK AREAS ON UT1 AND UT2. SEE DETAIL. 3. FINE SEDIMENT ACCUMULATED BEHIND THE ROCK CHECK DAM ON UT1 SHALL BE REMOVED AND DISPOSED OFF-SITE BEFORE REMOVING THE CHECK DAM. 4. STREAM BANKS SHALL BE STABILIZED WITH SEED, MULCH AND MATTING WITHIN 24 HOURS OF REACHING FINAL GRADES. 5. LOCATIONS AND ELEVATIONS OF BOULDER STEPS MAY BE ADJUSTED DURING CONSTRUCTION PER THE DIRECTION OF THE ENGINEER BASED ON FIELD CONDITIONS. 100 P .1 :m n n Q Lj Q cn o z 0 0 a j a_ w U w U) W n - • i U d o o _mo Lu CNJ �j2nniiw `O�: H zz E Q Z 60 9 - • i U d o o _mo Lu � ONO U H zz E Q Z 60 9 w � U 0 LU O J Z W (� > (n YLJ LLJ PLAN = w rn Q co z 100 ROP. BOULDER STEPS; RIFFLE TYPICAL ROCK CHECK DAM 91 i POOL TYPICAL — 81 6+00 6+30 6+60 6+90 7+20 PROFILE BEDROCK SLIDE SCALES: H:1"=30' V: 1" = 10' ELEVATIONS BASED ON ARBITRARY DATUM OF 100.0' w� w p Q U w U Z wwZvj 2i3:Pw a— UJC/)i) O = U 2 LD DATE: DATE: MARCH 2019 SCALE: AS SHOWN UT1 ENHANCEMENTS PLAN & PROFILE SHEET 3 OF 5 100 UT2 PROFILE DOWNSTREAM OF NORTH CULVERT SET TOP OF BOULDER STEP 9" -BELOW INVERT OF 0+30 0+60 0+90 1+20 1+50 100 J 90 1+80 SCALES: H: 1" = 40' V..1"=10' ELEVATIONS BASED ON ARBITRARY DATUM OF 100.0' rc n Q w a C/) o z _O o cn � w th ry U N W 0 0 Lo U) co 0 W(� 0000 U Q E Z U Z Z Lu j U_ 0 Z 2 = J J Lu Z YL LLI w Q U Z Z W W' W W of U) w U W z Ury ry Z W Z U) J Z0�w W � Q 2 Q w 0 = U LD U) _ DATE: MARCH 2019 SCALE: AS SHOWN UT2 ENHANCEMENT PLAN & PROFILE SHEET 4 OF 5 TOP OF BANK 1' MIN. REMOVE ALL DEBRIS, SCARIFY SURFACE, PLACE TOPSOILAND SEED/MULCH BEFORE PLACING MATTING MATTING PLACED FLUSH WITH BANK SURFACE, LAP OVER DOWN STREAM / DOWN SLOPE SEAMS 12" WOOD STAKE PLACED IN 3' O.C. DIAMOND PATTERN NON -WOVEN SILT BAG 110101N. FROM STREAM CLASS B STONE PAD OR PALLET SILT BAG MATTING ANCHORED 1' BELOW STREAM BED COFFER DAM; CLASS B STONE OR IT, ON-SITE COBBLE W/ PLASTIC SHEETING NOTES: 1. MATTING SHALL BE 780 G/Mz COIR. EROSION CONTROL MATTING 2. SEED BANKS WITH RYE GRAIN AND rl NATIVE RIPARIAN MIX, AND COVER 5 NTS WITH WHEAT OR OAT STRAW MULCH BEFORE INSTALLING MATTING. V DEEP SETTLING POOL FLOW II ANCHOR NON -WOVEN FILTER TOE OF BANK (TYP) FABRIC ON UPSTREAM SIDE OF DIVERSION PUMP TOP OF BANK (TYP) 17 I I BOULDERS AND BACKFILL WITH SIZED FOR 150% OF ON-SITE COBBLE AND GRAVEL BASE FLOW VARIES; D/S DAM MAY NOT BE NEEDED RIFFLE TYPICAL SECTION 6' +/ ANCHOR 4' INTO BANK ELEV. AT TIE -IN-1— HEADER APPROX. 1' HIGHER I FOOTER THAN INVERT ELEV. /--\\ FLOW � POOL TYPICAL SECTION Fffui"k NOTES: 1. BOULDERS SHALL BE DURABLE STONE, MIN. 2'X3'X3' AND RELATIVELY FLAT. 2 BOULDER STEP 2. DIMENSIONS AND NUMBER OF BOULDERS MAY BE ADJUSTED BASED ON 5 NTS FIELD CONDITIONS. 10" HDPE SHEETING WITH 6" OF ON-SITE COBBLE OVERLAY; USE SAND BAGS AT BASE AS NECESSARY DEWATERING PUMP SILT BAG ON PALLET OR AS NEEDED STONE, SEE DETAIL ABOVE r WORK AREA TOE OF BANK (TYP) T(1P nF RANK (TYM I I 3' PROFILE PROTECT EXIST. BANK VEGETATION FOR ADD'L FILTER n n Q Lij cn o z 0 0 a a_ W U U) w 0 -17 (D U) a �o u') 0 co Lu ONO ;� Q z=>_ =co =a= CNJ cS ; N, 101 _'x: � m =Z SPLASH PAD -17 (D U) a �o u') 0 co Lu ONO Q E z Z z W U 0 Lu O J z )N -SITE COBBLE _'x: � m =Z SPLASH PAD rn Q U z *NOTE: WORK AREA SHALL BE STABILIZED BY THE END OF EACH WORK DAY. TOP OF BANK BANK TO BANK MAX DEPTH STREAM BOTTOM + COFFER DAM 3 PUMP -AROUND SCHEMATIC '\�5j NTS SECTION Z W �rvl W W Q� U) W U W Z U orf Q J O � _ H W z O a = W _j Q U) Q O = U Wim= � � U U) 2 DATE: MARCH 2019 SCALE: AS SHOWN DETAILS SHEET 5 OF 5 High Hampton Resort Cross Section Plots and Shear Stress Calculations 88 87 86 0 85 c� w 84 83 82 0 5 Bankfull Dimensions 20.2 x -section area (ft.sq.) 11.2 width (ft) 1.8 mean depth (ft) 2.4 max depth (ft) 13.1 wetted parimeter (ft) 1.5 hyd radi (ft) 6.2 width -depth ratio Bankfull Flow 10 15 UT to Fowler Creek, riffle Width (ft) Flood Dimensions 20 25 30 35 Materials 28.7 W flood prone area (ft) 2.6 entrenchment ratio 2.4 low bank height (ft) 1.0 low bank height ratio Flow Resistance --- D50 (mm) --- D84 (mm) 292 threshold grain size (mm): Forces & Power 9.9 velocity (ft/s) 0.050 Manning's roughness 6.2 channel slope (%) 199.5 discharge rate (cfs) 0.25 D'Arcy-Weisbach fric. 5.94 shear stress (Ib/sq.ft.) 1.40 Froude number --- resistance factor u/u* 1.75 shear velocity (ft/s) --- relative roughness 69 unit strm power (Ib/ft/s) 91 90 89 C: 0 88 c� w 87 86 85 0 5 10 Bankfull Dimensions 16.4 x -section area (ft.sq.) 11.1 width (ft) 1.5 mean depth (ft) 2.4 max depth (ft) 13.0 wetted parimeter (ft) 1.3 hyd radi (ft) 7.6 width -depth ratio Bankfull Flow UT to Fowler Creek, riffle 15 20 25 30 35 40 45 Width (ft) Flood Dimensions Materials --- W flood prone area (ft) --- D50 (mm) --- entrenchment ratio --- D84 (mm) 2.4 low bank height (ft) 240 threshold grain size (mm): 1.0 low bank height ratio Flow Resistance Forces & Power 8.7 velocity (ft/s) 0.050 Manning's roughness 6.2 channel slope (%) 141.7 discharge rate (cfs) 0.27 D'Arcy-Weisbach fric. 4.88 shear stress (Ib/sq.ft.) 1.36 Froude number --- resistance factor u/u* 1.59 shear velocity (ft/s) --- relative roughness 49 unit strm power (Ib/ft/s) Cross Section UT1, XS3 0 5 10 15 20 25 r111G[iKfDl Bankfull Dimensions Flood Dimensions 39.9 x -section area (ft.sq.) --- W flood prone area (ft) 19.6 width (ft) --- entrenchment ratio 2.0 mean depth (ft) --- low bank height (ft) 3.2 max depth (ft) --- low bank height ratio 21.8 wetted parimeter (ft) 1.8 hyd radi (ft) 9.7 width -depth ratio Bankfull Flow 11.1 velocity (ft/s) 441.9 discharge rate (cfs) 1.45 Froude number Flow Resistance 0.050 Manning's roughness 0.24 D'Arcy-Weisbach fric --- resistance factor u/u* --- relative roughness 30 35 40 45 Materials --- D50 (mm) --- D84 (mm) 347 threshold grain size (mm): Forces & Power 6.2 channel slope (%) 7.06 shear stress (Ib/sq.ft.) 1.91 shear velocity (ft/s) 87 unit strm power (Ib/ft/s) 0 5 10 15 20 25 r111G[iKfDl Bankfull Dimensions Flood Dimensions 39.9 x -section area (ft.sq.) --- W flood prone area (ft) 19.6 width (ft) --- entrenchment ratio 2.0 mean depth (ft) --- low bank height (ft) 3.2 max depth (ft) --- low bank height ratio 21.8 wetted parimeter (ft) 1.8 hyd radi (ft) 9.7 width -depth ratio Bankfull Flow 11.1 velocity (ft/s) 441.9 discharge rate (cfs) 1.45 Froude number Flow Resistance 0.050 Manning's roughness 0.24 D'Arcy-Weisbach fric --- resistance factor u/u* --- relative roughness 30 35 40 45 Materials --- D50 (mm) --- D84 (mm) 347 threshold grain size (mm): Forces & Power 6.2 channel slope (%) 7.06 shear stress (Ib/sq.ft.) 1.91 shear velocity (ft/s) 87 unit strm power (Ib/ft/s) Cross Section UT1, XS4 UT to Fowler Creek, run 122 121 120 F 119 c 0 118 .6 a> 117 w 116 115 114 0 5 10 15 20 25 30 35 4 Width (ft) Bankfull Dimensions Flood Dimensions Materials 25.9 x -section area (ft.sq.) --- W flood prone area (ft) --- D50 (mm) 14.5 width (ft) --- entrenchment ratio --- D84 (mm) 1.8 mean depth (ft) --- low bank height (ft) 269 threshold grain size (mm): 2.4 max depth (ft) --- low bank height ratio 18.3 wetted parimeter (ft) 1.4 hyd radi (ft) 8.1 width -depth ratio Bankfull Flow Flow Resistance Forces & Power 9.3 velocity (ft/s) 0.050 Manning's roughness 6.2 channel slope (%) 241.9 discharge rate (cfs) 0.26 D'Arcy-Weisbach fric. 5.47 shear stress (Ib/sq.ft.) 1.39 Froude number --- resistance factor u/u* 1.68 shear velocity (ft/s) --- relative roughness 65 unit strm power (Ib/ft/s) UT to Fowler Creek, riffle 102 x -section area (ft.sq.) 101 width (ft) 100 mean depth (ft) 99 max depth (ft) c 98 0 wetted parimeter (ft) 1.8 97 m 15.4 w 96 95 Bankfull 94 93 0 Bankfull Dimensions 10 54.2 x -section area (ft.sq.) 28.8 width (ft) 1.9 mean depth (ft) 3.7 max depth (ft) 29.8 wetted parimeter (ft) 1.8 hyd radi (ft) 15.4 width -depth ratio Bankfull Flow 7.4 velocity (ft/s) 402.5 discharge rate (cfs) 0.97 Froude number 20 30 Width (ft) Flood Dimensions --- W flood prone area (ft) --- entrenchment ratio --- low bank height (ft) --- low bank height ratio Flow Resistance 0.040 Manning's roughness 0.15 D'Arcy-Weisbach fric. --- resistance factor u/u* --- relative roughness 40 50 Materials --- D50 (mm) --- D84 (mm) 100 threshold grain size (mm): Forces & Power 1.8 channel slope (%) 2.04 shear stress (Ib/sq.ft.) 1.03 shear velocity (ft/s) 15.7 unit strm power (Ib/ft/s) 0 96.5 96 95.5 95 0 94.5 0 94 w 93.5 93 92.5 92 91.5 0 E Bankfull Dimensions 14.5 x -section area (ft.sq.) 10.2 width (ft) 1.4 mean depth (ft) 2.1 max depth (ft) 11.7 wetted parimeter (ft) 1.2 hyd radi (ft) 7.2 width -depth ratio Bankfull Flow 10.7 velocity (ft/s) 154.0 discharge rate (cfs) 1.69 Froude number UT to Fowler Creek, Riffle 4 6 8 10 Width Flood Dimensions Materials 49.5 W flood prone area (ft) 4.8 entrenchment ratio 2.1 low bank height (ft) 1.0 low bank height ratio Flow Resistance 0.040 Manning's roughness 0.17 D'Arcy-Weisbach fric. --- resistance factor u/u* --- relative roughness 12 14 --- D50 (mm) --- D84 (mm) 234 threshold grain size (mm): Forces & Power 6.2 channel slope (%) 4.77 shear stress (Ib/sq.ft.) 1.57 shear velocity (ft/s) 58 unit strm power (Ib/ft/s) High Hampton Daylighted Stream (UT1) Cross Sections, 2/25/2019 XS2- Facing Upstream XS1- Facing Downstream XS2- Facing Downstream High Hampton Daylighted Stream Cross Sections, 2/25/2019 High Hampton Daylighted Stream Photo Points, 2/25/2019 PP2- Facing Upstream }Sl- PP:- Facing Downstream PP3- Facing Upstream PP3- Facing Downstream High Hampton Daylighted Stream Photo Points, 2/25/2019 1, mv� �i�l WIN-! 14 PP4- Facing Upstream z '4. PP4- Facing Tributary Upstream PP4- Facing Downstream PP5- Facing Upstream PP5- Facing Downstream High Hampton Perched Culverts (UT2) a •. �•.� �..�.,. w J -;.i,.. �,� � . j, i -.•.rte'— �✓,r�` j3.-. '` - y� ::itisv,�'- �y - x tit �,.yr �.;_�1� z •.;, - �•a^_ r Ir NW jv -; _