HomeMy WebLinkAboutRestoration Submittal Extension Request for Hinnant Property - Walnut Creek_20190226From: Bobby Billingsley
To: Scarbrauah, Anthony
Subject: [External] Hinnant Property Status - Walnut Creek
Date: Friday, February 22, 2019 7:47:51 AM
• External email. Do not click links o� attachments unless you verify. Send all suspicious email as al
to v
Anthony this is a follow up on our discussion yesterday regarding the way forward, from a permit
perspective, for the Dr. Keith Hlnnant site in the Village of Walnut Creek, Wayne County. There are
several "hoops" that the owner needs to go through to effectively be able to build and ultimately
reside on this property. Firstly, he is in the process of determining his house plan, which will give us
the footprint, elevations, wastewater estimation, etc. When that is more settled, we will need to
better evaluate the site from a wastewater perspective to determine how wastewater will be
handled, whether it be on or offsite. After that, several approvals and agreements will need to be
obtained from the Walnut Creek planning boards, including but not necessarily limited to permit to
fill the site, wastewater, drainage easement relocation, potentially pond drainage for rear site
improvements, architectural control, etc.
Dr. Hinnant would like to proceed with putting a bulkhead in along the rear and filling his site,
however, at this moment we don't know if this site is feasible or not. My suggestion would be to
hold off on permitting this site until we receive the house plan and can do better site planning and
layout, grading, and determine wastewater. After that we should be able to dually permit the buffer
restoration and approvals necessary through Walnut Creek. The revised buffer restoration submittal
will likely have a bulkhead option, with a timeline to install in the winter of 2019.
As we discussed though, as soon as the EC plan is approved, the owner does intend to clean the site
up and stabilize the area in the rear while these decisions are being made. Hopefully this approval
will be approved within the next couple of weeks.
With all of the above in mind, can we put a four month hold on the buffer restoration plan review
and subsequent approval? This would give us until July 1St ish to have a better plan in place on how
to proceed. If you have questions or concerns regarding the above, please advise.
Thanks,
Bobby Billingsley, PE
BobbyBillingsleyPThomasEngineeringPA.com
Thomas EngineeringPA.com
THOMAS est 198.3
ENGINEERING, PA
Phs. Address: 1316-B Commerce Drive
New Bern, NC 28562
Mail Address: PO Box 1309
New Bern, NC 28563
Office : 252.637.2727
Mobile: 252.671.2408
Fax: 252.636.2448
FCVirus-free. www.avg.com