HomeMy WebLinkAboutWQCSD0059_5DAY SSO Report_20190221 Form CS-SSO
Collection System Sanitary Sewer Overflow Reporting Form
State of North Carolina
Department of Environment and Natural Resources
Division of Water Resources
Manhole at Westall & Bragg Street, etc):
This form shall be submitted to the appropriate DWQ Regional Office within five days of the first knowledge of the sanitary sewer
overflow (SSO).
Permit Number:(WQCS# if active, otherwise use WQCSD#)
Facility:Incident #:
Owner:
Region:City:County:
Source of SSO (check applicable):Sanitary Sewer Pump Station / Lift Station
SPECIFIC location of the SSO (be consistent in description from past reports or documentation - i.e. Pump Station 6,
Manhole #:
Latitude (Decimal Degrees):Longitude (Decimal Degrees):
Incident Started Dt:Time:Incident End Dt:Time:
(mm-dd-yyyy)(hh:mm AM/PM)(mm-dd-yyyy)(hh:mm AM/PM)
Estimated Volume of the SSO:gallons Estimated Duration (Round to nearest hour):
Describe how the volume was determined:
Weather conditions during the SSO event:
Did SSO reach surface waters?Yes No Unknown Volume reaching surface waters (gals):
Surface water name:
Did the SSO result in a fish kill?Yes No Unknown If Yes, what is the estimated number of fish killed?
02/21/2019
City Of Saluda
City of Saluda
City of Saluda Collection System 201900394
AshevillePolk
Pearson Falls Rd., 100 yards from US 76
14,110 3:0
Partially Covered Manhole
Heavy Rain
0
14110
WQCSD0059
H5-01
þ ¨
þ ¨¨
þ¨¨
7:30 am 02/21/2019 10:30 am
Joels Creek
PART I:
SPECIFIC cause(s) of the SSO:
hours
þ Inflow and Infiltration þ Debris in line
24 hour verbal notification (name of person contacted ):
DWR Emergency Mgmt Date (mm-dd-yyy):02/21/2019þ 08:45:00 pm¨Time (hh:mm AM/PM):
Jerry Unkown
If an SSO is ongoing, please notify the appropriate Regional Office on a daily basis until SSO can be stopped.
Per G.S. 143-215.1C(b), the responsible party of a discharge of 1,000 or more of untreated wastewater to surface waters
shall issue a press release within 24-hours of first knowledge to all print and electronic news media providing general
coverage in the county where the discharge occurred. When 15,000 gallons or more of untreated wastewater enters surface
waters, a public notice shall be published within 10 days and proof of publication shall be provided to the Division within 30
days. Refer to the reference statute for further detail.
The Director, Division of Water Resources, may take enforcement action for SSOs that are required to be reported to
Division unless it is demonstrated that:
1) the discharge was cause by sever natural conditions and there were no feasible alternative to the discharge; or
2) the discharge was exceptional, unintentional, temporary and caused by factors beyond the reasonable control of the
Permittee and/or owner, and the discharge could not have been prevented by the exercise of reasonable control.
Part II must be completed to provide a justification claim for either of the above situations. This information will be the basis
WHETHER OR NOT PART III IS COMPLETED, A SIGNATURE IS REQUIRED AT THE END OF THIS FORM
CS-SSO Form Page:1
PART II:
ANSWER THE FOLLOWING QUESTIONS FOR EACH RELATED CAUSE CHECKED IN PART I OF THIS FORM AND
INCLUDE THE APPROPRIATE DOCUMENTATION AS REQUIRED OR DESIRED
COMPLETE ONLY THOSE SECTONS PERTAINING TO THE CAUSE OF THE SSO AS CHECKED IN PART I
(In the check boxes below, NA = Not Applicable and NE = Not Evaluated)
A HARDCOPY OF THIS FORM SHOULD BE SUBMITTED TO THE APPROPRIATE DWR REGIONAL OFFICE UNLESS IS
Inflow and Infiltration
Are you under an SOC (Special Order by Consent) or do you have a schedule in any
permit that addresses I/I?
NENANoYes¨þ ¨¨
Explain if Yes:
What corrective actions have been taken to reduce or eliminate I & I related overflows
at this spill location within the last year?
The City has worked to eliminate I&I at this location by repairing the upstream manholes, eliminating a break in the line
under the railroad tracks. The city has worked to eliminate storm water infiltration into one of the lift stations which feed into
the lines which feed the manhole.
Has there been any flow studies to determine I/I problems in the collection system at
the SSO location?
NENANoYes¨þ ¨¨
If Yes, when was the study completed and what actions did it recommend?
Has the line been smoke tested or videoed within the past year?NENANoYesþ¨¨¨
If Yes, when and indicate what actions are necessary and the status of such actions:
The line was videotaped during the last SSO. It was determined that a break underneath US 176 is permitting both I&I and
debris to enter the line. NCDOT has been contacted to discuss the storm drainage under the road which is causing the
problem. The City has hired an engineer to prepare an opinion of cost to repair and replace the line upstream which has a
known break.
Are there I/I related projects in your Capital Improvement Plan?NENANoYesþ¨¨¨
If Yes, explain:
The capital improvement plan has numerous projects which will help with I& I, but the current construction of the current
capital improvement plan is not going to address the I&I which impacts this SSO.
Have there been any grant or loan applications for I/I reduction projects?NENANoYesþ¨¨¨
If Yes, explain:
The City has a 2 million dollar loan which will replace a variety of sewer lines however those lines will likely have little impact
on this particular manhole.
Do you suspect any major sources of inflow or cross connections with storm sewers?NENANoYesþ¨¨¨
CS-SSO Form Page:2
If Yes, explain:
I suspect the line is receiving many source points of inflow along two specific trunk lines. on trunk line has 6" terra cota and
when the camera pushed through the line Inflow was found at each joint even during a dry period. The other trunk line
parallels a creek and the creek channel is collapsing. I anticipate the existing terra cota line is potentially compromised by
this collapse. The City will be inspecting this line within the next month. The line was inspected with a camera about one
year ago.
Have all lines contacting surface waters in the SSO location and upstream been
inspected recently?
NENANoYesþ¨¨¨
If Yes, explain:
The lines upstream are inspected regularly because they are the main trunk lines of the city. These same lines are also
cleaned and jettered regularly.
What other corrective actions are planned to prevent future I/I related SSOs at this
location?
The city will continue to smoke test and camera lines upstream of this manhole. Every opportunity to repair and find a break
will be taken.
Comments:
Debris in line
What type of debris has been found in the line?
Road base and terra cota chunks.
Suspected cause or source of debris.
The line was videotaped after the last SSO. It was determined that a break underneath US 176 is permitting both I&I and
debris to enter the line. NCDOT has been contacted to discuss the storm drainage under the road which is causing the
problem. The City has hired an engineer to prepare an opinion of cost to repair and replace the line upstream which has a
known break. Once this information is known, the city will pursue corrective action cooperating with NCDOT and as
resources permit.
Are manholes in the area secure and intact?NENANoYesþ¨¨¨
When was the area last checked/cleaned?
3 months ago
Have cleaning and inspections ever been increased at this location due to previous
problems with debris?
NENANoYesþ¨¨¨
Explain:
This is the main trunk line of the city. It is checked regularly for grease, debris and other material. It is cleaned with a jetter
at least twice a year sometimes more often.
Are appropriate educational materials being developed and distributed to prevent future
similar occurrences?
NENANoYes¨¨þ ¨
Comments:
This SSO is a result of debris and Inflow so educating the public will likely have no impact on reducing the likelihood of this
type of SSO.
System Visitation
ORC Yes¨
CS-SSO Form Page:3
Backup Yes¨
Name:
Cert#
Date visited:
Time visited:
How was the SSO remediated (i.e. Stopped and cleaned up)?
Debris was removed and cleared from the manhole and lines. The manhole began to function properly.
As a representative for the responsible party, I certify that the information contained in this report is true and accurate to the
best of my knowledge.
Person submitting claim:Date:02/21/19 08:45 pm
Signature:Title:Administrator Zoning
Telephone Number:
Any addition information desired to be submitted should be sent to the appropriate Division Regional Office within five days of first
knowledge of the SSO with reference to the incident number (the incident number is only generated when electronic entry of this
form is completed, if used).
Jonathan Cannon
CS-SSO Form Page:4