HomeMy WebLinkAboutNC0043532_NOV-2019-PC-0069 Response_20190220L
STANLY COUNTY
February 20, 2018
Corey Basinger, Regional Supervisor
NCDEQ Mooresville Regional Office
610 East Center Drive Suite 301
Mooresville, NC 28115
Re: Plan of Action NOC-2019-PC-0069
Dear Mr Basinger:
RECEIVED/NCO E N R/DWI$
FEB 2 5 2019
WORDS
MOORESVILLE REGIONAL OFFICE
We appreciated the opportunity to speak with you concerning the non -compliant issues related to
the recent inspection of the West Stanly WWTP.
Pursuant to that conversation, Stanly County will proceed with the following plan of action to
address the noted violation items noted from the inspection:
01
Q
Potassium Permanganate chemical feed that was installed at the McCoy PS has been
dismantled and removed. It was determined that the chemical injection needed to be
further upstream in order to have any effect on odor control. All chemicals have been
disposed of and equipment removed.
Chlorine contact chamber was noted to have floating debris and grease build up on walls.
The contact chamber was cleaned and all floating solids removed 2/6/2019.
The Secondary Clarifier has not been working for some time from what I being told.
Our plans are to proceed to construction with a new larger clarifier and permanently
remove this the two non -working clarifiers.
Head -works mechanical bar -screen at McCoy PS has been repaired and put back online
on 2/13/2019 and is operating normally.
Utilities Department 1000 N. First Street, Suite 12, Albemarle, NC28001
P/704,986,3686 www.stan& ountvncaov F/704,986.3711
L
STANLY COUNTY
wtew. 'A.. 64W suComs.
5. Stanly County Operational Staff has been deployed with vacuum trailer to remove grease
build up and clean out the influent channels. An electrician has been contacted to get a
fan switch installed at the top of the stairs to remove any danger of Hydrogen Sulfide gas
at head -works pump station. Shrubbery along the head -works fence line has been cut
back as requested by NCDEQ inspector. Additional warning signage has been put up at
the pump station. Additional warning and hazard signs will be installed on all sides of
the fence along with emergency contact phone numbers. This will be done at the W WTP
also.
6 Cleanup and Maintenance at W WTP is underway to remove any vector attraction. A
loader provided by the Collection maintenance dept. will be used to remove all full trash
cans and any solids that are lying one the ground.
It is our intent to update you as all remaining item are getting completed.
If you have any additional questions or concerns, please call me or email at the number or email
address listed below.
Respectfully,
Duane Wingo, PE
Stanly County Utilities Director
1000 N. First Street Suite 12 Albemarle, NC 28001
Phone: (704) 986-3691
Cell: (704) 221-4291
dwineo(iWanlvcountvnc.eov
Cc: Andy Lucas, County Manager
File: S:AUtilites\631 West Stanly WW'fP\Violations\February 11 2019 Violation Response
Utilities Department 1000 N. First Street, Suite 12, Albemarle, NC 28001
P1704.986.3686 www.stanbTgun4mr_goy F1704.986.3711