Loading...
HomeMy WebLinkAbout20190114 Ver 1_USACE Correspondence_20190214Strickland, Bev From: Williams, Andrew E CIV USARMY CESAW (US) <Andrew.E.Williams2@usace.army.mil> Sent: Thursday, February 14, 2019 12:58 PM To: Michael Brame Cc: David Brame; Homewood, Sue; Heather LaGamba Subject: [External] RE: Tanager Holdings Solar Site, Asheboro, Randolph County, NC - Stream Crossing PCN CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov<maiIto: report.spam@nc.gov> Michael, That is correct. Only the regional conditions that apply to all NWPs and NWP 14 will be applicable. Andrew Williams Regulatory Project Manager US Army Corps of Engineers Wilmington District, Raleigh Regulatory Field Office 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 919-554-4884 ext. 26 -----Original Message ----- From: Michael Brame [mailto:mbrame@pilotenviro.com] Sent: Thursday, February 14, 2019 11:27 AM To: Williams, Andrew E CIV USARMY CESAW (US) <Andrew.E.Williams2@usace.army.miI> Cc: David Brame <dbrame@pilotenviro.com>; Homewood, Sue <sue.homewood@ncdenr.gov>; Heather LaGamba <h I aga m ba @ p i I ote nvi ro. co m> Subject: [Non-DoD Source] Re: Tanager Holdings Solar Site, Asheboro, Randolph County, NC - Stream Crossing PCN Thank -you Andy, Just to confirm, the Regional Conditions for NWP 51, including conditions 4.1.2 and 4.1.3 will not apply to the NWP 14 that you will process? Sent from my iPhone > On Feb 13, 2019, at 3:28 PM, Williams, Andrew E CIV USARMY CESAW (US) <Andrew.E.Williams2@usace.army.miI> wrote: > All: > I have reviewed the Pre -construction Notification (PCN) for this project. We do not require any additional information for the application to be considered complete. However, please reference Note 2 on the Nationwide Permit (NWP) 51 (Land -Based Renewable Energy Generation Facilities) description. 1 > It states, If the only activities associated with the construction, expansion, or modification of a land-based renewable energy generation facility that require Department of the Army authorization are discharges of dredged or fill material into waters of the United States to construct, maintain, repair, and/or remove utility lines and/or road crossings, then NWP 12 and/or NWP 14 shall be used if those activities meet the terms and conditions of NWPs 12 and 14, including any applicable regional conditions and any case -specific conditions imposed by the district engineer. > Since the only impacts for this project are for a single road or transportation crossing, I plan to verify this under NWP 14. > Please let me know if you have any questions or concerns. Thanks. > Andrew Williams > Regulatory Project Manager > US Army Corps of Engineers > Wilmington District, Raleigh Regulatory Field Office > 3331 Heritage Trade Drive, Suite 105 > Wake Forest, North Carolina 27587 > 919-554-4884 ext. 26 > -----Original Message----- > From: David Brame [mailto:dbrame@pilotenviro.com] > Sent: Wednesday, January 16, 2019 2:27 PM > To: Homewood, Sue <sue.homewood@ncdenr.gov>; Williams, Andrew E CIV USARMY CESAW (US) <Andrew.E.Williams2@usace.army.mil> > Cc: Michael Brame <mbrame@pilotenviro.com>; Heather LaGamba <hlagamba@pilotenviro.com> > Subject: [Non-DoD Source] Tanager Holdings Solar Site, Asheboro, Randolph County, NC - Stream Crossing PCN > Andy/Sue, > PCN request will be mailed today. Electronic copy attached. > Let me know if you have any questions. > Sincerely, > David Brame, PWS > 336.708.4617 (c) > 336.310.4527 (o) > Blockedwww.pilotenviro.com <BlockedBlockedhttp://www.pilotenviro.com/> > dbrame@pilotenviro.com <mailto:dbrame@pilotenviro.com> Fil